MODIFICATION

Z -- Asphalt Overlay Ohana Campground Loops D & F - MOR

Notice Date
8/10/2016
 
Notice Type
Modification/Amendment
 
NAICS
237310 — Highway, Street, and Bridge Construction
 
Contracting Office
NPS, PWR - OLYM MABO Mount Rainier National Park 55210 238th Ave E ATTN: Pam Griffin Ashford WA 98304 US
 
ZIP Code
00000
 
Solicitation Number
P16PS02060
 
Response Due
8/15/2016
 
Archive Date
8/30/2016
 
Point of Contact
Griffin, Pamela
 
Small Business Set-Aside
Total Small Business
 
Description
The purpose of this amendment is to post clarifications resulting from the site visit held August 2, 2016. Clarifications based on discussion during the site visit: - Work includes digging out all unpaved utility trench cuts to a depth of 2 inches, then pre-leveling with HMA to the existing asphalt surface, all prior to the final HMA paving operation. - Pre-leveling with HMA is required for all potholes or other depressions. - Gravel from the utility trench excavations is acceptable to be re-used for constructing ramps from the finished asphalt surface into existing camp site access driveways. No asphalt chunks will be allowed in the access ramps. - No gravel is to be placed on the shoulder of the new pavement except at camp site access driveways. - Excess spoils from utility trench excavation shall be stockpiled at a site designated by the COR. One site will be designated per campground loop. - All excess asphalt, including discarded chunks and small areas of ravel along the side of the road shall be cleaned up and removed from the site by the Contractor. - The Contractor is responsible for all surface preparation including sweeping, duff removal along road edges, and tack coat application. - NPS will provide traffic control which will consist of closing the camp ground Loops D & F, and posting construction warning signs. - F loop - remove existing asphalt along the utility trench up to the existing saw cut prior to or during excavation and pre-level work. No other changes.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/DOI/NPS/APC-IS/P16PS02060/listing.html)
 
Record
SN04217483-W 20160812/160810234938-a3d9c2b135dc0fa3dc76114a41c408f5 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.