SOLICITATION NOTICE
Y -- Sierra Army Depot (SIAD) Sanitary Sewer Repair/Replacement
- Notice Date
- 7/8/2024 1:22:57 PM
- Notice Type
- Solicitation
- NAICS
- 237110
— Water and Sewer Line and Related Structures Construction
- Contracting Office
- W075 ENDIST SACRAMENTO SACRAMENTO CA 95814-2922 USA
- ZIP Code
- 95814-2922
- Solicitation Number
- W9123824R0043
- Response Due
- 7/25/2024 9:00:00 AM
- Archive Date
- 07/08/2025
- Point of Contact
- Heidi May, Phone: 3853039438, Amelia Bryant, Phone: 9165577685
- E-Mail Address
-
heidi.e.may@usace.army.mil, Amelia.K.Bryant@usace.army.mil
(heidi.e.may@usace.army.mil, Amelia.K.Bryant@usace.army.mil)
- Small Business Set-Aside
- SBA Total Small Business Set-Aside (FAR 19.5)
- Awardee
- null
- Description
- The United States Army Corps of Engineers (USACE) Sacramento District (SPK) has a requirement at The Sierra Army Depot (SIAD) in Herlong, California for Design-Bid-Build (DBB) construction services to repair sanitary sewer pipe defects, install new sanitary sewer cleanouts, and inspect sanitary sewer pipes and manholes. All repairs shall be made as specified by the SIAD Sanitary Sewer Evaluation Study (SSES) using like materials and equipment in accordance with Federal, State, and local regulations. The Contractor must: provide sewer bypass pumping and/or flow diversion as required; perform Closed Circuit Television (CCTV) inspections of sewer mains and service lines after repairs have been completed with results must be provided electronically; and conduct a high-pressure sewer line hydro-cleaning after the CCTV inspection. The Government anticipates options to include removal and replacing of manholes; removal and replacing of exiting sewer lines; and installing sanitary sewer cleanouts at multiple buildings. The facility must comply with Department of Defense (DoD), Army, and SIAD standards. The Contractor submitted plans and drawings must include sustainability requirements and address civil, structural, architectural, life safety, emergency lighting, mechanical, plumbing, and electrical needs to ensure a complete and usable structure. The period of performance (PoP) is anticipated to be 365 calendar days. In accordance with Federal Acquisition Regulation (FAR) 36.204(g), the magnitude of construction for the anticipated project is $5,000,000 to $10,000,000.The Government intends to solicit a Request for Proposals (RFP) that will result in award of a firm-fixed price (FFP) contract.The solicitation is anticipated to be issued using North American Industrial Classification System (NAICS) code 237110, Water and Sewer Line and Related Structures. The small business size standard for the NAICS, as established by the U.S. Small Business Administration, is $45,500,000 annual revenue. The Product Service Code for the potential requirement is anticipated to be Y1ND, Sewage and Waste Facilities. The solicitation is anticipated to be issued as total small business set-aside through the Procurement Integrated Enterprise Environment (PIEE - https://piee.eb.mil) and Governmentwide Point of Entry, the System for Award Management (SAM - www.SAM.gov) on or about 17 Jun 2024 with proposals tentatively due 17 Jul 2024. Please DO NOT request an updated schedule if estimated dates are surpassed; the Government will release all information publicly through PIEE and SAM when updates are available. Requests for schedule updates may be ignored.Please DO NOT request a copy of the solicitation, or draft plans and specifications, as they are not currently available. Any available technical data will be furnished with any forthcoming solicitation. Following solicitation release, all responsible sources may submit a proposal that shall be considered by the agency. This project and/or the anticipated solicitation may be changed, delayed, or canceled at any time.The anticipated solicitation and attachments may be posted in Portable Document Format (.pdf) which will require Adobe Acrobat Reader to open and view files. Adobe Acrobat Reader may be downloaded free of charge at http://www.adobe.com/products/reader.All prospective Offerors should be registered in the PIEE system at least one (1) week prior to the anticipated proposal due date. Registration is not required to download any forthcoming solicitation documents, plans, and/or specifications, but IS required to submit a proposal. Copies of the solicitation and attachments will be made available for inspection without charge after the solicitation is released, when accessed through PIEE. Failure to register in PIEE will prevent submission of proposals as the Government will not accept them by any other means. See linked PIEE registration instructions and web-based training for information about how to access the PIEE Solicitation Module and submit proposals. All prospective Offerors must be registered in SAM before the anticipated solicitation closing date. Please see the SAM website for information about SAM registration requirements and approval timelines. It is anticipated that any future solicitation and/or resulting contract will be subject to the E-Verify Employment Eligibility Verification Program (http://www.uscis.gov/e-verify) USACE will not notify prospective Offerors of any changes to the solicitation; Offerors must monitor PIEE and SAM for the solicitation to be posted, and for any posted changes or amendments. The ONLY Interested Vendors / Plan Holders / Bidders List is available through SAM.gov; Contractors are responsible for identifying their entity as an interested vendor and contacting other interested vendors. USACE SPK will not review capabilities statements submitted in response to this Synopsis or coordinate partnering arrangements between parties. Contractors should check SAM.gov frequently for changes to the interested vendors list and this Notice. 07/01/2024 Amendment 0001 issued to add sign in sheet/agenda for Site Visit07/08/2024 Amendment 0002 - 1. The purpose of the amendment is to: a. Change the proposal due date to 25 July 2024 at 10:00 MDT; b. Correct block 10 of the 1442 to reflect, The Sierra Army Depot (SIAD) CARR Level Sanitary Sewer Repair/Replacement. See summary of changes for full description change; c. Correct Option CLIN 1002 to reflect, 294ft 6inch PVC pipe See summary of changes for full CLIN extended description change; d. Correct Option CLIN 1003 to reflect, 30 ft of 8 inch pipe, 178 ft of 8 inch pipe and 70 ft of 8 inch pipe,; e. Delete Attachment 6 Main Design and Drawing, replace with Attachment 13 Main Design and Drawing dated 3 July 2024; 2. All other terms and conditions remain unchanged.
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/3562ae7173bd4c838c019eeca16787da/view)
- Record
- SN07119769-F 20240710/240708230112 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |