FBO DAILY - FEDBIZOPPS ISSUE OF SEPTEMBER 22, 2016 FBO #5417
MODIFICATION

H -- Chemical Tank Inspection - *Revised* Statement of Work

Notice Date
9/20/2016
 
Notice Type
Modification/Amendment
 
NAICS
541620 — Environmental Consulting Services
 
Contracting Office
Department of the Air Force, Air Mobility Command, 87th CONS, 2402 Vandenburg, McGuire AFB, New Jersey, 08641, United States
 
ZIP Code
08641
 
Solicitation Number
FA4484-16-Q-0031
 
Archive Date
10/8/2016
 
Point of Contact
Levi Ingram, Phone: 6097540687, Christine T. Lehtinen, Phone: 6097544713
 
E-Mail Address
levi.ingram.2@us.af.mil, christine.lehtinen@us.af.mil
(levi.ingram.2@us.af.mil, christine.lehtinen@us.af.mil)
 
Small Business Set-Aside
Service-Disabled Veteran-Owned Small Business
 
Description
Revised Statement of Work 1. As inquired during the Site Visit, are there any "As-Built" drawings for Building 99? a. If yes, will the Government supply the Contractors with the plans to determine wall thicknesses for the new wall penetration? ANSWER: YES....a photo of the wall thickness from the Plans will be provided in the SOW. The walls are 14" thick concrete. REVISED SOW SEE: 2.11 and Attachment 7 2. Will the Contractor require escorts while working the Project? ANSWER: NO....the contractor must sign in and out of the WTP daily before work begins. But during work Operations, no escort is required. REVISED SOW SEE: 2.16 3. Does the Government require that the Temporary Storage Tank be doubled walled for safety concerns? ANSWER: NO....Double Walled is NOT required, but if single walled, the contractor must provide containments to match the size of the tank. The contractor should select 1 of 2 tank options: Option #1: Provide a double walled tank, with NO Containments required Option #2: Provide a single walled tank, with Containments required REVISED SOW SEE: 2.6 4. Barricades: Should the Contractor include barricading for the Temporary Storage Tank in their Proposal or will the Government supply barricades? ANSWER: NO.....Barricades are not required to be provided by the contractor. WTP personnel are versed in working around utility tanks and equipment. 5. Will the Government require a Check Valve be installed on the bottom of the Temporary Storage Tank? ANSWER: The contractor can select 1 of 2 options to pump the existing tank. Pictures and description of the 2 options are in the revised SOW. Option # 1: Provide and install a check valve on the existing tank valve at the bottom of the tank to connect contractors drain hose/tubing Option # 2: Use manway at the top of the tank to run hose and drain tank from the top REVISED SOW SEE: 2.15 and Attachment 2 6. Please confirm that the Contractor is to return ALL chemicals from the Temporary Storage Tank to the Permanent Storage Tank once ALL inspections have been conducted? ANSWER: YES REVISED SOW SEE: 2.9
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USAF/AMC/305CONS/FA4484-16-Q-0031/listing.html)
 
Place of Performance
Address: 2402 Vandenberg Ave, Joint Base McGuire-Dix-Lakehurst, New Jersey, 08641, United States
Zip Code: 08641
 
Record
SN04280970-W 20160922/160921000235-db43d72d6ea505f7867cb10c6fd9fe14 (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.