Z -- Pre-solicitation notice to move two TSW(Top Spillway Wier)components to upstream spillway slots at McNary Dam, remove the downstream TSW2 components and haul away for disposal.

Notice Date
2/10/2010
 
Notice Type
Presolicitation
 
NAICS
811310 — Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance
 
Contracting Office
USACE District, Walla Walla, 201 N. Third Avenue, Walla Walla, WA 99362-1876
 
ZIP Code
99362-1876
 
Solicitation Number
W912EF10Q0027
 
Response Due
3/10/2010
 
Archive Date
5/9/2010
 
Point of Contact
Jean DesJarlais, 509-527-7222
 
E-Mail Address
USACE District, Walla Walla
(jean.j.desjarlais@usace.army.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
This synopsis is not a request for quotes or proposals. This is a pre-solicitation notice that a solicitation is scheduled to be released via FedBizOpps (wwww.fbo.gov) in the near future detailing this requirement. The contractor shall reconfigure the spillway gates according to the contract plans (to be provided with solicitation)to provide access to both the TSW1 crest, the TSW2 crest, the TSW2 leaf support frame, and the TSW2 downstream leaf. In order to obtain access to the TSW2 crest it is first necessary to remove the TSW2 downstream components. Currently TSW1 and 2 are located in spillbay19 and 20. These components are not readily suitable for highway transport without some disassembly. As a result the contractor shall take these components to a McNary provided work site for disassembly. When originally constructed, a special bottom seal assembly was fabricated and installed on the bottom of one upper spillway gate leaf for use in suspending flow over the TSW2 crest. This seal assembly shall also be removed from the gate at the disassembly site. The contractor shall then haul the downstream TSW2 components and the seal assembly offsite for disposal. With the TSW2 downstream components out of the way, the contractor shall then reconfigure the spillway gates to provide access to the TSW1 and TSW2 crest pieces. The contractor shall take those crest pieces and place them in two upstream spillway gate slots provided by McNary. Finally the contractor shall reconfigure the TSW spillbays to provide for normal spillway operation. The TSW and spillway gate components are large and heavy and not conducive to manipulate with a mobile crane. McNary will provide contractor access to a spillway crane. This announcement is for informational and planning purposes only and is not to be construed as a comitment by the Government, implied or otherwise, to issue a solicitation or award a contract.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA68/W912EF10Q0027/listing.html)
 
Place of Performance
Address: USACE District, Walla Walla 201 N. Third Avenue, Walla Walla WA
Zip Code: 99362-1876
 
Record
SN02062187-W 20100212/100210234433-8b1a45f9aa86585a2cc18b8545b62b19 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.