COMMERCE BUSINESS DAILY ISSUE OF JANUARY 11,1995 PSA#1260Yoshio Matsuda, Director-General, Chubu Regional Construction Bureau
(Moc), 2-5-1 Sannomaru, Naka-Ku, Nagoya-Shi 460 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 01/05/95 PG. 2. DUE 100095
POC Tel 81/52/962-6311 X2521 S1629 Construction Opening time and date
10:00, feb. 28, 1995. Open 1) Construction Title improvement of route
302 at shinpo for fy '94; 2) site shinpo-cho, tokai-Shi, aichi-ken; 3)
summary a) type of structure: through girder 18 06 meters in length
(widths 15.2, 4.7, and 12 66 meters); B) utility duct: 2 culverts 88
meters in length; and C) cut-off wall 644 meters in length, 20 meters
in shaft height; 4) Construction period approx. 13 months (400 days);
5) main materials to be used approx 3,500 tons of concrete, approx. 300
tons of reinforcing steel, approx 1,750 tons of cut-off steel sheet
piles, approx 230 tons of steel pipes; 6) deadline for submission of
application forms/related documents for qualification screening 4:00,
jan. 17, 1995; 7) contact for Tender documents contract Division,
General Affairs Department, Chubu Regional Construction Bureau,
ministry of Construction, 2-5-1 Sannomaru, Naka-Ku, Nagoya-Shi 460
eligible Tender participants 1) firms that do not fall under articles
70 and 71 of the cabinet order concerning budget, auditing, and
accounting; 2) firms qualified for open competitive tendering on Public
works by the Chubu Regional Construction Bureau; 3) firms that score
1,000 points or more in a formula calculated from bidding company's
objective criteria at the time of application for qualification; 4)
firms not undergoing bankruptcy procedures; 5) firms that have -- since
1988 as the main contractor -- actually carried out Construction of a
cross structure, using through girder- type or box-type structure, in
a currently used highway note only Construction projects in which
bidder has had a 30 percent or greater share are eligible for
consideration; 6) firms that can assign to the Construction site a
full-time Chief engineer or engineering supervisor who meets the
following criteria a) is qualified as a certified first-class
Construction supervisor or equivalent or higher; B) has -- since 1988
as Chief engineer or engineering supervisor of the main contractor --
constructed a cross structure, using through girder-type or box-type
structure, in a currently used highway; and C) in the case of
engineering supervisor, is qualified to supervise designated
Construction works; 7) firms not currently suspended from designation
by the Director of the Chubu Regional Construction Bureau; and 8) firms
not related by capital or personnel to the contractors involved in this
project submitting agency, not from U S. Embassy. Date of publication
in ''kensetsu kogyo shimbun'' 010595. Post contact/prepared by gtaevs
Please send a copy of your response to: Commercial Section (FCS TOP),
American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to TC0237..
(0009) Loren Data Corp. http://www.ld.com (SYN# 0442 19950110\99-0005.SOL)
99 - Miscellaneous Index Page
|
|