SOLICITATION NOTICE
Z -- Load Cell System
- Notice Date
- 3/30/2005
- Notice Type
- Solicitation Notice
- Contracting Office
- Bureau of Reclamation - Central California Area Office (CCAO) 7794 Folsom Dam Road Folsom CA 95630
- ZIP Code
- 95630
- Solicitation Number
- 05SQ240796
- Response Due
- 4/13/2005
- Archive Date
- 3/30/2006
- Small Business Set-Aside
- Total Small Business
- Description
- The Bureau of Reclamation, Folsom Power Plant has a requirement for the replacement and calibration of the load cell system and calibration of th load limit switch on the Folsom Power Plant draft tube bulkhead gate 10-ton trolley hoist. The existing load cell system shall be replaced with a remote reading (at or near the hoist control pendant) load cell system that is compatible with the other system equipment. The system shall be able operate to 12.5 tons, have plus or minus 1 percent of full load accuracy and have readout to 0.010 ton or 100 pounds, and operate in temperatures to 140 degrees F. The load sensing equipment shall be tested at 25%, 50%, 75%, and 100% of capacity, calibrated, and adjusted to be within the manufacturer's published accuracy tolerances. The hoist shall be overload tested (not to exceed 125%) for load certification due to the replacement of the load cell. If the system does not meet the accuracy tolerance requirements it shall be repaired or replaced and retested until the accuracy requirements are met. The Contractor shall provide and install an LED type indicator light, that is visible from the draft tube gate operating deck below the hoist in bright sunlight, to show that the overload protector has been activated. The overload protector shall be tested to verify it stops the hoist at the 10-ton overload capacity. 1. Contractor shall submit descriptive information on all new equipment to be provided for approval before installation. 2.Contractor shall submit the plan for transferring the test weights to the draft tube gate operating deck. Contractor shall submit the crane configuration, proposed setup location, and loading conditions, to meet the bridge limitations, for approval. 3. The Contractor shall provide a complete and operational load cell system and indicator for the overload protector system with the new components required. Contractor shall modify the drawings to show the system changes. 4. The Contractor shall perform all tests, adjustments, and calibration to verify that the system functions properly and without nuisance trips. The Contractor shall provide 5 copies of a test report with the test, adjustment, and calibration data obtained. 5. The Contractor shall provide 5 copies of installation and operation and maintenance manuals for the new equipment provided. This shall include a description of the operation of the system, trouble shooting guides, and exploded views showing the parts locations. Provide as-installed program settings of system parameters. Shall provide 2 copies and CD(s) of as-built electrical schematic and wiring diagram drawings in AutoCAD. NAICS 811310. The prospective offerors must be registered in the Central Contractor registration (CCR) (http://www.ccr.gov) prior to award. Offerors are advised that failure to register will render your firm ineligible for award. For complete statement of work contact Celia Choyce @ (916) 989-7223 or email at: cchoyce@mp.usbr.gov
- Web Link
-
Please click here to view more details.
(http://ideasec.nbc.gov/j2ee/announcementdetail.jsp?serverId=BR142520&objId=136725)
- Place of Performance
- Address: Folsom Power Plant 7794 Folsom Dam Road Folsom, CA
- Zip Code: 95630
- Country: us
- Zip Code: 95630
- Record
- SN00778794-W 20050401/050330212328 (fbodaily.com)
- Source
-
FedBizOpps.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |