Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
FBO DAILY ISSUE OF SEPTEMBER 01, 2010 FBO #3203
SOLICITATION NOTICE

K -- Annual SwitchGear Parallel Line Controls Maintenance

Notice Date
8/30/2010
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
423830 — Industrial Machinery and Equipment Merchant Wholesalers
 
Contracting Office
N00604 FISC PEARL HARBOR 1942 Gaffney Street, Ste 100 Bldg. 475-2, Code 200 Pearl Harbor, HI
 
ZIP Code
00000
 
Solicitation Number
N0060410T3098
 
Response Due
9/2/2010
 
Archive Date
10/2/2010
 
Point of Contact
Stephen G White 808 473-7572 Stephen G White (808) 473-7572 Stephen.g.White1@Navy.Mil; Jonathan Williams (808) 335-4407 Jonathan.Williams2@navy.Mil
 
E-Mail Address
Navsup Email
(Stephen.g.white1@Navy.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
Switchgear and Switchboard Assemblies 1. Remove exterior covers exposing the buswork. Clean insulators and inspect. Hipot all buswork. DLRO all joints to verify good connections. Reinstall exterior covers. 2. Test circuit breakers. Using the Zensol circuit breaker tester, verify all operational timing parameters. Using Hipot, verify vacuum bottle and insulator integrity. Using DLRO, verify contact resistance. 3. Test protective relays. Using Manta MTS-5000 power system simulator, verify actual operating parameters as programmed. Verify fault timings. Relays to be tested “ 1 each SR750, 2 each S4489, 1 each 751A, 7 (estimated) other miscellaneous protection devices. Simulate system wide faults to verify proper coordination of settings under both utility and generator supplied power conditions. 4. Clean switchgear interior. Tighten all terminal block connections. Visually inspect all components. 5. Submit report detailing test results by PDF. Evaluated feeder breaker Protective Relay 1. Go to the jobsite and download the existing settings from the Siemens feeder overcurrent relays. Document hardware and firmware revision levels. 2. Obtain connected load and transformer data for each feeder. 3. Perform calculations to evaluate what settings and logic would provide coordinated protection for each distribution feeder per NEC requirements. 4. Compare existing settings with those calculated. 5. Submit the results of the comparison to your engineering team for their review and comment. 6. Upon review, change indicated settings, logic, and firmware versions for each Siemens relay and perform operational testing. Evaluated Generator and Utility Feeder Protective Relays 1. Evaluate existing generation and utility logic and settings. 2. Perform calculations coordinated with distribution protection devices in accordance with NEC requirements and within the capabilities of the installed equipment. 3. Submit the results to your engineering team for their review and comment. 4. Upon review, change indicated settings and logic for each relay. Perform operational testing.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/DON/NAVSUP/N00604/N0060410T3098/listing.html)
 
Place of Performance
Address: Pacific Missile Range Facility
Zip Code: Receiving Office Code 7040
 
Record
SN02259575-W 20100901/100830234604-24ec7f68ee787af4a868bf8fea323df5 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.