COMMERCE BUSINESS DAILY ISSUE OF JANUARY 24,1995 PSA#1268NASA-Ames Research Center, Mail Stop 213-13, Moffett Field, CA
94035-1000 Z -- PROTECTIVE COATING SYSTEM FOR THE 40 X 80 WIND TUNNEL, PHASE 3
SOL IFB2-36291(VDG) DUE 031495 POC Contact Point, Chris Wolfe,
415/604-1442, Contracting Officer, Vivienne D. Gallo, 415/604-5808 The
successful Contractor shall provide materials, equipment, and labor
for the surface preparation and application of coatings to exterior
surfaces of NASA's 40 X 80 Wind Tunnel. The Contractor is advised that
the stuctural steel is coated with a red lead primer that has been
determined to contain 14 percent lead by weight. In addition, the
transite and galbestos siding on vast areas of the wind tunnel, if
abraded, poses a potential asbestos hazard. Specified procedures shall
be observed throughout the course of this contract. Contractor shall
be responsible for the removal containment/capture, on-site
handling/storage, and the disposal of the red lead hazardous waste.
Exterior items to be coated include the following: Structural steel,
ladders, stairs, platforms, rails, guardrails, and catwalks, drain
gutters and down spouts below aerodynamic ceiling line conduits and
miscellaneous piping attached to the tunnel doors, door frames and
window frames, roll- up and sliding doors and frames, all attached
miscellaneous steel, and all other attached ferrous items. The project
consists of a Base Bid and four (4) Options. The period of performance
for the Base Bid is 120 calendar days. Each option, if exercised, will
be an additional 30 calendar days each. Magnitude of Construction:
Between $1,000,000 and $5,000,000. The place of performance is
NASA-Ames Research Center, Moffett Field, CA 94035-1000. All
responsible sources may submit a bid which shall be considered by the
Agency. (0020) Loren Data Corp. http://www.ld.com (SYN# 0103 19950123\Z-0011.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|