SAMDAILY.US - ISSUE OF APRIL 24, 2021 SAM #7084
SOLICITATION NOTICE

J -- USNS HUNTER (TSV-3) Docking Phased Maintenance Availability (DPMA)

Notice Date
4/22/2021 2:59:04 PM
 
Notice Type
Solicitation
 
NAICS
336611 — Ship Building and Repairing
 
Contracting Office
MID ATLANTIC REG MAINT CTR NORFOLK VA 23511-2124 USA
 
ZIP Code
23511-2124
 
Solicitation Number
N50054-21-R-0005
 
Response Due
5/4/2021 12:00:00 AM
 
Archive Date
05/19/2021
 
Point of Contact
Veronica Johnson, Phone: 7574000214, Amy Caraway, Phone: 7574000173
 
E-Mail Address
veronica.johnson1@navy.mil, amy.caraway@navy.mil
(veronica.johnson1@navy.mil, amy.caraway@navy.mil)
 
Small Business Set-Aside
SBA Total Small Business Set-Aside (FAR 19.5)
 
Description
4/22/2021 The purpose of this Solicitation Amendment 0010 is to execute the following: Revise the performance start day of the avail to read June 21, 2021. Revise J-1 Pricing Workbook Rev-3. Revise J-3 Commencement and Completion Milestones USNS HUNTER Rev-4. Update Work Package Rev-1 Revise Section B, Notes Update Section J, List of Attachments. Provide Government Responses to S-7 Requests for Specification Clarification (Bidders Questions: 062 � 073) All other terms and conditions remain unchanged. 4/19/2021: The purpose of this Solicitation Amendment 0009 is to execute the following: Extend the proposal due date to May 4, 2021. Revise the Period of Performance to read June 27, 2021 to January 3, 2022. Revise J-1 Pricing Workbook Rev-2 Revise J-3 Commencement and Completion Milestones USNS HUNTER Rev-3. Revise Section C, Description/Specs/Work Statement Revise Section F, Delivery Information Revise Section J, List of Attachments Revise Section L, Instructions to Offerors. Revise Section M, Evaluation Factors for Award. All other terms and conditions remain unchanged. 3/15/2021: Amendment 0008 executes the following changes: 1. Correct administrative error to the Period of Performance end date to read September 17, 2021 to align with the attachment J-3 Commencement and Completion Milestones USNS HUNTER Rev-2. 2. All other terms and conditions remain unchanged. 3/9/2021: Amendment 0007 eecutes the following changes: 1. Extend the proposal due date to Thursday, March 18, 2021 at 12PM. 2. Revise the Period of Performance to September 19, 2021. 3. Revise Section J attachment J-3 Commencement and Completion Milestones USNS HUNTER. 4. All other terms and conditions remain unchanged. 2/25/2021: Amendment 0006 executes the following changes: 1. Provide Government Responses to S-7 Requests for Specification Clarification (Bidders Questions: 060 � 061). 2. All other terms and conditions remain unchanged. 2/24/2021: Amendment 0005 executes the following changes: 1. Provide Government Responses to S-7 Request for Speciication Clarification (Bidders Questions: 052-059). 2. Incorportate Errata 6 into the solicitation. 3. Add ERRATAs 1-6 to Section J, List of Attachments. 4. All other terms and conditions remain unchanged. 2/18/2021: Amendment 0004 executes the following changes: 1. Update Section L, Volume I, Technical, Factor II, a). 2. Extend the proposal due date to Friday, March 12, 2021. 3. Provide additional information to Bidders Question 012. 4. Attachment S-5 is updated to reflect the 18 Feet MLW based on Bidders Question 012. 5. Provide Government Responses to S-7 Requests for Specification Clarification (Bidders Questions: 016 � 051). 6. Incorporate Erratas 3, 4 and 5 into the solicitation. 7. Section J attachment J-1 Pricing Workbook and Labor and Material Rate (updated) in Amendment 0003. 8. Section J attachment J-3 Commencement and Completion Milestones USNS HUNTER (update) in Amendment 0003. 9. Section J attachment S-5 Eligibility Criteria Data Sheet (update) in Amendment 0004. � 10. All other terms and conditions remain unchanged. 2/10/2021: Amendment 0003 executes the following changes 1. Update Section L, Volume II, Factor VI � Past Performance 2. Update Attachment J-1, Pricing Workbook 3. Update Attachment J-3, Commencement and Completion Milestones 4. Provide additional information to Bidders Questions 002 � 010 which were initially addressed in Amendment 0002 5. Provide Government Responses to S-7 Requests for Specification Clarification (Bidders Questions: 011 � 015) 6. All other terms and conditions remain unchanged. ****** 2/9/2021: Amendment 0002 executes the following changes 1. Provide Government Response to S-7 Requests for Specification Clarification (Bidders Question: 002 - 010) �2. All other terms and conditions remain unchanged. ********* 2/8/2021: Amendment 0001 executes the following changes: 1. Update Section L, III. General Information A. Ship Checks 2. Provide Government Response to S-7 Requests for Specification Clarification (Bidders Question: 001) 3. Incorporate Erratas 1 and 2 into the solicitation; Errata 1 is the deletion of the work items and Errata 2 is the removal of fleeting from the 997-11-001 work item 4. All other terms and conditions remain unchanged. ******* Please see attached solicitation for USNS HUNTER(TSV-3) Docking Phased Maintenance Availability (DPMA). This�posting does not include all the relevant S & J attachments.� To receive access to Attachment S-5 Eligibility Criteria Data Form, Attachment J-1 (Pricing Workbook and Labor and Material Rate), Attachment J-2 (HUNTER TSV-3-MARMCN-501-21 SPEC Package), Attachment J-3 (Commencement and Completion Milestones USNS HUNTER), provide a written request to Contracting Officers, Amy Caraway at amy.caraway@navy.mil and Veronica Johnson at veronica.johnson1@navy.mil.� These attachments may be transmitted via email or DoD SAFE.�
 
Web Link
SAM.gov Permalink
(https://beta.sam.gov/opp/de3c3bc9cfa043bcb8ad6c6bd6883721/view)
 
Place of Performance
Address: Norfolk, VA 23511, USA
Zip Code: 23511
Country: USA
 
Record
SN05980228-F 20210424/210422230113 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  © 1994-2020, Loren Data Corp.