Y -- Gull Lake Ceiling Replacement - Solicitation

Notice Date
8/24/2017
 
Notice Type
Combined Synopsis/Solicitation
 
NAICS
238310 — Drywall and Insulation Contractors
 
Contracting Office
Department of the Army, U.S. Army Corps of Engineers, USACE District, St. Paul, Attn: CEMVP-CT, 180 East Fifth Street, St. Paul, Minnesota, 55101-1678, United States
 
ZIP Code
55101-1678
 
Solicitation Number
W912ES17T0128
 
Archive Date
9/21/2017
 
Point of Contact
Jesse Onkka, Phone: 6512905444, Shamron Richardson, Phone: 651-290-5415
 
E-Mail Address
Jesse.L.Onkka@usace.army.mil, Shamron.J.Richardson@usace.army.mil
(Jesse.L.Onkka@usace.army.mil, Shamron.J.Richardson@usace.army.mil)
 
Small Business Set-Aside
Total Small Business
 
Description
SF-1442 REMOVAL AND REPLACEMENT OF CEILING TILE, CEILING TILE GRID, INSULATION AND LIGHTING IN THE GULL LAKE RANGER OFFICE U.S. Army Corps of Engineers 10867 East Gull Lake Drive Brainerd, MN 56401 651-290-5771 1. GENERAL: The contractor shall supply all equipment, labor and materials necessary to remove and properly dispose of all the existing ceiling tiles & grids, florescent lighting and insulation and replace with new closed cell spray foam insulation, ceiling tiles & grids, and LED lighting in accordance with the manufacturers recommendations and local building codes. 2. MEASUREMENT AND PAYMENT: The payment provided for in the contract shall constitute full compensation for furnishing all materials and for performing all work under the contract in a complete and acceptable manner. The contract work shall include providing plant, equipment, tools, supplies, labor, supervision, incidental materials, quality control, environmental protection, testing and meeting safety requirements, and for performing all work required for which separate payment is not otherwise provided. Compensation for all work shown, specified, or essential to completion of the project (whether or not the specific material or operation is indicated) shall be included on the bidding schedule. Payment provided for in the contract includes compensation for all risk, loss, damage, and expense arising out of the nature of the work or its prosecution, subject to conditions of the contract. The contractor must submit a detailed invoice to the Site Lead, Brian Turner, for payment at the following address: U.S. Army Corps of Engineers Gull Lake Recreation Area 10867 East Gull Lake Drive Brainerd, MN 56401 or emailed to brian.w.turner@usace.army.mil 2.1 Unit Prices: Payment items for the work of this contract are listed in the BIDDING SCHEDULE. The payment items provided for on the bidding schedule embody the work; but the work descriptions provided below do not specifically discuss all incidental work and materials required to complete the contract work. 3.0. RANGER OFFICE BUILDING: 3.1. Description: The Ranger Office Building is a one level cedar wood covered steel building that was converted into offices in the 1990's. The framework consists of red metal beams with steel sheeting attached to them. At the time of the conversion 2" x 6" studs were added with insulated walls creating approximately 2,400 square feet of office space/utility rooms and lunch room. Two layers of drop ceilings exist in the approximately 2,400 square foot original office space with fluorescent 2' x 4' light fixtures existing in the present drop ceiling and incandescent light fixtures still present in the original drop ceiling. The drop ceiling contains 28 (qty) 2' x 4' fluorescent hanging troffer light fixtures of which 8 have been recently upgraded to LED light fixtures. 4. SPECIFICATIONS: 4.1. Protective Coverings: The contractor shall cover all walls and floors with plastic or tarps to protect the walls and floors from damage during the removal of the ceilings and during spraying of the foam insulation. It is the contractors responsibility to remove any materials accidently sprayed on the walls or floors. 4.2. Removal of Drop Ceilings: The contractor shall supply all equipment, labor and materials required to remove and dispose of the two drop ceilings found in the original 2,400 square foot office space, which are approximately 60' by 40' each and consist of tile, grid, florescent and incandescent fixtures and light bulbs, and a 6" layer of fiberglass insulation above the second ceiling. All materials shall be disposed of in accordance with all required local and State of Minnesota disposal regulations. The current LED lights shall be removed, stored so as to avoid damage, and then reinstalled as part of section 4.6 bleow. 4.3. Rigid Insulation: The exterior walls of the building are insulated and sheet rocked from the floor to the height of the current drop ceiling. From the level of the current drop ceiling to where the wall and roof of the building meet the bare metal of the exterior wall is exposed. The Contractor shall cover this section of the exterior wall (from above the finished wall to the roof) with a sheet of 1 inch rigid foam insulation. The foam shall be fastened to the metal sheeting so that the spray foam can be applied to the rigid insulation and not directly to the metal exterior wall. The method used to fasten the foam panels to the exterior walls shall not puncture the exterior wall of the building. 4.4. Hardboard Roof Insulation Support: The Contractor shall secure the existing 1 inch hardboard insulation snuggly to the roof to obtain a flat surface prior to applying spray foam. The method of obtaining a flat surface is at the discretion of the contractor provided it does not damage or void the warranty on the existing roof. 4.5. Spray Foam: The contractor shall spray Closed Cell Spray Polyurethane Foam (here-in referred to as ccSPF) insulation to the underside of the steel roof that is directly over the 2,400 square feet of original building heated offices to obtain an R-Value of at least R49. The heated office area is approximately 60' by 40' and has interior walls composed of either tongue and groove wood paneling or.5 inch painted sheetrock. The interior of all exterior exposed walls within the offices, above the drop ceiling, shall sprayed with ccSPF insulation to totally envelope the walls and obtain an R-Value of at least R21 (excluding the ridged insulation panels). No gaps shall remain unsprayed between the insulated outer wall and the ceiling. It is the responsibility of the contractor to determine quantity prior to quoting the job, as no allowance will be made for any additional quantities required. The installing contractor shall have current industry recognized professional training or accreditation for high pressure spray polyurethane foam insulation. Proof of training or accreditation shall be provided at the pre-work conference. Upon completion of the foaming the contractor shall provide the park manager with a summary of the installation, including at a minimum: manufacturer of the insulation, R-Value of the product, date of installation, and the contractor's certification that the installation has been performed in accordance with local code requirements. Installation of the Spray Polyurethane Foam shall be in compliance with all federal, state, and local regulations, including, but not limited to, OSHA National Emphasis Program guidance on Isocyanates. Installation shall comply with all manufacturer's specifications for installation and utilize industry best practices. The contractor will be responsible for placement of health and safety barriers within the work zone. Contractor will be responsible for all clean-up, removal and disposal of materials associated with spray polyurethane foam installation including, but not limited to: decontamination of any surfaces that have come into contact with isocyanates or other ccSPF chemicals, all dust, debris, foam trimmings, empty and partially used containers or drums in accordance with applicable federal, state, and local requirements. Closed Cell Spray Polyurethane Foam Specifications: • Interior grade • Two-component closed-cell foam • High pressure application 4.6. Warranty: The contractor shall provide any warranty(s) offered by the manufacturer or which they provide to their other customers in excess of the one year mandated under contract clause 52.246-21 Warranty of Construction. 4.7. Drop Ceiling: After spraying the ceiling with insulation the contractor shall supply all equipment, labor and materials required to install drop ceiling tile and grid to the office space which is comprised of the approximately 2,400 square foot original office. The new ceilings shall be installed at the same height as the existing visible ceiling. The lunch room/utility room, office rooms and bathrooms all have ceilings that are approximately 8 feet high and the brochure room, lobby and conference room have ceiling that are approximately 10 feet high. Ceiling Tile Specifications: • 24" x 24" acoustic drop ceiling tiles for commercial settings • 9/16" inch edge profile • Composed of mineral fiber • Minimum 50% sound absorption • White color • Tegular edge lay-in • Class A fire retardant • Mold, mildew, and bacteria resistant • Fine, smooth style, non-directional texture similar to below picture: Ceiling Tile Grid Specifications: • Ceiling Tile Grid must be compatible with ceiling tile system • 9/16 Exposed Tee System • White powder coat or baked polyester paint • Hot dipped galvanized steel • Flush fitting • Intermediate to heavy duty classification for Office/commercial application 4.8. LED Lighting: The contractor shall supply all equipment, labor and materials required to supply and install the existing LED lights, new 24" by 48" LED Troffer lighting, and 6" LED Recessed Can lighting in the ceiling grids for each room. See attachment 13.6 Current Ceilings and New Lighting Layouts for location of the new lighting in each room. All lights shall be installed according to the National Electric Code. The existing LED lights in the office and ranger office are to be reinstalled in their current locations. Troffer Lighting: • 24 inch by 48 inch • White fixture trim • Edge lit recessed LED Troffer • Color temperature of 4,000 Kelvin • Color Rendering Index of 80 • Light output at least 4,500 (lumens) Recessed Lighting: • 6 inch diameter • White reflector cone and fixture trim • Color temperature of 5,000 Kelvin • Color Rendering Index of 90 • Light Output at least 730 (lumens) • 6 inch aluminum insulation contact (IC) housing • Housing shall be New Construction style, equipped with hanger bars 5. DESCRIPTION AND LOCATION. Gull Lake Recreation Area is a heavily utilized multi-purpose recreation area that includes: a campground with 42 campsites, boat ramp, swim beach, fishing piers, a dam, office and multiple restroom facilities. The Recreation Area is located 8 miles north of Baxter, MN off of Highway 371 on the SE side of Gull Lake. The address is: 10867 East Gull Lake Drive Brainerd, MN 56401. 6. CONTRACT PERIOD. All contract work must be completed by 30 November 2017. The Ranger Office will be occupied by 2 employees utilizing the space for office accommodations. Work will be scheduled and arranged to cause as little disruption to normal working conditions as possible. The general public shall be warned with signs &/or barricades and not be allowed in the work areas while work is being performed. 7. SAFETY. All work shall be performed in accordance with all federal, state and local laws and regulations and the Corps of Engineers Safety and Health Manual, EM-385-1-1. A copy of this manual can be found on line at http://www.publications.usace.army.mil/Portals/76/Publications/EngineerManuals/EM_385-1-1.pdf 8. ORIENTATION. Prior to the start of work, the Government will provide an orientation to the Contractor and contract personnel which will include discussion of contract requirements, facility inventory, safety considerations, quality control, security and administration. Contractors are encouraged to make a site visit to inspect the Ranger Office before submitting a quote. Visits can be prearranged by contacting Brian Turner at 651-290-5771 or by email at brian.w.turner@usace.army.mil Monday-Friday between the hours of 8:00 am and 4:30 pm. 9. WORK PLAN. The contractor shall submit a plan that details the sequence and scheduling of the proposed work during a Monday-Friday work week. The work plan shall be submitted within 10 days of notice to proceed. The work plan shall be discussed at the initial pre-construction meeting to be held at the Gull Lake Site. The "Work Plan" shall be approved prior to start of work. 10. DISPOSAL: All excess materials shall be disposed of off-site in accordance with all local, State and Federal Disposal Codes. 11. SECURITY: The Contractor is responsible for securing the work areas so that park visitors have to maintain a safe distance from all work areas. The Contractor is also responsible for securing the Rangers Offices when work is not being performed if Corps personnel are not present so that the offices are not vandalized during the construction phase. 12. WORK AREA: Any damages to Corps' property shall be repaired at the Contractor's expense.
 
Web Link
FBO.gov Permalink
(https://www.fbo.gov/spg/USA/COE/DACA37/W912ES17T0128/listing.html)
 
Record
SN04645294-W 20170826/170824232315-26e56df4ca88492c5f81312fbe08a99c (fbodaily.com)
 
Source
FedBizOpps Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's FBO Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.