COMMERCE BUSINESS DAILY ISSUE OF JANUARY 26,1995 PSA#1270Yoshio Warita, Director-General, Kanto Regional Construction Bureau
(Moc), 1-3-1 Otemachi, Chiyoda-Ku, Tokyo 100 99 -- JAPAN: SOL KENSETSU KOGYO SHIMBUN: 01/18/95 PG. 3. DUE 100095
POC Tel 81/3/3211-6261 S16 Construction of Ministry of transport
training Center opening time and date 10:00, mar. 15, 1995. Open 1)
Construction Title Construction of Ministry of transport training
Center in zone one site; 2) site 3- 11-1-gai kashiwanoha, kashiwa-shi,
chiba-ken; 3) summary a) site area 37,831 square meters; B) structure
reinforced concrete Construction, three stories above ground, length
of building 86 meters; C) size land arba 1,602 square meters, total
floor area 4,806 square meters; D) use for training facility; E) work:
this project involves Construction of Ministry of transport training
Center in zone one site; work at this time includes all works excluding
part of interior finish work; and F) additional work to be scheduled
part of interior finish work; 4) Construction period approx. 13 months
(overall project 22 months); 5) main materials to be used 3,700 cubic
meters of concrete, 500 tons of reinforcing steel, 800 square meters
of glass; 6) documents for qualification screening 17:30, jan. 30,
1995; 7) contact for tender documents contract Division, Kanto Regional
Construction Bureau, Ministry of Construction, 1-3-1 Otemachi,
Chiyoda-Ku, Tokyo 100 12 eligible tender participants: 1) firms that Do
not fall under articles 70 and 71 of the cabinet order concerning
budget, auditing, and accounting; 2) firms Qualified for open
competitive tendering on Construction works by the Kanto Regional
Construction Bureau; 3) firms that score 1,100 points Or more in a
formula calculated from bidding company's objective criteria at the
time of application for qualification; 4) firms not undergoing
bankruptcy procedures; 5) firms that have, as the main contractor,
actually carried out Construction of the following (a) and (B) a) since
April 1989, a government building made of reinforced concrete Or
steel-framed reinforced concrete, at least three stories above ground,
and at least 3,000 square meters total floor area; and B) since April
1984, a flat-shaped, block Construction made of reinforced concrete
and at least 60 meters length, without any expansion joints installed
note: Only Construction Projects in which bidder has had a 30 percent
Or greater share are eligible for consideration; 6) firms that can
assign to the Construction site a full- time chief engineer Or
engineering supervisor who meets the following criteria a) is Qualified
as a certified first-class Construction supervisor Or equivalent Or
higher; B) has, since April 1989, had Construction experience as
described in item (5) - (a) above; and C) in the case of engineering
supervisor, is Qualified to 8UPERVISE designated Construction works; 7)
firms not currently suspended from designation by the Director of the
Kanto Regional Construction Bureau; and 8) firms not related by capital
Or personnel to the contractors involved in this project bid documents
must be obtained directly from the submitting Agency, not from U S.
Embassy date of publication in '' kensetsu kogyo shimbun'' 011895.
Please send a copy of your response to: Commercial Section (FCS TOP),
American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to TC0268..
(0024) Loren Data Corp. http://www.ld.com (SYN# 0467 19950125\99-0002.SOL)
99 - Miscellaneous Index Page
|
|