Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF JUNE 28, 2022 SAM #7515
MODIFICATION

Z -- GAOA SFK DRY BLOOD DAM RECONSTRUCTION

Notice Date
6/26/2022 6:11:34 AM
 
Notice Type
Solicitation
 
NAICS
237990 — Other Heavy and Civil Engineering Construction
 
Contracting Office
NATIONAL OPERATIONS CENTER DENVER CO 80225 USA
 
ZIP Code
80225
 
Solicitation Number
140L0622R0038
 
Response Due
8/3/2022 1:00:00 PM
 
Archive Date
08/18/2022
 
Point of Contact
Roush, Nathan, Phone: (303) 236-2211, Fax: (303) 236-9470
 
E-Mail Address
nroush@blm.gov
(nroush@blm.gov)
 
Small Business Set-Aside
SBA Total Small Business Set-Aside (FAR 19.5)
 
Description
The Bureau of Land Management (BLM) has a construction requirement for all labor, materials, equipment, and supervision to repair South Fork Dry Blood Dam located in Petroleum County, approximately 14 miles north of Winnet, MT. The requirement entails the following significant tasks: 1. Dewater reservoir and construction area. 2. Excavate a portion of the existing dam embankment and foundation to remove the existing primary spillway. 3. Reconstruct the dam embankment, including: a. Placement of compacted fill from onsite borrow sources, b. Placement of compacted lime amended fill, c. Placement of imported erosion protection within excavated areas of the upstream face, d. Placement of erosion protection matting within excavated areas of the downstream face, e. Placement and compaction of imported sand and gravel for internal filter and drain features. 4. Construct a precast concrete spillway riser for a new principal spillway. 5. Construct concrete encased, precast reinforced concrete pipe outlet conduit. 6. Construct precast concrete low-level inlet structure. 7. Construct a grouted riprap stilling basin. 8. Place road gravel surfacing along the crest of the dam. 9. Construct a temporary construction access road from Valentine Rd. to the dam embankment crest, as necessary. 10. Construct improvements to the auxiliary spillway upstream and downstream of the dam centerline. 11. Remove existing barb wire fencing and cattle guards in the vicinity of the dam. 12. Install a cattle new cattle guard on Valentine Rd. and construct a new barb wire fence. 13. Reclaim all disturbed areas, including staging areas and temporary roads. Reclamation consists of preparation of the soil for seeding but does not include seeding.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/7da99fe53c364bf8a123e6b02ca227d4/view)
 
Record
SN06369339-F 20220628/220626230102 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.