Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF NOVEMBER 04, 2021 SAM #7278
SOURCES SOUGHT

99 -- Red Rock SE Des Moines Pump Station Rehabilitation

Notice Date
11/2/2021 1:41:38 PM
 
Notice Type
Sources Sought
 
NAICS
237310 — Highway, Street, and Bridge Construction
 
Contracting Office
W07V ENDIST ROCK ISLAND ROCK ISLAND IL 61299-5001 USA
 
ZIP Code
61299-5001
 
Solicitation Number
W912EK-22-PUMP-STATION-REHAB
 
Response Due
11/8/2021 10:00:00 AM
 
Archive Date
11/23/2021
 
Point of Contact
Troy Robbins, Phone: 3097945205, Joseph Porter, Phone: 3097945333
 
E-Mail Address
troy.a.robbins@usace.army.mil, joseph.e.porter@usace.army.mil
(troy.a.robbins@usace.army.mil, joseph.e.porter@usace.army.mil)
 
Description
Sources Sought/Request for Information Red Rock SE Des Moines Pump Station Rehabilitation� Purpose and Objectives: � The purpose of this notice is to obtain information regarding: (1) the availability and capability of qualified small business sources; (2) whether they are small businesses; HUBZone small businesses; service-disabled, veteran- owned small businesses; 8(a) small businesses; veteran-owned small businesses; woman-owned small businesses; or small disadvantaged businesses; and (3) their understanding, capabilities and experience relative to the proposed acquisition to assist the Government in determining the expectation of receiving bids from responsible small business contractors at fair market prices. Your responses to the information requested will assist the Government in determining the appropriate acquisition method, including whether a set- aside is possible. An organization that is not considered a small business under the applicable NAICS code can submit a response to this notice, however their capabilities may/may not be assessed for the purposes of this notice.� A determination by the Government not to compete this requirement as a set-aside based upon responses to this Notice is solely within the discretion of the Government.� The Corps of Engineers (COE), Rock Island District does not intend to award a contract on the basis of responses received, however as a result of this Sources Sought Notice, the COE may issue a Request for Proposal (RFP).� Interested parties are expected to review this Notice and the Project Requirements to familiarize themselves with the requirements of this project.� Background: � � The Red Rock Southeast Des Moines Pump Station was federally constructed in 1968 and is federally operated. �It is located on the left descending bank of the Des Moines River, approximately 0.3 miles upstream of the confluence of the Des Moines River and Four Mile Creek. �The pump station forebay and surrounding area has exhibited visible seepage distress as a result of flood events in the past decade as well as deflection of the forebay wing wall sections. �This project also includes construction work in and around the pump station building to address maintenance and operation concerns related to this 50 year old structure. � � � Project Requirements:� This project will include the installation of approximately 1000 feet of vinyl or steel sheet pile. � This project will also include pump station rehabilitation to include demolition, excavation, material compaction and grading, concrete work, metal fabrication work, mechanical work, Electrical work, CCTV, process controls, geotextile, aggregate and riprap, site restoration, and seeding.� NAICS Code and Size Standard: � In the event an RFP is issued, North American Industry Classification System (NAICS) code 237310 with a size standard of $36.5M is being considered.� Solicitation Type: �The Government is considering using a Lowest Price Technically Acceptable or Best Value Trade Off Method for solicitation of this project. �Potential evaluation factors could be Technical; to include, High Water Contingency, Dewatering Experience and Planning, and Confined Space experience/capabilities; Price; Past Performance and Small Business Participation. �Please provide any feedback on the potential solicitation and evaluation method, as well as appropriate provisions and considerations for these types of solicitations and evaluations, from an industry perspective. Capability Statement/Information Sought:� All parties interested in this project must demonstrate that they would have the potential to be a responsive and responsible contractor for the following project technical criteria� Tailored Capability Statements shall demonstrate a clear understanding of all tasks specified in the draft Project Requirements. Tailored Capability Statements for this requirement shall address the following areas:� 1. Company Name, DUNS/CAGE (If your company does not have at the time of this sources sought, please be aware that you will be required to register your company in the System of Award Management (SAM) system to be eligible for any future Federal contracts), POC information including an email, and your current small business status. 2. �Demonstrate the ability to meet the mandatory criteria as noted below: ��� �Experience performing work in a confined space. ��� �Cofferdam design, installation, sealing, and dewatering capability. ��� �Experience with high-water remediation which may impact work activities. ��� �Experience installing vinyl sheet pile.� 2. Project examples with similar complexity and scope (and ideally including all of the mandatory criteria above). �Examples should include all pertinent information regarding the requirements to clearly demonstrate the understanding and abilities of your company. �If you performed previous work as a part of a team, with subcontractors (or other arrangements) please provide information on that relationship, tasks performed by team members etc. to be able to provide the Government with a sense of prime contract management as well as team member/subcontractor management. 3. �Description of how, as a small business, you would be capable of performing the work, either by 100% self-performance or through teaming. �Specifically, if you would not be self-performing 100% of the work, please provide: ��� �An estimate of your self-performance and a proposed team approach (for example: �are you part of an approved mentor prot�g� team through the SBA 8(a) or All Small Mentor Prot�g� Program? � ��� �Will you be teaming with other small businesses to meet the self-performance requirements? ��� �Will your subcontractors be primarily small businesses?� ��� �What type of work would likely be subcontracted? �� ��� �Have you performed this type of work previously with similar teaming arrangements? �If so, what were issues with contract performance? �� ��� �NOTE: �Small businesses may submit a capability statement that includes the expertise of large business partner companies under a teaming arrangement. If a teaming arrangement is contemplated, then the response to this sources sought must clearly discuss the areas of the Draft Performance Work Statement that the small business firm intends to perform and the specific areas that the large business teaming partner intends to perform. Please note that at least 15% of the total cost of the contract value must be incurred by or for personnel of the small business firm (or similarly situated entities) pursuant to the FAR clause at 52.219-14 entitled �Limitations on Subcontracting (NOV 2011)�.� In order for the Government to make a Small Business (SB) set-aside (or other socioeconomic sub-category) determination, it is emphasized that SB concerns provide sufficient written information to clearly demonstrate their capacity, capability, and responsibility (in accordance with FAR 9.1 and the requirements at FAR 19.502(b)(1) to successfully perform and manage all the requirements of this effort. Information Submission Instructions:� 1. Page Limitations:� Interested qualified small business organizations should submit a tailored capability statement for this requirement not to exceed twenty (20) single sided pages including all information that clearly details the firm�s ability to perform the aspects of the notice described above and in the Project Requirements.� 2. Number of Copies:� All capability Statement sent in response to this SOURCES SOUGHT/Request for Information notice must be submitted via e-mail to the contract specialist, Joseph Porter at �joseph.e.porter@usace.army.mil �and Deputy, Small Business Programs Troy Robbins�at Troy.A.Robbins@usace.army.mil. The e-mail subject line must specify Response to Sources Sought: �Red Rock SE Des Moines Pump Station. � 3. Due Date/Time� Electronically submitted tailored capability statements are due no later than November 8th 2021 however this does not restrict the Government from accepting responses after this time, if it is in the best interests of the Government for market research purposes, and also does not prohibit the Government from seeking potential capable, and responsible sources from information available from other resources (for instance: �small business databases, known sources, previous contractors) to determine a final procurement strategy. �
 
Web Link
SAM.gov Permalink
(https://beta.sam.gov/opp/51af926aa5cb4234bf5e46ef6b3428f4/view)
 
Record
SN06169554-F 20211104/211102230118 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.