FBO DAILY ISSUE OF SEPTEMBER 16, 2007 FBO #2120
MODIFICATION

41 -- AMENDMENT 0003 TO CBR FILTER UNITS

Notice Date
9/14/2007
 
Notice Type
Modification
 
NAICS
423730 — Warm Air Heating and Air-Conditioning Equipment and Supplies Merchant Wholesalers
 
Contracting Office
ACA, Aberdeen Proving Ground, Directorate of Contracting, 4118 Susquehanna Avenue, Aberdeen Proving Ground, MD 21005-3013
 
ZIP Code
21005-3013
 
Solicitation Number
W91ZLK-07-T-0800
 
Response Due
9/18/2007
 
Archive Date
11/17/2007
 
Point of Contact
bkuklinski, 410-278-0883
 
E-Mail Address
ACA, Aberdeen Proving Ground
(barbara.kuklinski@us.army.mil)
 
Small Business Set-Aside
N/A
 
Description
THIS AMENDMENT IS ISSUED TO PROVIDE ADDITIONAL QUESTIONS AND ANSWERS. THE CLOSING DATE AND TIME FOR QUOTATIONS REMAINS UNCHANGED. QUESTION 1. Question 17 revisited: ASME N510, Section 6, Duct and Housing Leak and Structural Capability Te sts provide the procedure for performing the duct/housing leak tests, not the acceptance criteria. ASME N509, Section 4.14.2 states that The system designer (Engineer) shall determine leakage criteria and allowable leakage to meet governing Codes, Standar ds, regulations, and plant-specific requirements. ASME AG-1, Article HA-4531 and SA-4531 state that the Owner or designee shall establish the allowable leakage to ensure ventilation, temperature, and contamination control functions are achieved. Please e stablish the allowable pressure boundary leak rate so we know we are providing what is required. ANSWER: 0.0005 CFM/cubic feet volume The maximum leakage rate in CFM = (0.002 x V) / 60 minutes. The rate is measured by pressurizing the housin g to 10 inches water gage and then monitoring the pressure and temperature after 5 minutes or more. QUESTION 2. With regard to the aspect ratio question: 2.1 Since the FIF is now rated for 2000 CFM, the 5000 CFM system will require six FIF 's (three in parallel x two in series. We need confirmation that APG wants the FIF's stacked one on top of the other so that the overall dimensions for one FIF section is 50 inches wide by 76 inches high by 24 inches deep. ANSWER: The Gove rnment is providing 8 FIF housings for the 5000 CFM system. Please integrate the 8 housings Four in parallel and Four in series. Allowed to stack two high two wide which requires access from both sides for filter change out. 2.2 Since the FIF is now rat ed for 2000 CFM, the 3000 CFM system will require four FIF's (two in parallel x two in series). We need confirmation that APG wants the FIF's stacked one on top of the other so that the overall dimensions for one FIF section is 50 inches wide by 48 inches high by 24 inches deep. ANSWER: The Government is providing 6 FIF housings for the 3000 CFM system. Please integrate the 6 FIF housings three in parallel and three in series. Allowed to stack three high with access from one side. The two FIF systems are for a special chamber where excess gas absorption capacity is desired. NOTE: THIS NOTICE WAS NOT POSTED TO FEDBIZOPPS ON THE DATE INDICATED IN THE NOTICE ITSELF (14-SEP-2007); HOWEVER, IT DID APPEAR IN THE FEDBIZOPPS FTP FEED ON THIS DATE. PLEASE CONTACT fbo.support@gsa.gov REGARDING THIS ISSUE.
 
Web Link
Link to FedBizOpps document.
(http://www.fbo.gov/spg/USA/DABJ/DABJ05/W91ZLK-07-T-0800/listing.html)
 
Place of Performance
Address: ACA, Aberdeen Proving Ground Directorate of Contracting, 4118 Susquehanna Avenue Aberdeen Proving Ground MD
Zip Code: 21005-3013
Country: US
 
Record
SN01408346-F 20070916/070915205539 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.