Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF OCTOBER 20, 2021 SAM #7263
SPECIAL NOTICE

J -- 626-22-1-4138-0008 TRIENNIAL INSPECTION

Notice Date
10/18/2021 9:15:30 AM
 
Notice Type
Special Notice
 
NAICS
811310 — Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance
 
Contracting Office
249-NETWORK CONTRACT OFFICE 9 (36C249) MURFREESBORO TN 37129 USA
 
ZIP Code
37129
 
Solicitation Number
36C24922Q0018
 
Archive Date
12/17/2021
 
Point of Contact
John McDaniel, Contract Specialist, Phone: 615-225-6788
 
E-Mail Address
John.McDaniel1@va.gov
(John.McDaniel1@va.gov)
 
Awardee
null
 
Description
Page 6 of 7 DEPARTMENT OF VETERANS AFFAIRS Nashville VA MEDICAL CENTER STATEMENT OF WORK FOR Maintenance, Inspection, and Testing of the Electrical Power Distribution System 1. Introduction: This Statement of Work (SOW) describes the requirements for the maintenance, inspection, testing, operation and/or calibration of the Electrical Power Distribution System and all of its components at the TVHS, Nashville VA Medical Center, 1310 24th Avenue South, Nashville TN 37212. These work items are referenced as Maintenance and Testing in this document, hereafter. This SOW describes the requirements for the Qualified Electrical Contract Professionals known as Contractors in this document, hereafter. Contractors who are contracted by VA Medical Center to perform maintenance and testing of the Electrical Power Distribution System, and all of its components shall meet all requirements stated in Section 2 of this SOW. This SOW describes the requirements to establish maintenance and testing reports. 2. Qualifications of Contractors: Contractors shall be experienced Electrical Contractors, having properly trained and licensed permanent staff required to perform the proposed work. Electrical Contracting (i.e., the construction, repair, testing and maintenance of industrial and commercial electrical distribution systems) shall be the primary interest/specialty of the Contractor s business. Contractors shall be certified by the InterNational Electrical Testing Association (NETA) or equivalent certifying organization as Certified Technicians with each having completed the appropriate Occupational Safety & Health Administration (OSHA) approved construction safety training. Contractors shall have technical training and demonstrable track records of working experience in maintenance, inspection, and testing of the Electrical Power Distribution Systems and related components in healthcare, industrial, educational, and commercial facilities for a minimum of five (5) continuous years. Electrical components on which the Contractors have experience shall include, but not be limited to, switchboards & switchgear (low and medium voltage); low voltage controls; emergency and standby generators; automatic transfer switches, wiring, transformers, meters, and other electrical appurtenances. Contractors shall have safety trainings either on-the-job or class-room type - in electrical safety outlined in the OSHA Standard 29 Code of Federal Regulations (CFR) 1910 Subpart S Electrical, and the NFPA 70E Standard for Electrical Safety in the Workplace. Training certification shall be provided indicating each technician is a Qualified Person as defined by NFPA 70E. Training certifications shall be submitted to the VA Contracting Officer prior to work. If no training certifications are available, the contractor Employer shall certify that he/she has met this requirement in writing, and submit it to the VA Contracting Officer prior to work. Contractors shall have ready access to the latest versions of the following references: NFPA 70, National Electrical Code. NFPA 70B, Recommended Practice for Electrical Equipment Maintenance. NFPA 70E, Standard for Electrical Safety for the Workplace. NFPA 110, Standard for Emergency and Standby Power System. OSHA Standard 29 CFR 1910, Subparts I & S. InterNational Electrical Testing Association, Inc. (NETA) Maintenance and Testing Specifications. Operating /Maintenance manuals and specifications of the electrical equipment to be maintained and tested. These documents may be obtained from the VHA Medical Center, or the equipment manufacturers. VHA Directive [2006-056][1028], Electrical Power Distribution System E. Contractors shall have and provide all necessary tools, equipment, and Personal Protective Equipment (PPE) to perform the work safely, effectively, and timely. Tools, equipment, and PPE shall comply with the requirements of OSHA Standard 29 CFR 1910, Subpart I, and NFPA 70E. Prior to initiating work, Contractor Shall do a walk thru to verify all different manufacturers of equipment and shall provide documentation that all instruments, test equipment, tools and PPE have current calibration and are manufacturer compliant. Dated calibration labels shall be visible on all instruments, test equipment, tools, and PPE as appropriate. 3. Summary of Work: The Contractor shall provide a proposed schedule within 5 working days of bid award. The schedule shall be in the form of a progress chart of suitable scale to indicate the work scheduled for completion by any given date during the work period.; Due to the power outages required for maintenance and testing, and the power requirements for the medical center, all outages and testing are to be coordinated and scheduled with the Contracting officer representative, Electrician Supervisor and The Maintenance and operation supervisor, any requirements for adjusting the schedule (e.g. to minimize disruption to the VAMC) shall be incorporated by the Contractor. VA shall indicate approval or disapproval of schedule within five (5) calendar days. Outages shall be scheduled only after the facilities normal working hours of 8a-4:30p and on weekends. Contractors shall report deficiencies that are deemed critical or catastrophic immediately to the Contracting Officers Representative and or the Electric Shop Supervisor or the Maintenance and Operations Supervisor for immediate actions. Work items, definitions, and references shall comply with the latest edition of the NETA Maintenance Testing Specifications (MTS) and with the VHA Directive, Electrical Power Distribution System. . Below [Attached] is a list of electrical equipment that shall be maintained and tested: Switchgear and Switchboard Assemblies. Transformers, Dry Type, Air-Cooled, Low-voltage, Small. Transformers, Dry Type, Air-Cooled, Low-voltage, Large. Transformers, Liquid-Filled. Voltage regulators-single phase step type, medium voltage Calibration of medium voltage regulators is required to ensure proper voltages at building switchboards. Metal Enclosed Busways. Switches, Air, Low-Voltage. Switches, Air, Medium-Voltage, Metal-Enclosed. Switches, Oil, Medium-Voltage. Switches, Vacuum, Medium-Voltage. Switches, SF6, Medium-Voltage. Circuit Breakers, Air, Insulated-Case/ Molded-Case. Circuit Breakers, Air, Low-Voltage Power. Circuit Breakers, Air, Medium-Voltage. Circuit Breakers, Vacuum, Medium-Voltage. Protective Relays, Mechanical, and Solid State. Protective Relays, Microprocessor Based. Grounding Systems. Ground-fault Protection Systems. Motor Control, Motor Starters, Low-Voltage. Motor Control, Motor Starter, Medium-Voltage. Emergency Systems, Engine Generators. Operational functional tests only, load bank test are completed under a service contract. Emergency Systems, Automatic Transfer Switches. All maintenance, testing and functional tests of the transfer switches are to be performed by a manufacturers factory trained and authorized service technician. Manholes and associated underground cables and connections. Unit substation, battery charger, battery cleaning and battery load testing. . Government Furnished. Inventory of Electrical Power Distribution System equipment to be maintained, inspected, and tested under this Scope of Work. Due to current construction projects, expect changes in the inventory, the most recent copy will be provided to the contractor prior to the start of the contracted maintenance and inspection. One-line and other informational drawings of the Electrical Power Distribution System. These drawings are not certified as-built drawings. Due to construction projects, expect changes in the one line diagram. Electrical Power System study information relevant to the scope of effort, such as coordination study data, short circuit analysis, arc-flash hazard analysis and available protective device setting information. Infra-Red Scanning/Thermo graphic Survey shall be performed on all electrical equipment. Use an infra-red scanning camera to detect hot spots in the Electrical Power Distribution System. Objective of this work is to detect any loose, broken, overloaded or corroded connections in the system. Survey will be conducted during the hours of 9am-3pm Monday-Friday during the times of peak load. Note that since this work item must be done while the Electrical Power Distribution System is energized, appropriate safety precautions with proper PPE must be taken before, during and after scanning the system. Contractor shall provide 2 separate hard copy reports on the Infra-Red/Thermo graphic study indicating all detected items needing corrections. Include thermal images of detected items within the report and recommendations for correction. System Function Tests. Provide function test for all equipment listed in this Scope of Work. 4-Hour Power Outage Test The Contractor shall be present for and will participate in the VAMC 4-hour test of the Essential Electrical System (EES). This test shall fulfill the requirements of VHA Directive, Electrical Power Distribution System, NFPA 110 (e.g., Para. 8.4.9.) and The Joint Commission. This test will be in conjunction with the testing and maintenance of the facilities Unit Sub-station equipment and will include opening of all utility service connections serving the VAMC for a minimum of 4-hours. During the test period, verify operation of all EES components including the transfer to emergency power and return to normal service. The Contractor shall include in their bid proposal all costs associated with the services of the local utility company for the duration of the test. The estimated duration of the Contractor s involvement is between 8 12 hours. The Contractor shall assist the VAMC staff with troubleshooting and correcting malfunctioning electrical equipment discovered during the test. Contractor shall record hourly generator stats and make any required adjustments and/or re-calibrations to all equipment which has been otherwise maintained, inspected, and tested under this Scope of Work.] The Contractor shall provide a separate document stating the completion of the EES system outage test. Summary of Work: A. A complete written report of the work performed shall be provided to the VA within 7 working days of contract work completion. Information shown in the report shall meet the following: Company s name, addresses, telephone, & FAX numbers. Name and signature of contractors who perform the maintenance and testing. VA Work Contract Number, name, and number of VA Contracting Officer. Date and Time of work. Copies of contractors valid licenses, professional and training certificates. Descriptions and model number of specialized tools and equipment used, such as torque wrench or infra-red scanning camera. Equipment items shall be listed in the report in a manner as the distribution system is installed (MV equipment, Bldg. MV equipment, switch boards, switch board breakers, panels, panel breakers, switches etc. Location, Type, Name, and nameplate information of electrical equipment maintained and tested. Descriptions of work items. Test data. Reference materials such as equipment manufacturer s specifications, coordination study, etc. Remarks on conditions of electrical equipment. List all deficiencies, if any. Recommended corrective actions, if any. B. Submit two (2) hard copies of the complete written report, and one (1) CD-ROM or DVD of the electronic version of the report in Microsoft Word format to the Contracting Officers Representative (COR) within seven (7) calendar days of contracted work completion. All reference materials shall be included in the electronic version of the report, either through scanning or other means of electronic text import methods. END
 
Web Link
SAM.gov Permalink
(https://beta.sam.gov/opp/18123578c1444b5c9db69261b6db0597/view)
 
Record
SN06159138-F 20211020/211018230112 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.