MODIFICATION
56 -- DECC Bldg 891 Electrical Upgrade, Hill AFB - Amendment 2
- Notice Date
- 10/29/2015
- Notice Type
- Modification/Amendment
- NAICS
- 236220
— Commercial and Institutional Building Construction
- Contracting Office
- Department of the Army, U.S. Army Corps of Engineers, USACE District, Sacramento, 1325 J. Street, Sacramento, California, 95814, United States
- ZIP Code
- 95814
- Solicitation Number
- W91238-15-R-0077
- Point of Contact
- Charlie W. Gritzmacher, Phone: 9165575193
- E-Mail Address
-
Charles.W.Gritzmacher@usace.army.mil
(Charles.W.Gritzmacher@usace.army.mil)
- Small Business Set-Aside
- N/A
- Description
- Attachment 3 - Specifications for Amd. #3 Amendment #3 ***Amendment 0003 - The purpose of amendment 3 is to: A. Extend the proposal due date from 2 Nov 2015 to 6 Nov 2015 2pm B. Revise section 00 22 00, 4.3.3.3 Project Schedule NTP date from 01 Jun 14 to 21 Mar 2016. C. Revise attachment #2 Specifications - Section 01 10 10: paragraph 11.1.1.1 (see attach. #3 for revision) D. Revise attachment #2 Specifications - Section 01 10 10: paragraph 15.1.1 (see attach. #3 for revision) E. Revise attachment #2 Specifications - RFP Concept Draw ing, CLIN 2 C Bus One Line Concept Diagram (see attach. #3 for revision) F. Revise attachment #2 Specifications - Attachment 10, Div 25 Integrated Automation: paragraph under "Integrated Automation Enterprise Contract". (see attach. #3 for revision) G. Revise attachment #2 Specifications - Electrical BAS Points sheets provided as reference. (see attach. #3 for revision) *** ***Amendment 0002 - Revised CLIN schedule - see amended solicitation attachment.*** ***Amendment 0001 - The Site Visit has been re-scheduled for Thursday, 15 October 2015. The Hill AFB visit request and the VAR letter must be submitted no later than 1200 hours Mountain Time on Friday, 9 October 2015. NOTE - please send the two requests in separate emails per the site visit instructions in the solicitation. Contractors who have already submitted their visit request and VAR letter do not have to re-submit. All questions entertained at the site visit must be submitted via DrChecks no later than COB 21 October 2015.*** US Army Core of Engineers (USACE), Sacramento District is requesting proposals for a Design-Build General Construction contract. This design-build project will upgrade the electrical distribution system for the existing single story DECC building 891 at Hill Air Force Base. The project shall be designed and constructed within the criteria prescribed in the Statement of Work (SOW) and specifications. This project is intended to provide a redundant power source consistent with DISA DECC architectures conforming to a Tier III datacenter configuration for essential electrical distribution that serves Heating, Ventilation and Air Conditioning (HVAC) and house loads. This requirement will be pursued as a Total Small Business set-aside, limited to Utah based small businesses only. The solicitation will be advertised in accordance with FAR 36.3 entitled, "Two-Phase Design Build Selection Procedures". ***Please note site visit is scheduled for 08 October 2015 at 0800. See section 00 21 00 - Instructions, clause 52.236-27 of draft solicitation for further information and access requirements. All questions must be submitted via DrChecks no later than COB 15 October 2015. ***Phase I proposals will be due 2 November 2015 by 02:00pm PST.
- Web Link
-
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA05/W91238-15-R-0077/listing.html)
- Place of Performance
- Address: Hill AFB, UT, United States
- Record
- SN03932734-W 20151031/151029234234-d6f9a07747f72cb0951434a2fc03368d (fbodaily.com)
- Source
-
FedBizOpps Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's FBO Daily Index Page |