AWARD
Z -- RECOVERY--Z--PROJECT NUMBER 18050, Tenkiller Ferry Lake, OK, PROJECT NUMBER 18350, Toronto Lake, KS, PROJECT NUMBER 5790, Fall River Lake, KS, PROJECT NUMBER 6000, Fort Gibson Lake, OK, PROJECT NUMBER 7850, Hulah Lake, OK, PROJECT NUMBER (See Desc)
- Notice Date
- 1/12/2011
- Notice Type
- Award Notice
- NAICS
- 236220
— Commercial and Institutional Building Construction
- Contracting Office
- USACE District, Tulsa, ATTN: CESWT-CT, 1645 South 101st East Avenue, Tulsa, OK 74128-4609
- ZIP Code
- 74128-4609
- Solicitation Number
- W9126G-08-R-0171
- Archive Date
- 3/8/2011
- Point of Contact
- Phyllis O. Jordan, 918 832-4120
- E-Mail Address
-
USACE District, Tulsa
(phyllis.jordan@usace.army.mil)
- Small Business Set-Aside
- N/A
- Award Number
- W9126G-08-D-0083, DS01, DS0103
- Award Date
- 11/22/2010
- Awardee
- OVERLAND CORPORATION (109041970) <br> 7 MILES SOUTH ARDMORE ON HWY 77<br> ARDMORE, OK 73401-1947
- Award Amount
- $36,210.00
- Description
- (Subject Continued) 8790, Kaw Lake, OK RECOVERY - PER FAR 5.7 THIS NOTICE IS PROVIDED FOR INFORMATION PURPOSES ONLY; THEREFORE FAR 5.203 DOES NOT APPLY. THIS OPPORTUNITY WAS AVAILABLE ONLY TO CONTRACTOR(S) UNDER: Mutiple Award Task Order Contract (MATOC) As part of Operations and Maintenance, Army, Recovery Act, this modification has been issued to Overland Corporation, to perform the following work--Additional Guardrail Installation: Fall River--Remove and replace 370 LF of guardrail at the power house road. Remove and do not replace 790 LF of unwarranted damaged guardrail on the roadway approach to the main embankment. Toronto--Remove and replace 225 LF of guardrail at the power house road. Replace the deleted parapet walls with two turned down rail connections. Tenkiller--Remove and replace 400 LF of guardrail at the power house parking lot. Ft Gibson: Remove and replace 450 LF of guardrail at the power house road. Hula--Replace one parapet wall with tapered flat work to prevent blunt end collisions. Revise one parapet wall by removal of the imbedded light fixure in the existing parapet wall, breaking back the existing parapet wall to allow epoxy coated rebar to be doweled in and encased in new structural concrete flush with the roadway surface of the existing parapet wall. Kaw--Install new Tribeam connections in lieu of the two parapet walls by coring the existing parapet wall for tiebeam connections.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA56/W9126G-08-R-0171/listing.html)
- Record
- SN02358886-W 20110114/110112234228-972ecc15da10ee377c00e0cf28ad1f57 (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |