Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
FBO DAILY - FEDBIZOPPS ISSUE OF MAY 04, 2013 FBO #4179
SOURCES SOUGHT

Y -- Piers and Dredging, Umm Qasr, Iraq

Notice Date
5/2/2013
 
Notice Type
Sources Sought
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
USACE Middle East District, P.O. Box 2250, Winchester, VA 22604-1450
 
ZIP Code
22604-1450
 
Solicitation Number
W912ER-13-R-0050
 
Response Due
5/8/2013
 
Archive Date
7/1/2013
 
Point of Contact
Tino Philip, 5406653953
 
E-Mail Address
USACE Middle East District
(tino.philip@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Description
SYNOPSIS: The U.S. Army Corps of Engineer (USACE) Middle East District intends to solicit names of construction firms experienced in working in the Middle East region who are interested in submitting a firm-fixed price offer for this project. MED is anticipating a project at an Iraqi Naval installation located at the Port of Umm Qasr, approximately 35 miles to the southeast of the Iraqi city of Basrah, adjacent to the southeastern border of the country. The anticipated period of performance is 365 calendar days for the Project. A firm fixed price contract will be awarded to a prime construction contractor. The magnitude of the project is between $10,000,000 and $25,000,000. PROPOSAL PERIOD: The Two-Phase Design-Build Solicitation is scheduled for release on or about 22 May 2013. The Phase One proposals will be due on or about 21 Jun 2013. Contract award is scheduled on or about 05 Sep 2013. PROJECT SCOPE: This project includes the following elements: a.Design and construct a floating pier, approximately 165m in length, for berthing of vessels with draft of up to 6 meters. This new pier will connect to an existing fixed concrete pier by means of a new ramp or gangway that is included in this design-build contract. The proposed pier will include utility connections to existing or future infrastructure to include electrical shore power connections, compressed air, fresh (non-potable) water, fuel lines and lighting. b.Design and construct supporting facilities for the floating pier. These Supporting facilities include electrical, water and fuel infrastructure, transformers, site work, a paved road connecting the pier to existing road infrastructure and drainage. c.Design and execute an initial dredging operation from the boundary of the commercial port to the southern border of Iraq as shown in the attached figure. The approximate dredging area is 300,000 square meters and the approximate volume of dredged material to be removed is 900,000 cubic meters, including a 1.0 meter overdredge tolerance. The contractor will construct a dredged materials disposal area in an authorized location adjacent to the dredging area. The contractor will provide a dredged material disposal system that allows for dredging operations with no interruption of navigational traffic in the existing nearby channels. d.For one entire year, after the initial dredging is complete, the contractor will provide maintenance dredging to maintain the required design depth. The contractor will prepare and provide an engineered maintenance dredging plan and schedule which satisfies the maintenance dredging requirements. As part of the design effort, the contractor must prepare a detailed project site conditions report. This report shall include the results of several studies and investigations of the project area, including (but not limited to) geotechnical studies, navigational studies, a hydrographic survey and a bathymetric survey. PROPOSAL PROCEDURES: The Request for Proposal (RFP) will be issued only to prime contractors. The Best Value Trade-Offs (BVTO) contracting method will be used to evaluate proposals. Evaluation criteria will be stated in the RFP. The Government may include options in the Solicitation. This acquisition will result in a single fixed price construction contract awarded based on BVTO determination. PROCESSES AND PROCEDURES/INFORMATION FOR: REQUESTING SOLICITATIONS/BIDDERS LIST REGISTRATION This notice is for market research purposes only and is not a request for proposal (RFP) nor does it restrict the Government as to the ultimate acquisition approach. The Government will not reimburse respondents for any costs incurred in preparation of a response to this notice. To respond to this sources sought notice, submit a capabilities statement through the following site: http://www.aed.usace.army.mil/contracting.asp Click on the SOURCES SOUGHT tab; click the COMPLETE button under the CAPABILITIES STATEMENT column of the solicitation of interest; fill in the requested information; click REGISTER. (Solicitation release information will only be released to those who have electronically filled out a Capabilities Statement. Capabilities Statements are required for EACH solicitation of interest.) Questions concerning the Processes and Procedures can be sent to Tino Philip, Telephone (540) 665-3953, e-mail Tino.Philip@usace.army.mil.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA78/W912ER-13-R-0050/listing.html)
 
Record
SN03051632-W 20130504/130502235135-73d205ece25d14c7d326e703ab4b30fb (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.