AWARD

Y -- Oahe Passive Transfer Oil Containment

Notice Date
9/30/2015
 
Notice Type
Award Notice
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
USACE District, Omaha, 1616 Capital Ave, Omaha, NE 68102-4901
 
ZIP Code
68102-4901
 
Solicitation Number
W9128F-15-B-0004
 
Response Due
8/27/2015
 
Archive Date
10/30/2015
 
Point of Contact
Shanna Comparato, 402-995-2067
 
E-Mail Address
USACE District, Omaha
(shanna.m.comparato@usace.army.mil)
 
Small Business Set-Aside
N/A
 
Award Number
W9128F-15-C-0029
 
Award Date
9/29/2015
 
Awardee
SHARPE ENTERPRISES, INC. (609364604) <br> 3500 SD HWY 34 <br> PIERRE, SD 57501
 
Award Amount
$1,678,200.00
 
Line Number
0001-0008
 
Description
1. Main Unit Transformer Oil Containment This project is to install passive oil containment systems on ten (10) Generator Step-Up(GSU) Transformers located on the tailrace deck at the Oahe Powerhouse. Transformer 1 is a three-phase 115 kV transformer rated 103MVA and holds 4050 gallons of oil. There are 3 single-phase 230 kV transformers for banks 2, 3, and 4 for a total of 9 transformers each rated about 69 MVA and hold 4400 gallons of oil per phase. Each transformer is enclosed in concrete walls on three sides, with the downstream side open. The upstream wall is the powerhouse while the other two are firewalls. A curb will be placed on the downstream side of the powerhouse to provide enough containment to hold all of the transformer oil and the water from a 25-year, 24-hour storm event. A passive oil containment system will be placed in the lower section of each transformer vault. The passive liner will allow storm water to flow through while containing any hydrocarbons. Six-inches of fire quenching stone will then be placed on top of the liner to help extinguish puddle fires. Oil absorbing mats placed on top of the rock will be used to help collect small chronic leaks of the existing transformer to protect the life of the passive system. In the event of a catastrophic oil failure, the passive liner will solidify creating a water-tight barrier inside the vault. This will prevent any hydrocarbons from reaching the drain and being discharged into the river. Stairs may be installed to allow personnel to easily access the transformer vault. In addition to the containment on the GSU transformers, a similar passive containment system may be required the two (2)-1MVA station service transformers.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA45/W9128F-15-B-0004/listing.html)
 
Record
SN03910581-W 20151002/151001000455-2201f2dc20174985341a69de2104c03a (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.