Y -- Camp Speicher Power Plant and Electrical Distribution Camp Speicher, Iraq

Notice Date
1/30/2004
 
Notice Type
Solicitation Notice
 
Contracting Office
Corps of Engineers, Europe District, Contracting Division, CMR 410 BOX 7, APO, AE 09096
 
ZIP Code
09096
 
Solicitation Number
W912GB-04-R-0028
 
Response Due
2/9/2004
 
Archive Date
4/9/2004
 
Point of Contact
Ted Kunzog, 011496118162615
 
E-Mail Address
Email your questions to Corps of Engineers, Europe District, Contracting Division
(Ted.Kunzog@us.army.mil)
 
Small Business Set-Aside
N/A
 
Description
Camp Speicher Power Plant and Electrical Distribution DESCRIPTION OF WORK - SPECIFIC The Work described in this section shall include, but not be limited to, the following: Contractor Scope of Work Power Plant: This shall include the procurement, installation, testing, commissioning, and startup of the Power Plant in accordance with the contract documents. The Power Plant shall include a 7-day supply of fuel storage and necessary manifolds and piping from the tanks to the generators. Fuel storage tank shall be steel construction. Seven-day fuel supply shall be calculated as fuel consumption of all generators running at 70 percent capacity 24 hours per day for 7 days. The Contractor shall provide concrete pads for fuel tanks, generator, and switchgear. Medium-Voltage Switchgear: This shall include the installation, testing, commissioning, and energizing of the Main Switchgear and Power Distribution Centers (PDCs), and as specified in the contract documents. Medium-Voltage Distribution: This shall include the procurement, installation, testing, commissioning, and energizing the high voltage distribution system in accordance with the scope of work. High voltage cables are both aerial and below grade. This includes all underground cables f rom the Power Plant to the Primary Side of the new Main Switchgear, and from the Secondary Side of the new Main Switchgear to the pole risers of the Overhead Circuits. Provide new transformer stations as indicated in the contract drawings. Provide under ground riser cabling to the new transformer stations. Secondary cabling from the transformer stations shall be furnished and installed by another contract. Low Voltage Distribution: This includes the procurement, installation, testing, commissioning and energizing the Low Voltage Distribution System in accordance with the Scope of Work. This includes control voltage for the generator panels, power distribution centers for each generator with control voltage transformers, and secondary voltage for utility lighting, power, and controls in the control building. Exterior c abling shall be both below grade and above grade. The Contractor shall trench for below grade cables. For above grade cables, the contactor shall install cables in conduits. Grounding System: This shall include the procurement, installation, testing, and commissioning the Grounding (Earthing) System as stated in these documents. Earth resistance of 25 ohms or less shall be achieved. Pre-Fabricated Control Building: This shall include the procurement and installation of a pre-fabricated power control building as further described in the specifications.
 
Place of Performance
Address: Corps of Engineers, Europe District, Contracting Division CMR 410 BOX 7, APO AE
Zip Code: 09096
Country: DE
 
Record
SN00513201-W 20040201/040130212511 (fbodaily.com)
 
Source
FedBizOpps.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.