Z -- FY22: NRM Tier 2 (PROJ: 672-22-604) DB - Replace Facility Main Feeders at San Juan VAMC.

Notice Date
7/5/2022 11:51:29 AM
 
Notice Type
Solicitation
 
NAICS
236220 — Commercial and Institutional Building Construction
 
Contracting Office
248-NETWORK CONTRACT OFFICE 8 (36C248) TAMPA FL 33637 USA
 
ZIP Code
33637
 
Solicitation Number
36C24822R0102
 
Response Due
7/8/2022 12:30:00 PM
 
Archive Date
08/07/2022
 
Point of Contact
Rey F Clemente, Contract Specialist
 
E-Mail Address
rey.clemente@va.gov
(rey.clemente@va.gov)
 
Awardee
null
 
Description
Request for Information and Government Responses for Solicitation Number: 36C24822R0102 FY22 NRM TIER 2 (PROJ 672-22-604) DB Replace Facility Main Feeders at VACHS, San Juan, PR 00921-3201: Does the feeder s replacement include the grounding conductor also? Government Responses: Yes, the feeders consist of 3 live cables, including a ground conductor. The ground conductors need to be replaced also. The grounding conductor is essential part of the electrical system of the feeders, in accordance with Specification 26 05 13 Medium-Voltage Cables paragraph 1.2. located in page 1 of 11 pages as shown in referenced subparagraph A. Section 26 05 11 A and Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: Requirements that apply to all sections of Division 26. Subparagraph B. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for personnel safety and to provide a low impedance path for possible ground fault currents. Also, this requirement is in provided Scope of Work (SOW), paragraph 2.f. located in page 10 of 90 pages: All electrical equipment and components associated with the feeder s replacement shall be furnished by D-B Team including new splices and miscellaneous electrical equipment if necessary. The project will include the following, in accordance with the SOW, Section 2, paragraph a located in page 10 of 90 pages: Replacement of all normal power feeders form the main substation to all existing substations on the facility. New feeders shall be rated at 15 KV. Drawings are available for D/B Firm to verify route, length, and capacity of each feeder, but it is the responsibility of the D/B Firm to validate the information on them. Work shall be performed without interrupting normal operations of the facility. Also, with the SOW, Section 2, paragraph d. Replacement of all standby power feeders from paralleling switch gear to all existing substations on the facility. New feeders shall be rated at 15 KV. Drawings are available for D/B Firm to verify route, length, and capacity of the feeder, but it is the responsibility of the D/B Firm to validate the information on them. Work shall be performed without interrupting normal operations of the facility and stand by power capability.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/6cc862d81f82499c8022c60d845f5d78/view)
 
Record
SN06378053-F 20220707/220705230057 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.