MODIFICATION

Y -- Emergency Generator Upgrade - Claremore Indian Hospital

Notice Date
8/27/2014
 
Notice Type
Modification/Amendment
 
NAICS
237130 — Power and Communication Line and Related Structures Construction
 
Contracting Office
Department of Health and Human Services, Indian Health Service, Oklahoma City Area Office, 701 Market Drive, Oklahoma City, Oklahoma, 73114, United States
 
ZIP Code
73114
 
Solicitation Number
246-2014-P-0019
 
Archive Date
9/27/2014
 
Point of Contact
Duke A Henthorn, , Judy Perkins, Phone: 405.951.6023
 
E-Mail Address
duke.henthorn@IHS.gov, judy.perkins2@ihs.gov
(duke.henthorn@IHS.gov, judy.perkins2@ihs.gov)
 
Small Business Set-Aside
Service-Disabled Veteran-Owned Small Business
 
Description
The following questions and responses are added; Question: In regards to the transfer switches, will the existing service disconnect switches for the transfer switches(that are mounted down on the floor below the transfer switches) be replaced? If yes, do the new transfers switches need to have the disconnects mounted on them or do separate new disconnects need to be mounted back in the electrical room? Response: This is covered in the SOW. Disconnects between generator and ATS boxes are to be removed from the room and may be placed next to, not on, the ATS boxes or may be out by/part of the generator. Question: Is it a requirement for 120 volt electrical outlets mounted inside the generator enclosure that can be used if someone is working around the generator? Convenience 120 Response : VAC outlets required at the generator pad. I would prefer they be accessible from the pad or outside the generator enclosure. If the enclosure/generator comes with it, great, if not, put them on the pad. Question : A 600kw generator is capable of producing 900 amps at 100% load but the generators come standard with a 1000 amp 80% Rated thermal breaker which will trip at 800amps and a 50% load would come out to 400amps. Would the hospital prefer a 100% rated adjustable breaker so they can get 900amps out of a 600kw and the 50% load rating would be 450amps? Response: Yes, if it's allowed by code. Question : It was stated at the site visit that the hospital does not perform load banking and use building load, do you still require the generator to have the load bank quick connect plugs on the generator? Response : Yes, only stated that they haven't been performing load bank testing and are not required to for accreditation purposes, but nonetheless we still want the load bank quick connect plugs on the generator. Question: Paragraph V.B.a of the Solicitation for this project references "Attachment G. Recommended Emergency Generator & Fuel Tank Location." We have been unable to find Attachment G on the posting to the FBO.gov website. Is this attachment forthcoming? Response: Yes, to be attached in FBO.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/HHS/IHS/IHS-Oklahoma/246-2014-P-0019/listing.html)
 
Place of Performance
Address: Claremore Indian Hospital, 101 South Moore Avenue, Claremore, Oklahoma, 74017, United States
Zip Code: 74017
 
Record
SN03483055-W 20140829/140828022413-3d7e773c66d2e5b6c0214d3c9e5aefee (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.