SOLICITATION NOTICE

19 -- Amendment 1: CLARIFICATIONS to "Purchase of sectional barge and marine knuckleboom crane, North Cascades NPS Complex, WA"

Notice Date
4/9/2009
 
Notice Type
Modification/Amendment
 
Contracting Office
Department of the Interior, National Park Service, NPS - All Offices, PWR - NOCA - North Cascades NPS Complex 7280 Ranger Station Road Marblemount WA 98267
 
ZIP Code
98267
 
Solicitation Number
Q9471091018
 
Response Due
4/21/2009
 
Archive Date
4/9/2010
 
Point of Contact
Sarah J. Welch Contract Specialist 3608547220 Sarah_Welch@nps.gov;<br />
 
Small Business Set-Aside
Total Small Business
 
Description
The information contained herein supplements the original combined synopsis/solicitation, which can be viewed at http://ideasec.nbc.gov; do a quick search for document #Q9471091018. Incorporate this information when preparing your quote. NPS is providing the following answers to questions posed by interested vendors. Q1. Will the government's barge towing vessel be available to assist during the barge launching? A1. There will be an NPS vessel on site, but NPS will not assist with the launch. Assembly and launching are the sole responsibility of the contractor. Q2. Is the vendor's barge launching responsibility finalized when the assembled barge is moored dockside at the Old Mill Park boat launch?A2. Yes. Q3. Is it permissible for the barge to be assembled in the lake, rather than in the parking lot at Old Mill Park?A3. Yes, if the barge can be assembled within the available 24' width. Q4. Will NPS employees assist during barge launching?A4. No (see A1). Q5. Is aluminum construction acceptable for the barge?A5. Aluminum is not preferred even if it meets our load capacity specs. The nature of the rocky shoreline where we often put in makes aluminum a less favorable option. Q6. Will alternate configurations to what we specified will be considered and evaluated?A6. Offered products need to at least meet our minimum performance specifications to be considered. You may suggest and price changes as options, which we'll consider. For example, including fixtures for towing, mooring and anchoring is acceptable. However, offers for barges that exceed the maximum dimensions stated in the solicitation (20' W x 40' L plus rakes) will not be considered. Q7. Are there any more details available about the launch site at Old Mill Park?A7. The launch site includes three slips with cement ramps going down into the lake. The center slip is the widest (24') and is defined by floating sidewalk-sized docks on either side anchored by pilings spaced approximately 6-8' apart. The length of the docks exceeds 50', and is likely close to 80'. On the outside edge of a neighboring slip, there is a log boom with pilings spaced along its length, which is overall 75' - 100'. Lake Chelan is a reservoir whose elevation varies with the seasons. Current lake level can be monitored at http://www.chelanpud.org/lake-chelan-lake-levels.cfm. Photos are available at http://mansonparks.com/references.html. Additional photos can be e-mailed upon request (send an e-mail to sarah_welch@nps.gov). Driving directions are at http://www.chelanpud.org/driving-directions-to-old-mill-park.html. Q8. What working radius would be best for the cranes reach?A8. Working radius of 32' to 36'. Q9. What rated capacity for the crane would be best for your application?A9. Lift 2000 lbs at 30'-36' distance. Q10. Who will pay for crane delivery to installer?A10. NPS will arrange and pay for the transport of the crane (see (22) in solicitation). Note the pick-up address for the crane in Item 2a in the price schedule, if you are offering a crane. Q11. In addition to providing photos of the barge and crane already used on Ross Lake, will you divulge the purchase price of those items?A11. That purchase was far enough in the past that the purchase price is irrelevant to this action. Q12. Need more information on what kind of "industry-standard" rakes are desired (see specification (1)).A12. The desired configuration is for a square (box) stern and sloped (raked) bow for the full width of each section. If the rake is a separate item to be attached to the barge sections, rather than part of the overall design and fabrication, then the attachment system should follow that described in specification (3) in solicitation. It is preferred that the system holding barge sections together and the system holding rakes to sections should be the same. Rake surface should match the surface of the barge sections in condition and elevation.
 
Web Link
FedBizOpps Complete View
(https://www.fbo.gov/?s=opportunity&mode=form&id=16262d3d55df596195c7717642d9802b&tab=core&_cview=1)
 
Place of Performance
Address: Deliver to Chelan WA 98816<br />
Zip Code: 98267<br />
 
Record
SN01789522-W 20090411/090409220127-16262d3d55df596195c7717642d9802b (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.