COMMERCE BUSINESS DAILY ISSUE OF JANUARY 18,1995 PSA#1264Tsugito Hatano, Director-General, Niitata Construction Bureau, Japan
Highway Public, Corporation, 1-1 Tenjin, Niigata-Shi, Niigata-Ken 950 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 01/10/95 PG. 5. DUE 150095
POC Tel 81/25/243-3911 S1622 Construction of tunnel opening time and
date 15:00, mar. 28, 1995. Open 1) Construction Title phase-one
Construction of the sakai tunnel on the hokuriku expressway; 2) site
asahi- Cho-sakai, shimo-shinkawa-gun, toyama-Ken; 3) summary this
project is to construct a Highway of 1,300 meters in length (earth work
volume approx 94,000 cubic meters), mainly involving excavation of a
tunnel (at one site, 1,300 meters in length); total length 1,300
meters; width - tunnel portion 8.5 meters; earth work volume 94,000
cubic meters; and tunnel at one site - 1,300 meters; 4) Construction
period 780 days (winter recess jan. 5 to mar 5); 5) main materials to
be used: 7,900 cubic meters of concrete, 70 tons of reinforcing steel;
6) documents for qualification screening 16:00, feb. 9, 1995; 7)
contact for Tender documents contract division, procurement and right-
of-way department, Niigata Construction Bureau, Japan Highway Public
Corporation, 1-1 Tenjin, Niigata-Shi 950 eligible Tender participants
firms qualified to participate in this project's bidding must satisfy
all of the following conditions and have their qualifications for this
project's bidding screened and confirmed by the Director of the
Niigata Construction Bureau 1) firms that do not fall under article 4
of the contract regulations of Japan Highway Public Corporation; 2)
consortia comprised of two firms pre-qualified for open competitive
tendering on Road and earth work by the Niigata Construction Bureau of
Japan Highway Public Corporation for fy 93/94; 3) all member firms
must have - - in the past five years (since 1989) as the main
contractor -- actually carried out Construction of a tunnel of at least
1 0 kilometer extension and at least 50 square meters designed inner
Section by the ''natm'' method note: only Construction projects in
which bidder has had a 30 percent or greater share are eligible for
consideration; 4) firms that can assign to the Construction site a
field Representative or a full-time chief engineer or engineering
supervisor who meets the following criteria in the past five years
(since 1989) as field Representative or as chief engineer or
bngineering supervisor, has constructed a tunnel by the ''natm''
method; 5) firms not suspended from designation in no 5 zone by Japan
Highway Public Corporation; 6) firms that can present an adequate plan
for tunneling; 7) each member firm must satisfy the following criteria
a) has been in operation for at least five years in qualified business
under the Construction business law; B) can assign to the Construction
site a full-time engineering supervisor qualified for this project
under the Construction business law or a full-time nationally- licensed
chief engineer; and C) has an at least 30 percent share of involvement,
and the Representative firm must have the greatest share firms
pre-qualified by the Construction minister regarding items (a) and (B)
in evaluation of their management operations are exempted from these
criteria; and 8) firms not related by capital or personnel to the
contractors involved in this project (see Tender documents for
details). Bid documents must be obtained directly from the submitting
agency, not from U S. Embassy. Date of publication in ''kensetsu kogyo
shimbun'' 011095. Post contact/prepared by gtaevs Please send a copy
of your response to: Commercial Section (FCS TOP), American Embassy,
Tokyo, Unit 45004, APO Ap 96337, Refer to TC0254.. (0013) Loren Data Corp. http://www.ld.com (SYN# 0445 19950117\99-0011.SOL)
99 - Miscellaneous Index Page
|
|