AWARD
M -- RECOVERY--M--MODIFICATION NOTICE - REPLACE POWERHOUSE ROOF - WEST POINT POWERHOUSE, OPERATION AND MAINTENANCE OF GOVERNMENT-OWNED FACILITES AND EQUIPMENT, WEST POINT, GEORGIA
- Notice Date
- 8/3/2009
- Notice Type
- Award Notice
- NAICS
- 561210
— Facilities Support Services
- Contracting Office
- Department of the Army, U.S. Army Corps of Engineers, US Army Engineer District, Mobile, US Army Engineer District, Mobile, P. O. Box 2288, 109 Saint Joseph Street (zip 36602), Mobile, AL 36628-0001
- ZIP Code
- 36628-0001
- Solicitation Number
- W91278-09-106-ARRA
- Archive Date
- 10/13/2009
- Point of Contact
- Helene Mitchell, 2514416531<br />
- E-Mail Address
-
US Army Engineer District, Mobile
(helene.s.mitchell@sam.usace.army.mil)
- Small Business Set-Aside
- N/A
- Award Number
- W91278-06-C-0003 P00047
- Award Date
- 7/31/2009
- Awardee
- Anderson Construction Company, 58 Crozier Road, Fort Gaines, GA 39851
- Award Amount
- 758841.65
- Line Number
- 0021,0022
- Description
- This contract action was not awarded as a fixed price type because uncertainties involved in contract performance did not permit costs to be estimated with sufficient accuracy to use any type of fixed price contract. As such, a cost-reimbursement type action was awarded (FAR 16.301-2). Furthermore: 1) The contractor prepared the specifications and drawings for the new roof in 2008 but actual replacement of the roof was delayed due to lack of funds. 2) Acquisition strategy meetings held prior to ARRA funding determined existing contractor would be responsible for installing the new roof. 3) The contractor has experience from replacing roofs at Jim Woodruff Powerhouse and George G. Andrews Powerhouse. 4) The contractor has experience with working around power generation schedules due to the operation of rotating equipment. 5) The contractor has experience with working around the existing contractor whos performing on-site rehabilitation of generator units 2 and 3. 6) The contractor has experience in working around high voltage equipment, arc flash hazard, and suspended platforms. The incumbent contractor not only has the management, technical, and administrative skills to efficiently and effectively accomplish this work at a reasonable cost, but also the advantage of the flexibility to readily adjust to any unforeseen circumstance encountered during the job.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA01/W91278-09-106-ARRA/listing.html)
- Record
- SN01897185-W 20090805/090803235748-459cef52e53021b995026d79c910473d (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |