SOLICITATION NOTICE

C -- PBA Substation Repair

Notice Date
1/3/2023 8:51:35 AM
 
Notice Type
Solicitation
 
NAICS
237130 — Power and Communication Line and Related Structures Construction
 
Contracting Office
W6QK ACC-RI ROCK ISLAND IL 61299-0000 USA
 
ZIP Code
61299-0000
 
Solicitation Number
W519TC23B2001
 
Response Due
1/20/2023 10:00:00 AM
 
Archive Date
02/04/2023
 
Point of Contact
Jadwiga Baranowski, Phone: 3097825839, John Fotos
 
E-Mail Address
jadwiga.b.baranowski.civ@army.mil, john.g.fotos.civ@army.mil
(jadwiga.b.baranowski.civ@army.mil, john.g.fotos.civ@army.mil)
 
Description
NARRATIVE AMENDMENT 0001 1. The purpose of Amendment P0001 of Solicitation W519TC-23-B-2001 is to change the timeline to be as follows: Solicitation issued: 22 December 2022 Deadline for Registering for Site Visit � 12 January 2023 @ 1:00 PM CT Site Visit � 18 January 2023 @ 9:00 AM CT Questions from Site Visit due by � 20 January 2023 @ 4:00 PM CT Technical Proposals (Step-One) Closes � 3 February 2023 @ 1:00 PM CT Price Bid (Step-Two) Closes � 24 February 2023 @ 1:00 PM CT Bid Opening via Microsoft Teams Teleconference - 28 February 2023 9:00 AM CT 2. All other terms and conditions of this solicitation remain unchanged. NARRATIVE 1. The U.S. Army Contracting Command � Rock Island (ACC-RI) issues Invitation for Bid (IFB) W519TC-23-B- 2001 for the repair of two substations (Substation �B� and Substation �C�) located at Pine Bluff Arsenal in Pine Bluff, Arkansas. All work shall be completed in accordance with Attachment 0001 � Scope of Work (SOW). 2. This IFB is issued as a Women-Owned Small Business (WOSB) Eligible Under WOSB Program Set Aside. It is anticipated that a single Firm Fixed Price (FFP) type contract will be awarded to the responsive, responsible bidder whose bid represents the lowest priced, technically acceptable bid. This IFB is issued using the Two-Step Sealed Bidding Method. See Section 00 21 13 � Instructions to Bidders within this solicitation for the Technical Requirements and Evaluation Criteria for Step-One. 3. A pre-construction site visit is scheduled for 9:00 AM CT on 04 January 2023. All interested contractors are encouraged to attend the site visit. See SITE VISIT INFORMATION for more information. USG will not answer any questions at the site visit. Contractor questions regarding solicitation and work solicited in the SOW are due to the POCs listed below no later than COB 06 January 2023 in order to assure that all Contractor questions can be answered and posted for all Contractors knowledge prior to the closing of Step-One, Technical Proposal. 4. Technical proposals (Step-One) shall not include prices or pricing information. Technical proposals are due by 1:00 PM CT on 20 January 2023, and shall be emailed to the following POCs: Jadwiga Baranowski at jadwiga.b.baranowski.civ@army.mil John Fotos at john.g.fotos.civ@army.mil 5. Only bids based upon technical proposals (Step-One) determined to be acceptable, either initially or as a result of discussions, will be considered further for award into Step-Two. Each bid in the second step must be based on the bidder�s own technical proposal. Bidders shall submit bids that are acceptable without additional explanation or information. The Government may make a final determination regarding a technical proposal�s acceptability solely on the basis of the bid as submitted. The Government may proceed with Step-Two without requesting further information from any bidder; however, the Government may request additional information from bidders that it considers reasonably susceptible of being made acceptable, and may discuss bids with the prospective bidders. 6. A notice of unacceptability will be forwarded to the Bidder upon completion of the technical proposal evaluation (Step-One) and final determination of unacceptability. 7. Bidders are cautioned to ensure their Step-Two bids are fully complete, including all fill-ins. Any bidder submitting a bid agrees by submission that their bid and the prices contained therein will be valid for 60 days after receipt of bids. 8. Bids from eligible bidders are due 2:00 PM CT on 10 February 2023 (Step-Two). Contractor bid submission shall be emailed to: Jadwiga Baranowski at jadwiga.b.baranowski.civ@army.mil John Fotos at john.g.fotos.civ@army.mil The Bid Opening will take place at 9:00 AM CT on 14 February 2023. See Bid Opening for more details. 9. The prevailing Davis-Bacon Act for wage determination will be incorporated into the resultant contract and will be in effect for the entire performance period of the resultant contract. The most recent wage determination can be found online at https://www.wdol.gov/dba.aspx or see Attachment 0002 � Davis Bacon Wage Determination. If the wage determination is revised during the period of performance, it shall be provided to the contractor through modification to the resultant contract. 10. Timeline: Solicitation issued: 22 December 2022 Deadline for Registering for Site Visit � 29 December 2022 @ 1:00 PM CT Site Visit � 04 January 2023 @ 9:00 AM CT Questions from Site Visit due by � 06 January 2023 @ 4:00 PM CT Technical Proposals (Step-One) Closes � 20 January 2023 @ 1:00 PM CT Price Bid (Step-Two) Closes � 10 February 2023 @ 1:00 PM CT Bid Opening via Microsoft Teams Teleconference-14 February 2023 9:00 AM CT 11. This executive summary is provided as an administrative convenience and is not intended to alter the terms and conditions of the IFB in any way. Any inconsistencies between this executive summary and other IFB provisions shall be resolved in favor of the other IFB provisions. 12. The POCs for this IFB are Jadwiga Baranowski, Contract Specialist at jadwiga.b.baranowski.civ@army.mil and John Fotos, Contracting Officer at john.g.fotos.civ@army.mil
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/5d03afe09d004129b013bf31cdfd8ae2/view)
 
Record
SN06554879-F 20230105/230103230103 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.