AWARD
A -- RECOVERY--A--Distributed Power Systems for Sustainable Energy Resources
- Notice Date
- 8/17/2009
- Notice Type
- Award Notice
- NAICS
- 541712
— Research and Development in the Physical, Engineering, and Life Sciences (except Biotechnology)
- Contracting Office
- Department of the Army, U.S. Army Corps of Engineers, U.S. Army Humphreys Engineer Center Support Activity, US Army Humphreys Engineer Center Support Activity, ATTN: CEHEC-CT, 7701 Telegraph Road, Alexandria, VA 22315-3860
- ZIP Code
- 22315-3860
- Solicitation Number
- W912HQ-SI-0939
- Response Due
- 7/22/2009
- Archive Date
- 9/20/2009
- Point of Contact
- Danielle Billings, 703-428-6123<br />
- E-Mail Address
-
US Army Humphreys Engineer Center Support Activity
(danielle.j.billings@usace.army.mil)
- Small Business Set-Aside
- N/A
- Award Number
- W912HQ-09-C-0055
- Award Date
- 8/12/2009
- Awardee
- United Technologies Corporation<BR>411 Silver Ln<BR>East Hartford, CT 06118
- Award Amount
- 2,017,003.00
- Line Number
- 0001, 0002
- Description
- This contract action was not awarded as a fixed price type because uncertainties involved in contract performance did not permit costs to be estimated with sufficient accuracy to use any type of fixed price contract. As such, a cost-reimbursement type action was awarded (FAR 16.301-2). Project Number SI-0939 entitled Distributed Power Systems for Sustainable Energy Resources. This work falls within the topic areas of both Continuous Building Commissioning and Solid Waste Gasification. This funded amount of $1,390,003.00 falls within the topic of Continuous Building Commissioning and $627,000.00 falls within the topic of Solid Waste Gasification. RATIONALE FOR CONTRACT AWARD THAT IS NOT FIXED-PRICE: This is a R&D type contract in support of the Environmental Security Technology Certification Program (ESTCP) issued against BAA-09-0003. Cost reimbursement contracts are suitable for use when uncertainties involved in contract performance do not permit cost to be estimated with sufficient accuracy to use any type of fixed price contract. The nature of development work often requires a cost-reimbursement arrangement. In addition, the contractor's accounting system has been deemed adequate for determining cost applicable to the contract and appropriate Government surveillance during performance will provide reasonable assurance that efficient methods and cost controls are used.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA72/W912HQ-SI-0939/listing.html)
- Record
- SN01914224-W 20090819/090818000815-42b6f5118a1aaf8a57fa964140704e32 (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |