Y -- Construct Bldg 108 IT Center 656-14-246 - Attachment

Notice Date
8/18/2016
 
Notice Type
Attachment
 
NAICS
236220 — Commercial and Institutional Building Construction
 
Contracting Office
Department of Veterans Affairs;NCO 23 - Minneapolis;708 S. Third St., Suite 200E;Attention: Network Contract Manager;Minneapolis MN 55415
 
ZIP Code
55415
 
Solicitation Number
VA26316R0153
 
Archive Date
11/25/2016
 
Point of Contact
Richard Digatono
 
E-Mail Address
richard.digatono@va.gov
(Richard.Digatono@va.gov)
 
Small Business Set-Aside
Veteran-Owned Small Business
 
Award Number
VA263-16-C-0091
 
Award Date
8/18/2016
 
Awardee
PARADIGM CONSTRUCTION, L.L.C.;5000 S MAC ARTHUR LN STE 102;SIOUX FALLS;SD;57108
 
Award Amount
$6,268,778.00
 
Line Number
Line Item # 1.
 
Description
GENERAL INTENTION A. Contractor shall furnish all labor, materials, tools and equipment required to completely and satisfactorily perform the construction of a new data center immediately East of and adjoining to building 4. Base bid will include the incorporation of Half Tap Splicing of the 17,000 existing copper pairs for connection to the new Data Center location. This splicing will occur in the tunnels as required by drawings and specifications. Adjacent buildings will remain occupied by the VA throughout construction. Work in occupied areas may need to be accomplished outside of normal working hours if noise, dust and other hazards cannot be mitigated. Coordination with other construction projects may be required during the course of construction. STATEMENT OF BID ITEM(S) A. ITEM I, Contractor shall furnish all labor, materials, tools and equipment required to completely and satisfactorily perform the construction of a new data center immediately East of and adjoining to building 4. Base bid will include the incorporation of Half Tap Splicing of the 17,000 existing copper pairs for connection to the new Data Center location. This splicing will occur in the tunnels per drawings and specifications. Work includes but is not limited to general construction, metals, wood, plastics and composites, thermal and moisture protection, openings, finishes, furnishings, fire suppression, plumbing, HVAC and mechanical, electrical, multiple communications systems, electronic safety and security, earthwork and exterior improvements, utility systems and electrical power generation. "Work Duration is 340 days "Work hours are to normal hours with the exception of extreme noise, dust, vibration producing operations, may be off hours that case. 1. This contract will require extensive access to VA Information Technology and data areas. Due to the sensitive information contained in these secure areas, the Contractor or sub-contractors will be required to have an escort from the VA when entering, and while executing work in these areas. These areas can be defined as any areas that contain secure VA communications and data equipment that requires a clearance or specific VA credentials to enter. These areas include but are not limited to individual building data closets, and building 108, the current campus data center. a. The contractor must coordinate with his sub-contractors to determine in advance when access to these defined areas will be needed. b. Request for access and escort shall be submitted in writing to the COTR a minimum of 10 business days prior to the day access is requested. Request shall include: building and room the work is being executed in, summary of work to be executed and the expected duration of the work. The COTR will coordinate access with SCVAMC OI&T staff. The VA will make all reasonable efforts to provide access/ escort at the requested date and time. If the specific date and time requested is not available the COTR will provide the contractor the closest available dates and times escort is available. c. The contractor should have subsequent work scheduled in the event the specific dates and times requested are not available. In the event the first available date for access/ escort exceeds the requested access date by 72 hours (not including weekends and holidays) the Contracting Officer shall be notified in order to make a determination as to whether the postponement of access constitutes a legitimate delay, and if a modification to the contract is required.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/VA/MiVAMC618/MiVAMC618/Awards/VA263-16-C-0091.html)
 
Document(s)
Attachment
 
File Name: VA263-16-C-0091 VA263-16-C-0091_1.docx (https://www.vendorportal.ecms.va.gov/FBODocumentServer/DocumentServer.aspx?DocumentId=2951957&FileName=VA263-16-C-0091-000.docx)
Link: https://www.vendorportal.ecms.va.gov/FBODocumentServer/DocumentServer.aspx?DocumentId=2951957&FileName=VA263-16-C-0091-000.docx

 
Note: If links are broken, refer to Point of Contact above or contact the FBO Help Desk at 877-472-3779.
 
Record
SN04230830-W 20160820/160819000040-c7efc0c5b3c0eaa2cec81dc89a84a49d (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.