SOLICITATION NOTICE
Z -- Defense Supply Center Richmond(DSCR) Building 54 Tower Door Replacement
- Notice Date
- 7/11/2024 8:58:36 AM
- Notice Type
- Presolicitation
- NAICS
- 236220
— Commercial and Institutional Building Construction
- Contracting Office
- DCSO RICHMOND DIVISION #1 RICHMOND VA 23237 USA
- ZIP Code
- 23237
- Solicitation Number
- SP470324Q0055
- Response Due
- 8/8/2024 2:00:00 PM
- Archive Date
- 08/23/2024
- Point of Contact
- Robert Moragues, Contracting Officer, Phone: 8042795309, Fax: 8042793246, Kyle Gregory, Contracting Officer, Phone: 8049806388
- E-Mail Address
-
robert.moragues@dla.mil, Kyle.Gregory@dla.mil
(robert.moragues@dla.mil, Kyle.Gregory@dla.mil)
- Small Business Set-Aside
- SBA Total Small Business Set-Aside (FAR 19.5)
- Description
- This is an announcement which synopsizes the subject requirement.� A formal solicitation will be posted under the same notice ID on or around 12 July 2024.� The solicitation will be posted for 30 days.� The upcomming requirement is synopsized as follows: Defense Supply Center Richmond(DSCR) Building 54 has a requirement to remove existing personnel doors and replace them with an updated ""storefront"" style door.� There are four personnel doors mounted in glass block in building 54 in the East side tower. There are also two doors in the West side towers. All the doors and frames are rusted, and the life expectancy has passed.� The objective is to remove and replace four personnel doors that are mounted in 8�X8� glass block with aluminum storefront type entrances. Also, remove and replace two steel personnel doors in-kind. There are two photos at the end of this document that show representative examples of each type of door setup being replaced.� The specific requirements are: �� Each door is approximately 3�x7�. � Each tower glass block area to be removed is approximately 7�X12� including the door and frame. � Remove and dispose of 2 large metal canopies on the East side and 2 small metal canopies on the West side. Patch all holes to match surrounding area. � Only one door in each East tower can be replaced at a time. The door must be 100% completed and accepted by the government before moving to the next door. � Only one door on the West side can be replaced at a time. � If any door opening is not enclosed by the end of the workday the contractor shall cover the entire opening to prevent weather etc. from entering the building. � For each East side tower door, remove the door/frame, and all glass block to the lintel located approximately 12� high. � Prepare the opening to accept the storefront type door. � Replace all the East tower doors with a storefront type of layout including transom and side lites. The transom glass above the door shall include several mullions to break up the large glass area. Provide a sketch and photos showing the look/layout of the proposed storefront door system for approval. � All doors, frames, mullions etc. shall be aluminum, the color is Manor Brown. Contact the PM for the Shermin Williams color formula. The finish shall anodized. � Center the door in the opening. � Keep the door swing the same as existing. � Replace the handicapped operator and activation buttons on all doors that currently have handicapped operators. All doors need to have electric strikes. � Replace the motion sensors that unlock the doors from the inside. � Caulk all areas to match the door color. � All doors to receive new weatherstripping. � All hardware to be commercial grade/heavy duty. All doors to have exterior pull handles and a lockset. All doors to have panic hardware. � Any conduit etc. needs to be painted to match the color it is secured to. � Replace all thresholds. � Cleanout and fill/seal the crack at each threshold area where the interior concrete meets the exterior. The South 2 door has a large gap in the concrete. � Add new conduit and wiring to the exterior of the South 2 door for the handicapped operator. � For all East doors, remove, prepare the surface and replace 8 VCT tiles in front of the doors that have become damaged. Provide the PM with a color selection of tile to use to replace. � Repair the CMU interior block by the top left of the lintel of the North 1 door, paint to match. � Repair the CMU interior block by the top right of the lintel of the North 2 door, paint to match. � Prepare and replace 24 VCT tile inside doors West 1 and 2. Replace cove base. � Paint the exterior lintel block the same color as the door and frame above West 1 and 2 doors. � Prepare and skim coat the exterior concrete outside door West 1. � Reuse of existing conduit and wiring is acceptable. � Save some glass block for reuse in case any get broken from door/frame replacement. Any glass block that gets broken shall be replaced by the contractor at no additional cost. � Contractor shall take their own measurements. � All doors shall meet all ADA requirements. � Label all doors using the type of label, style, font as existing. � Reuse all security devices and card readers. � Any screws bolts, etc. that are removed and not replace shall have the holes filled and painted to match. � The location of dumpsters is shown on the map in red at the end of this document. The dumpsters shall not be on the sidewalk or pavement. Alternative dumpster locations must be approved. Repair all damaged grass areas with seed and straw. � Provide a portable toilet. The period of performance will be 120 days after NTP.�� The NAICS for this requirement is 236220 with a small business size standard of $45M. Additional information will be�
- Web Link
-
SAM.gov Permalink
(https://sam.gov/opp/9a923a4951444753838a246f11a89703/view)
- Place of Performance
- Address: Richmond, VA 23297, USA
- Zip Code: 23297
- Country: USA
- Zip Code: 23297
- Record
- SN07124805-F 20240713/240711230116 (samdaily.us)
- Source
-
SAM.gov Link to This Notice
(may not be valid after Archive Date)
| FSG Index | This Issue's Index | Today's SAM Daily Index Page |