AWARD

96 -- Operations Division Rock Supply

Notice Date
6/16/2021 7:33:41 AM
 
Notice Type
Award Notice
 
NAICS
212319 — Other Crushed and Broken Stone Mining and Quarrying
 
Contracting Office
W07V ENDIST N ORLEANS NEW ORLEANS LA 70118-3651 USA
 
ZIP Code
70118-3651
 
Solicitation Number
W912P821C0028
 
Archive Date
06/30/2021
 
Point of Contact
Edith M Brandon, Phone: 5048621047, Stacie M. Osborne, Phone: 5048622615
 
E-Mail Address
edith.m.brandon@usace.army.mil, stacie.m.osborne@usace.army.mil
(edith.m.brandon@usace.army.mil, stacie.m.osborne@usace.army.mil)
 
Award Number
W912P821C0028
 
Award Date
06/15/2021
 
Awardee
Crowley Holdings, LLC New Orleans LA USA
 
Award Amount
1100200.00
 
Description
ITEM 001: The contractor will supply approximately 2 each loaded barges of B-size stone (or equivalent as approved by the government) to Schooner Bayou Control Structure located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive 2 barges at the same time. When unloading is near completion on the barges, the government will coordinate the pickup and return of the barge set.� ITEM 002: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery. ITEM 003: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to the Schooner Bayou Control Structure located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges. ITEM 004: The contractor will supply approximately 3 each loaded barges of B-size stone (or equivalent as approved by the government) to Freshwater Bayou Lock located at approximate Freshwater Bayou Channel Mile 1.5. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive all 3 barges at the same time. When unloading is near completion on the set of barges, the government will coordinate the pickup and return of the barge set. located at Schooner Bayou, 3.1 miles west of Freshwater Bayou Mile 15.9. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. ITEM 005: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery. ITEM 006: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to Freshwater Bayou Lock located at approximate Freshwater Bayou Channel Mile 1.5. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges. ITEM 007: The contractor will supply approximately 6 each loaded barges of B-size stone (or equivalent as approved by the government) to Catfish Point Control Structure located at Mile 24 of the Mermentau River, slightly west of Mermentau River/Grand Lake intersection. Each barge shall contain approximately 1,400 tons of Grade B stone (or equivalent as approved by the government). All delivered barges will start with a 5 day unloading period. All barges will be delivered at a coordinated period with the Government. The corps expects to receive 3 barges at the same time. When unloading is near completion on the barges, the government will coordinate the pickup and return of the barge set. ITEM 008: This item covers a demurrage 24 hour rental rate for each barge beyond the initial 5 days of barge delivery. This line will be activated only if the government holds any barge for longer than 5 days or 120 hours after its initial delivery. ITEM 009: This item covers the delivery of loaded barges AND the pickup/return of unloaded barges associated with the rock supply to the Catfish Point Control Structure located at Mile 24 of the Mermentau River, slightly west of Mermentau River/Grand Lake intersection. The barge unloading time is expected to take up to 12 total days total starting at the initial delivery time of barges.
 
Web Link
SAM.gov Permalink
(https://beta.sam.gov/opp/6b3bb21ccedf4b00accdb4fe9e9a9e5f/view)
 
Place of Performance
Address: New Orleans, LA 70118, USA
Zip Code: 70118
Country: USA
 
Record
SN06033079-F 20210618/210616230116 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.