Loren Data's SAM Daily™

fbodaily.com
Home Today's SAM Search Archives Numbered Notes CBD Archives Subscribe
SAMDAILY.US - ISSUE OF MAY 24, 2023 SAM #7848
SOLICITATION NOTICE

Z -- 635-18-108 - Correct Domestic Hot Water Distribution System Deficiencies (VA-22-00087870)

Notice Date
5/22/2023 9:14:50 AM
 
Notice Type
Solicitation
 
NAICS
237110 — Water and Sewer Line and Related Structures Construction
 
Contracting Office
NETWORK CONTRACT OFFICE 19 (36C259) Greenwood Village CO 80111 USA
 
ZIP Code
80111
 
Solicitation Number
36C25923R0072
 
Response Due
6/21/2023 1:00:00 PM
 
Archive Date
07/21/2023
 
Point of Contact
Joseph (Joe) N Wingfield (CO), Contract Officer
 
E-Mail Address
joseph.wingfield@va.gov
(joseph.wingfield@va.gov)
 
Small Business Set-Aside
SDVOSBC Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
 
Awardee
null
 
Description
May 2020 635-416 Construct Mental Health Tower Page 8 of 15 Statement of Work (SOW) for Professional Services Oklahoma City Department of Veterans Affairs Medical Center 921 NE 13th St Oklahoma City, Oklahoma 73104 Project Title: Correct Domestic Hot Water Distribution System Deficiencies VA Project Number: 635-18-108 The Department of Veterans Affairs, Veterans Health Administration (VHA), hereafter referred to as the VA , VAMC , or the Government , is seeking General Contractor firms to provide all construction services for the project Correct Domestic Hot Water Distribution System Deficiencies, hereafter referred to as the Project at the VA Medical Center (VAMC) in Oklahoma City, Oklahoma. The construction contractor team responsible for the execution of the Project will hereafter be referred to as the Contractor . It is the intent of this solicitation to follow the design and specifications attached with the SOW. Verification of all existing site conditions shall be done and reflected in the Contractor s proposal. Anything overlooked or not included in the proposal required for code compliance should be verified and promptly reported to the COR. Contractor shall remedy at no additional cost to the Government.   SCOPE OF WORK: The scope of this work entails improvement to the domestic hot water VA Legionella Directive and Latency deficiencies at the Oklahoma VA Medical Facility. Work will follow all Oklahoma VA Infection Control requirements. Coordinate and schedule all water and necessary utility shutoffs with COR. Demolition: All interior partitions, ceilings, flooring including all terrazzo bases necessary to access relevant scope content. See plumbing narrative and drawings for extent of plumbing and possible medical gases demolition Electrical elements as listed in the drawings (wiring, panels, transformers, switch panels, lighting, outlets, etc.) Mechanical units and ductwork necessary to facilitate the domestic water distribution service in its new function, see mechanical narrative and drawings for extent of mechanical demo Architectural: Layout will be as shown on the drawings to provide the construction and correction of corresponding domestic water distribution in accordance with construction documents. Construction including replacement and repair of all metal framing, insulation, drywall, hollow metal frames, acoustical suspended ceilings, custom casework, fire extinguisher cabinet, signage and related toilet and room or adjacent area accessories affected by work or damage by Contractor. Interiors: Finishes include painting, and full replacement or repair to plastic laminate casework, wall protection, rubber base, solid surface, vinyl composition tile, welded sheet flooring, luxury vinyl tile and porcelain tile affected by work or damage by Contractor. FF&E: Furnishings and Equipment included in the construction documents is based on VA standards. The list of equipment and furnishes to be provided is listed in the construction documents. The contractor shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of this project. 1. Building #1, Room SB100: Replace existing building #1 tube style steam to water heat exchanger skid with new tube style steam to water heat exchanger skid (HEX-1). Reconnect to existing piping. Add expansion tanks (ET-1, ET-2) to both HEX-1 and existing laundry heat exchanger skid. Replace existing hot water recirculation pumps with new (P-1, P-2, P-3). Connect to existing piping. 2. Building #1, Room BF155: Replace existing ER wing vertical steam to water heat exchanger with a new vertical steam to water heat exchanger skid (HEX-6). Connect to existing piping. Replace existing hot water recirculation pump with new (P-8). Connect to existing piping. 3. Building #1, Room BF118: Replace existing E and F wing vertical steam to water heat exchangers with new vertical steam to water heat exchanger skids (HEX-2, HEX-3). Connect to existing piping. Replace existing hot water recirculation pumps with new (P-5, P-6, P-7). Connect to existing piping. Replace existing steam condensate pump with new (SP-2). Connect to existing piping. 4. Building #19 (Research), Room GR106: Replace existing Building #19 vertical steam to water heat exchangers with new vertical steam to water heat exchanger skids (HEX-4, HEX-5). Connect to existing piping. Replace existing hot water recirculation pump with new (P-4). Connect to existing piping. Replace exiting steam flash tank and steam pump with new (FT-1, SP-1). Connect to existing piping. Relocate and replace existing hydronic hot water pumps with new (P-10, P-11). Install new piping from existing to new pump locations. Relocate and replace existing chilled water pump with new (P-9). Install new piping from existing to new pump location. Add new Phigenics PWA water monitoring and analytics station (like existing in building #1) to the hot water generation plant as shown on the plans. Contractor to contact and purchase all water monitoring equipment from Phigenics, contact information on plans. 5. Building #1 and building #19, throughout building: Add new thermostatic mixing valve to lavatory, hand sink, lab sink, scrub sink, kitchen sink, eye wash station, hose bibb, etc. throughout the building as shown on plans. All fixtures may not be shown on plans due to volume and lack of access to hospital areas during visits. Replace all water supply stops and supply lines. Add new thermostatic mixing valve and trim to existing showers throughout the building as shown on the plans. All showers may not be shown on plans due to volume and lack of access to hospital areas during visits. Contractor to coordinate access to each shower on a case-by-case basis, whether it s through the front or back of the shower wall. Replace existing sink/lavatory faucets were shown on plans. Set new faucets to purge branch lines at times deemed feasible by COR and hospital staff. All fixtures may not be shown on plans due to volume and lack of access to hospital areas during visits. Add additional hot water recirculation piping and balancing valves as shown on the plans. Connect to existing piping. Add additional zone/wing shut off valves to existing domestic water piping as shown on plans. Add new Phigenics water monitoring and communication system at points shown on the plans. These new monitoring points are to be added to the existing monitoring report. Real time access to this report is to be given to OKC VA engineer on staff, as well as anyone else requested by the COR. Contractor to contact and purchase all water monitoring equipment from Phigenics, contact information on plans. Phasing: The areas adjacent to the proposed addition shall be continuously occupied by the OKC VAMC. The Contractor shall implement phasing to ensure that the construction will not impact or impede the VAMC s mission to care to the Veterans. The contractor shall provide quality control of all work conducted and the individual appointed shall be competent and educated/experienced in the field of work this scope encompasses. Codes and Standards: The Contractor shall follow all applicable codes and standards to this type of work including but not limited to Health Care System Memorandums (HCSM), OSHA Guidelines, NFPA 101, NFPA 70, Lock-out-Tag-out, and Rules of Station. ADENDUM- Pre-Construction Request for Information (PRFI): There are areas of the hospital that have been updated/remodeled since the issued date on the Contract Documents. Were the changes shown accounted for in the other projects? Please confirm and provide the areas that do not need to be addressed. Response: 5 East, 7 East, B-mod and 7F will not be a part of the solicitation. We can go over the drawings on a call to further inform you on these areas. Replacing the mixing valves in the showers will require demolition of the tile if there is not access from the backside. If the tile is discontinued and cannot be matched, what is the direction? Response: The intent on replacing the shower valves was to access from the backside without need for tile demolition. There are multiple foot pedal operated faucets throughout the hospital with the hot and cold stops located at the base of the wall. Will these require to be relocated higher or remain in the existing location? Relocating them will be much more intrusive. Please advise. Response: Existing stop locations to remain. BF118 - In the basement, there is a 3"" Hot water and 4"" Cold water shown for us to tie into for a bypass. We were unable to find these lines. Please advise. Response: Locate nearest minimum 2"" DCW/DHW riser serving area outside emergency wing for bypass. There are several locations throughout the building that have mop sinks that are not marked to have their faucets replaced. Should they be changed? Response: No faucets to be changed out for mop basins or HAC closest unless specifically shown on plans. What is the required flow rate of the branch line balancing valves? Should there be any balancing valves on the main lines? Response: Minimum branch flow rates to be 0.5 gpm. Overlapping work. There are several locations throughout the building where some of the work listed on these prints has already been done or is updated, i.e., new construction areas, ball type SOVs already installed where new ones are called out. Is the intent to carry on with the scope of the prints or will this need to be assessed as discovered for the duration of the project? Response: Refer to question 1. There are a few locations where there are existing sinks that are not called out for any changes to be made that don t seem to have been updated recently or aren t shown on the prints at all. Do these need to have new faucets/mixing valves added? Some are mop/service sinks. Response: No faucets to be changed out for mop basins or HAC closest unless specifically shown on plans. BF144C sink is called out for new faucet and mixing valve with keyed note 2 on sheet M201. Sinks/Lav off hallway C4B4 callout out for new faucets and mixing valves with keyed note 1 on sheet M702. On the Dead Leg at this location, should the new shutoff valve for future use be installed in the hallway instead of in the electrical closet? This would leave the dead leg longer than six inches as noted in Note 6 this page but would be a better placement of the valve since the facility plumbers don t have access to the electrical closet on their own without calling another department to come and open the door, as witnessed during our walk through. Also, it just seems like bad practice to have a water valve in an electrical closet. Response: There is already existing piping and valves located above the electrical closet. Per the scope, the dead leg must remove back to 6"" or less in length. The dead leg is to be removed back above the electrical closet and valved for future. Throughout the facility there are some locations where the shutoff valves installed are Gate type and they re not called out on the print to add new SOVs, as these are prone to failure with age, if they haven't already, do we need to install new Ball Valves down stream of existing shutoffs? Some of these will probably end up having to be changed out during this project anyway out of necessity to facilitate our work due to valve failure. Would make progress timelier to have this planned for ahead of time. Response: Yes, install new ball valve s downstream of existing shutoffs. Non-Keyed note says ""Add Re-circulation to Hot Water"" but does not have lines drawn to where it is to go to. This is the only one in the whole print set labeled this way and wanted to clarify there wasn't a different intention than the others. Response: Add new 1/2"" DHWR to existing DHW serving sink in 8B101 and connect to new DHWR piping in hallway C8B4 outside room 8B105. In the Northwest corner of south end of the first floor, all the ""new hot water return lines"" are tying back into the hot water supply in this area. This doesn t provide a way for there to be constant circulation of the system. which means all the water in this section of piping will eventually cool down into the temperature range where legionella grows, defeating the purpose of the project at large. There are more locations like this throughout the project. Recommend running a new dedicated return line to tie into. Response: These return lines are intended to tie back the hot water supply mains that are constantly being circulated. 8th Floor North, psych ward. This wing appears to be an anti-ligature wing with all anti ligature fixtures. If the intent is to keep this wing anti ligature, none of the scheduled replacement parts meet an anti-ligature standard. Verify if this is to remain anti ligature or not. If so, we will need a different basis for design for faucets, shower valves, etc. Response: Yes, A/E to provide different basis of design. There are 16 locations where the under-sink mixing valve is called out that aren't traditional sinks. The faucets are wall mounted mop sink style faucets for floor wash down. Mixing valves for these would need to be piped in above ceiling. Are the mixing valves still required in these locations for this type of faucet? Response: Install new mixing valve above ceiling at piping serving wall mounted faucets. In Room GR106, the Heat exchangers are too tall for the room with all the other systems there that are to remain. Suggest moving the new heat exchangers to GR100. This would also allow the new pumps to be installed in GR106 instead of GR107, thus leaving the existing storage room intact and available. Response: A/E advises moving the heat exchangers to storage GR107 instead of GR100 to minimize re-piping length. The new pumps could then be installed in GR106. COR to provide insight as well. In room Bf 155, can we move the Glycol tank in this room to the back end of the mechanical room under the air separator and re pipe it, to help accommodate the larger footprint of the new heat exchanger and piping where the current heat exchanger is sitting. Response: A/E does not take exception to moving the existing glycol tank to help make room for heat exchanger in BF155. What are the ICRA requirements for this project, primarily associated with #5 on the SOW? Response: ICRA will vary based on how invasive the work in an area will be. Most will be class II or class III. Phasing - In reference to #5 on the SOW, how many rooms will we be given access to at a particular time? Response: OKC VAMC will provide as many rooms as the contractor can handle for a standard workday. Details 3 and 4 on M203 show the new equipment (HEX 2, HEX3, P5, P6, P7, S2) to be in the same location of the existing equipment, on the back wall behind the piping, not accessible for maintenance in the future. It is recommended to move the equipment to the front, more accessible for the end user. Response: A/E does not take exception to installing the heat exchangers in front of the piping for accessibility. There is a steam line and a condensate line that are dead ended above the lobby in front of the elevators on the ground floor. The lines will be cut off during a steam outage we need to do for HEX 2 & 3. Do the deadlines need to be reconnected or can they be completely abandoned and removed? Response: Leave lines dead and remove to help clean up space. The plumbing fixture schedule shows the specific model number for the shower valve but doesn't say anything about the shower head. Just want to clarify that we are to change out the shower heads and not keep the old ones in place. If we are to replace the old shower heads with new ones, please provide style wanted for regular and anti-ligature. Response: Shower heads not intended to be replaced, only the shower valve. The eyewash stations in building 19 are all already supplied by the mixing valves for the emergency showers in the same rooms. Was the intent to just add a mixing valve to these lines where it was thought that there wasn't one? Or was the intent to shorten up the piping length and available area for legionella to grow? Response: Intent was to add a mixing valve where it was thought there wasn't one. If eyewash is already served by tempered water, then another mixing valve is not required. Please provide an equipment schedule identifying the model # and quantity of Phigenics equipment to be installed. Schedule should reference room # and provide a list of water monitoring parameters to be measured at each location. It should identify if the equipment is connected to domestic cold water or hot water. Is sheet E1300, dated 6-15-2020 included in the bid documents? Response: This sheet indicates to have the information requested. Period of Performance: Anticipated length of Construction is 240 days with 1 month for solicitation of construction contractor. Task Management. Engineering shall identify a Contracting Officer s Representative (COR). The COR will provide technical assistance and clarification required for the performance of this contract, participate in project meetings, review invoices, and receive deliverables. After contract award, the Contracting Officer will appoint a COR and issue a COR appointment letter stating the authority for the COR. The contractor will receive a copy of the written appointment Payment Information. The contractor shall provide the following payment information for VA use. It must be an exact match with the information under the contract number in the Contract Registration (not the contractor s company or individual representative s registration) as well as with the information under the contractor s DUNS number in the System Award for Management http://www.SAM.gov. Mismatched information will result in rejected invoice. Company Name Legal Business Name and DBA (Doing Business As) Name Mailing Address Contact and Address Information Remittance Address Remit to Address Information Employer s Identification Number Federal Tax ID DUNS (Data Universal Numbering System) CODES, STANDARDS AND EXECUTIVE ORDERS VA has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. VA design Manuals and Master Specifications specify other codes and standards that VA follows on its projects: VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application Guide, and other Guidance on the Technical Information Library (TIL) (http://www.cfm.va.gov/til/). PG-18-1 Master Construction Specifications PG-18-3 Design and Construction Procedures PG-18-4 Standard Details and CAD Standards VA BIM Manual V2.2 PG-18-5 Equipment Guide List H-18-8 VA Seismic Design Handbook PG-18-9 Space Planning Criteria PG-18-10 Design Manuals (by discipline) PG-18-12 Design Guides (graphical, by function) PG-18-13 Barrier Free Design Guides PG-18-14 Room Finishes, Door, and Hardware Schedules (consult COR for local standards) PG-18-15 Minimum Requirements for A/E Submissions PG-18-17 Environmental Compliance Manual H-7545 VA Cultural Resource Management VA Handbook 0056, Sustainable Building Program VA Directive 0056, Sustainable Building Program VA Directive 0055, VA Energy and Water Management Program NFPA 101 Life Safety Code NFPA National Fire Codes International Building Code (IBC) and all other International Code Series (IPC, IMC, IECC, IFGC, etc.) when applicable or referenced in VA Design documents/ guides. Occupational, Safety and Health Administration (OSHA) Standards. National Electrical Code (NEC) Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1. ASME Boiler and Pressure Vessel Code ASME Code for Pressure Piping Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13) Building Code Requirements for Reinforced Concrete, American Concrete Institute and Commentary (ACI 318) Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC) Energy policy Act of 2007 (EPAct) DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi-Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435. Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU) Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Management. The Provisions for Construction and Safety Signs. Stated in the General Requirements Section 01010 of the VA Master Construction Specification. Ventilation for Acceptable Indoor Air Quality ASHRAE Standard 62.1- 2013. Safety Standard for Refrigeration Systems ASHRAE Standard 15 2016.
 
Web Link
SAM.gov Permalink
(https://sam.gov/opp/528e64ff4fc547f7a2d1b77487e4b441/view)
 
Place of Performance
Address: Oklahoma City, OK 73104, USA
Zip Code: 73104
Country: USA
 
Record
SN06690417-F 20230524/230522230112 (samdaily.us)
 
Source
SAM.gov Link to This Notice
(may not be valid after Archive Date)

FSG Index  |  This Issue's Index  |  Today's SAM Daily Index Page |
ECGrid: EDI VAN Interconnect ECGridOS: EDI Web Services Interconnect API Government Data Publications CBDDisk Subscribers
 Privacy Policy  Jenny in Wanderland!  © 1994-2024, Loren Data Corp.