SOLICITATION NOTICE

Z -- Construct Interior Design Tasks

Notice Date
6/10/2008
 
Notice Type
Modification/Amendment
 
NAICS
236220 — Commercial and Institutional Building Construction
 
Contracting Office
Department of Veterans Affairs, Syracuse VAMC, Department of Veterans Affairs Medical Center, Contracting Officer (528A7-2/90 NCA);Department of Veterans Affairs Syracuse;800 Irving Ave;Syracuse NY 13210
 
ZIP Code
13210
 
Solicitation Number
VA-528-08-RP-0141
 
Response Due
6/19/2008
 
Archive Date
8/18/2008
 
Point of Contact
Michael ReedContracting Officer
 
Small Business Set-Aside
N/A
 
Description
Revised drawings and specs (complete new sets of each) were issued 6/9/08 and will be available at no cost in paper or CD form from Plan & Print Systems, 6295 East Malloy Road, East Syracuse, NY 13057, (315) 437-5111. They will also be available for review at Syracuse Builders Exchange, 6563 Ridings Road (315) 437-9936. The following is included in Amendment #1 to the Solicitation that is part of the revised specs. THE FOLLOWING IS APPLICABLE ONLY TO OFFERS FROM OTHER THAN SMALL BUSINESS: In accordance with FAR 52.219-9, a subcontracting plan is required to be approved prior to award of any contract resulting from this solicitation if that award is to be made to OTHER THAN small business. Any Offeror completing FAR 52.219-1 certifying that the Offeror is NOT a small business is required, as part of its offer, to submit a draft subcontracting plan. The completeness and acceptability of this plan will be used as part of this evaluation factor for any such Offeror. THIS PLAN SHOULD BE SUBMITTED AS AN ATTACHMENT TO THE COST PROPOSAL. The Department of Veterans Affairs Fiscal Year 2008 and 2009 Small Business Program Goals are: Small Business28.7% Service-Disabled Veteran-Owned Small Business 7% Veteran-Owned Small Business 10% Small Disadvantaged Business 5% Historically Underutilized Business (HUB) Zone Small Business 3% Women-Owned Small Business 5% The Minimum Acceptable Goals for Subcontracting Plans (IF REQUIRED) are: Small Business23% Service-Disabled Veteran-Owned Small Business 3% Veteran-Owned Small Business 7% Small Disadvantaged Business 5% Historically Underutilized Business (HUB) Zone Small Business 3% Women-Owned Small Business 5% http://www.va.gov/osdbu/dbwva/subcontracting.asp provides guidance on subcontracting plans. The following were in attendance at the June 4th Pre-Proposal Meeting: Chad OBrienStrock Contracting Steve BenedictThe Hayner Hoyt Corporation Gail IannuzziG.M. Crisalli & Associates Hunter GrimesDiverse Construction Group Jim HaganNorthland Associates Tom CollinsDEMCO Bill DonohueDEMCO John IvoryMAC Construction James JordanOmega QSE, Inc. Eric BurnhamPower Comm Electric Jeff ShermanSherman Construction The following Project Narratives were reviewed at the June 4th Pre-Proposal Meeting: Item 1 (Project 1): 528A7-08-702, Renovate Imaging for Angio & CT New Equipment A.Location: 3rd Floor West B.Size: Approximately 2,600 SF (Angio) + 350 SF (CT) C.Contractor Scope of Work for Angio: Removals, reconfigurations and reconstruction to provide a new Angio Suite. Work includes: 1.Removal of asbestos-containing floor tile and pipe insulation 2.Replacement of walls, cabinetry, doors, frames, hardware, floor finishes, wall finishes, and ceilings 3.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 4.Replacement of plumbing fixtures, piping, and valves 5.Replacement of sprinkler heads and piping 6.Replacement of electrical systems including lighting, power, smoke & fire detection, communications, and radiology electrical systems D.Contractor Scope of Work for CT: Removals and replacement of some of the radiology electrical system; minor ceilings modifications to accommodate new equipment E.Work by Others: 1.Removal of existing Angio & CT equipment 2.Installation of new Angio & CT equipment 3.Removal and reinstallation of existing loose furnishings F.Key Issues: Close coordination is required for all trades to accommodate new construction above ceiling and below floor of Angio & CT rooms Item 2 (Project 2): 528A7-08-709, Renovate 5 South for Outpatient PT A.Location: 5th Floor South B.Size: Approximately 6,900 SF C.Contractor Scope of Work: Removals, reconfiguration, and reconstruction to provide a PT Suite, including therapy rooms, toilet rooms, storage rooms, exam rooms, offices, nurse's station, waiting areas, etc. Work includes: 1.Removal of asbestos - containing floor tile and pipe insulation 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, and ceilings 3.New cabinetry and millwork 4.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 5.Replacement of plumbing fixtures, piping, and valves 6.Replacement of sprinkler heads, and piping 7.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Key Issues: The entire project area is over the existing operating rooms suite; operating room access is limited E.Work by Others: 1.Removal/reinstallation of loose furnishings and equipment Item 3 (Project 3): 528A7-08-704, Renovate for Low Vision A.Location: 2nd Floor South B.Size: Approximately 1,200 SF C.Contractor Scope of Work: Removals, reconfigurations, and reconstruction to provide a new low Vision Suite. Work includes: 1.Removal of asbestos-containing floor tile and pipe insulation 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, and ceilings 3.New cabinetry and millwork 4.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 5.Replacement of plumbing fixtures, piping, and valves 6.Replacement of sprinkler heads, and piping 7.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Work by Others: 1.Removal/reinstallation of loose furnishings and equipment E.Key Issues: Project includes reconstruction work in main corridor, but corridor access must be maintained Item 4 (Project 4): 528A7-08-705, Replace ICU Lav/Toilet Units A.Location: 6th Floor West B.Size: 13 Rooms (10 Private rooms, 3 Semi-Private rooms) C.Contractor Scope of Work in the 10 Private Rooms: replace existing lav/toilet units, including: 1.Replacement of some VCT 2.Removal/reinstallation of wall-mounted items 3.New ceramic wall tile 4.Replacement of lav/toilet units, including necessary plumbing modifications D.Contractor Scope of Work in Semi-Private Room B622: 1.Removal/reinstallation of wall-mounted items 2.Replacement of existing ceramic wall tile 3.Removal of existing wall-mounted sink 4.Provide new lav/toilet unit, including necessary plumbing modifications and removal of asbestos-containing pipe insulation E.Contractor Scope of Work in Semi-Private Rooms B619 & B621: 1.Removal of existing bathroom between B619 & B621 completely 2.Construction of new wall between B619 & B621 3.Replacement of floor finishes, wall finishes, and ceilings 4.Replacement of HVAC ductwork, diffusers, and radiant panels 5.Removal of existing plumbing fixtures and installation of new lav/toilet unit 6.Removal/reinstallation of wall-mounted items 7.Replacement of sprinkler piping and heads 8.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications F.Work by Others: 1.Removal/reinstallation of loose furnishings G.Key Issues: Only one room will be available at a time Item 5 (Project 5): 528A7-08-708, Remodel Canteen Dining Room A.Location: Ground Floor Southwest B.Size: Approximately 4,000 SF C.Contractor Scope of Work: Replacement of finishes, including: 1.Removal of asbestos - containing floor tile 2.Removal of existing tables and seating 3.Replacement of floor finishes and wall finishes 4.Cleaning of existing metal pan ceiling 5.Removal/reinstallation of wall-mounted items D.Work by Others: 1.New tables and seating (loose) E.Key Issues: VA will furnish sheet vinyl flooring and vinyl wall covering for installation by contractor Option 1 (Project 6): 528A7-07-703 All Additional Work for Renovate Histology C368 A.Location: 3rd Floor Southwest B.Size: Approximately 700 SF C.Contractor Scope of Work: 1.Removal of asbestos - containing floor tile and pipe insulation 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, ceilings, cabinetry, and millwork 3.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 4.Replacement of plumbing fixtures, piping, and valves 5.Replacement of sprinkler heads, and piping 6.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Work by Others: 1.Removal/reinstallation of loose furnishings and equipment. E.Key Issues: Work includes cosmetic renovation of toilet room C365. Option 2 (Project 7): 528A7-08-710 All Additional Work for Renovate Speech Pathology A.Location: Ground Floor Northeast B.Size: Approximately 600 SF C.Contractor Scope of Work: 1.Removal of asbestos - containing pipe insulation 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, and ceilings 3.New cabinetry and millwork 4.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 5.Replacement of plumbing fixtures, piping, and valves 6.Replacement of sprinkler heads, and piping 7.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Work by Others: 1.Removal/reinstallation of loose furnishings and equipment E.Key Issues: Work includes removal of existing audiology booth which must be sawcut/dismantled to fit through doors; project is across the hall from the Director's Office Option 3 (Project 8): 528A7-08-711 All Additional Work for Renovate Imaging Reading Area A.Location: 3rd Floor West B.Size: Approximately 350 SF C.Contractor Scope of Work: 1.Removal and infill of one exterior window 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, ceilings, cabinetry, and millwork 3.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 4.Replacement of plumbing fixtures, piping, and valves 5.Replacement of sprinkler heads, and piping 6.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Work by Others: 1.Removal/reinstallation of loose furnishings and equipment Option 4 (Project 9): 528A7-08-733 All Additional Work for Renovate X-Ray A328 A.Location: 3rd Floor East B.Size: Approximately 700 SF C.Contractor Scope of Work: 1.Removal of asbestos - containing floor tile and pipe insulation 2.Replacement of walls, doors, frames, hardware, floor finishes, wall finishes, ceilings, cabinetry, and millwork 3.Replacement of HVAC ductwork, diffusers, radiant panels, piping, and valves 4.Replacement of plumbing fixtures, piping, and valves 5.Replacement of sprinkler heads, and piping 6.Replacement of electrical systems including lighting, power, smoke & fire detection, and communications D.Work by Others: 1.Removal of existing imaging equipment and installation of new imaging equipment 2.Removal and reinstallation of loose furnishings E.Key Issues: Close coordination is required for all trades to accommodate new construction above ceiling and below floor
 
Web Link
FedBizOpps Complete View
(https://www.fbo.gov/?s=opportunity&mode=form&id=7bf1b513b46903622a7c9bebe6783f96&tab=core&_cview=1)
 
Place of Performance
Address: VA Medical Center;800 Irving Avenue;Syracuse, NY
Zip Code: 13210
 
Record
SN01590518-W 20080612/080610222002-54f2cb775f104edfc867fdf7cf2c4979 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.