MODIFICATION

Z -- Design-Build, Repair (Remediate) Airfield Obstructions

Notice Date
9/3/2009
 
Notice Type
Modification/Amendment
 
NAICS
238990 — All Other Specialty Trade Contractors
 
Contracting Office
Department of the Air Force, Air Education and Training Command, Lackland AFB - 37th Contracting Squadron, 1655 Selfridge Avenue, Lackland AFB, Texas, 78236-5253
 
ZIP Code
78236-5253
 
Solicitation Number
FA3047-09-B-0002
 
Archive Date
9/30/2009
 
Point of Contact
Belinda S. Gallo, Phone: 2106715144, Jackie L. Murray, Phone: 2106711728
 
E-Mail Address
belinda.gallo@lackland.af.mil, jackie.murray@lackland.af.mil
(belinda.gallo@lackland.af.mil, jackie.murray@lackland.af.mil)
 
Small Business Set-Aside
HUBZone
 
Description
The following 30 questions have been received (2 Sep 09) and are awaiting a technical response. The purpose of presenting the questions now without responses is to avoid duplication of future questions for subject project: Question 1: CLIN 0001 - Will the existing approach lighting stations be in the correct locations after installation of the relocated threshold light bar? Government Response: Pending Question 2: CLIN 0001 - Please confirm the correct location / position of the relocated threshold light bar. (i.e. Will it be moved North to the edge of the runway full strength pavement?) Government Response: Pending Question 3: CLIN 0001 - Can the existing threshold light bar be blanked of w/ covers or will the existing light bar have to be removed? Government Response: Pending Question 4: CLIN 0001 - Will the Taxiway Edge Lights on the South side of the connecting taxiway be deleted due to relocation of the South threshold light bar? Government Response: Pending Question 5: CLIN 0002 - Confirm that the existing threshold light bar is to be completely removed and a new light installed with fixtures in the correct orientation? Government Response: Pending Question 6: CLIN 0003 - Is it correct to assume that the contractor is to replace all of the heliax cable between the new localizer antenna shelter locations and the antennas in lieu of splicing the existing cable? Government Response: Pending Question 7: CLIN 0003 - What size heliax cable is the contractor to install? Government Response: Pending Question 8: CLIN 0003 - Is the contractor to design and install a new underground fuel vault for the North ILS shelter genset or remove and relocate the existing underground fuel vault? Government Response: Pending Question 9: CLIN 0003 - If a new fuel vault is installed, can the existing underground fuel vault be abandoned in place? Government Response: Pending Question 10: CLIN 0003 - Is the primary power to the existing ILS shelters 600V or medium voltage? Government Response: Pending Question 11: CLIN 0003 - If the primary power line is medium voltages, who owns the line (i.e.: local utility power company or USG)? Government Response: Pending Question 12: CLIN 0003 - Is the contractor responsible for moving the electronics equipment within the localizer shelters that are being relocated? Government Response: Pending Question 13: CLIN 0003 - Will the localizers require re-tuning after new cables are installed and what entity will perform this task? Government Response: Pending Question 14: CLIN 0003 - Will the localizers require flight checks after new cables are installed? Government Response: Pending Question 15: CLIN 0004 - Who is the contact representative for the City Public Utility Service Company? This information will be required in order to calculate costs associated with relocation of this equipment and appurtenances. Government Response: Pending Question 16: CLIN 0004 - What existing equipment does the distribution panel connected to the load side of the CPS pad mount transformer feed? Is a one-line diagram or a feeder schedule available to determine what equipment is fed from this panel? Government Response: Pending Question 17: CLIN 0004 - Does the sectionalizer switch connect to any other CPS transformers or equipment? Government Response: Pending Question 18: CLIN 0005 - What is the operating voltage for the North Main Glide Slope Vault distribution system? This includes the primary power into the vault and the secondary power as connected to the existing genset. Government Response: Pending Question 19: CLIN 0005 - Is a one-line diagram or equipment schedule available for the distribution equipment in the existing North Main Glide Slope Vault? Government Response: Pending Question 20: CLIN 0005 - Is there an existing underground duct bank system (with an empty raceway) from the new vault location at Upson Park to the North Glide Slope Shelter location? Government Response: Pending Question 21: CLIN 0005 - Is a new building to be provided or is the existing structure intended to be relocated regardless of the current condition of the building? Government Response: Pending Question 22: CLIN 0006 - Is the work to be performed in this CLIN currently being done under a separate contract? Government Response: Pending Question 23: CLIN 0007 - Please confirm if CLIN 0007 will be included in this solicitation? Government Response: Pending Question 24: CLIN 0008 - Are any drawings or construction documents available for the existing storm drain structure? Government Response: Pending Question 25: CLIN 0008 - Will any borrow dirt be available on site or will the contractor be required to haul all embankment onto the work site? Government Response: Pending Question 26: Are geotechnical reports available that are within the project area? Government Response: Pending Question 27: Is there a specific CAD package that is required for the design drawings? If yes, please specify which package and version. Government Response: Pending Question 28: How many drawings/specification submittals will be required and at what percentages complete? Government Response: Pending Question 29: Please provide record / As-Built drawings of the existing facilities to be relocated / modified in this project. Government Response: Pending Question 30: Is the threshold bar at each runway end the only ALSF-1 station requiring relocation / modification? Government Response: Pending (End)
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USAF/AETC/LackAFBCS/FA3047-09-B-0002/listing.html)
 
Place of Performance
Address: Lackland AFB-Runway, San Antonio, Texas, 78236, United States
Zip Code: 78236
 
Record
SN01939847-W 20090905/090904001354-93b80e0fbb6b5f9c68f6fbab61e715ba (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.