COMMERCE BUSINESS DAILY ISSUE OF JANUARY 26,1995 PSA#1270U.S. Army Engineer District, Alaska, ATTN: CENPA-EN, P.O. Box 898,
Anchorage, AK 99506-0898 (Physical Address: Bluff & Plum Streets,
Building 21-700 (Rm 200), Elmendorf AFB, AK 99506-0898) C -- INDEFINITE DELIVERY ARCHITECT-ENGINEER SERVICES CONTRACT FOR
SURVEY AND RELATED SERVICES, VARIOUS LOCATIONS, ALASKA SOL
DACA85-95-R-0016 POC Administrative Inquiries: Ms. June Kedney,
907/753-5624 or Technical Inquiries: Mr. Jerry Zuspan, 907/753-2660,
Contracting Officer: Ms. Gail West 1. CONTRACT INFORMATION: This
announcement is open to all businesses regardless of size. All
responders are advised that this project may be cancelled or revised at
any time during the solicitation, selection, evaluation, negotiation
and final award. The contract shall be an indefinite delivery firm
fixed price. The limit for each delivery order shall be $150,000.00
with a contract limit of $750,000.00 for a 1 year period. The contract
may include an option for an additional year and an additional
$750,000.00. More than one AE firm may be selected. Contract(s) award
is anticipated for May 95. Responding firms must address each
discipline, clearly indicate which shall be subcontracted, and provide
a separate SF254 and SF255 for each subcontractor necessary. The
contractor shall employ, for the purpose of performing that portion of
the contract work in the State of Alaska, individuals who are
residents of the State, and who, in the case of any craft or trade,
possess or would be able to acquire promptly the necessary skills to
perform the contract. 2. PROJECT INFORMATION: The AE selected would be
required to have sufficient staff, flexibility, and capability to be
available on an as-needed basis. Typical types of services to be
provided may include hydrographic, aerial mapping, GPS control,
boundary establishment, and other specialized surveys. It may also
include performing field topographic, planimetric, and utility surveys,
office computations, and 3D digital mapping for use in developing
''Plans and Specifications.''. LOCATION: Various Locations, Alaska. 3.
SELECTION CRITERIA: See Note 24 for general selection process. The
following selection criteria headings are listed in descending order of
importance: (a) professional personnel in the following disciplines:
(weighted equally) (1) minimum in-house requirements are 2 surveyors
licensed by the State of Alaska with a crew of 2 party chiefs and 4
staff sruveyors and be able to document at least 3 years experience in
hydrographic surveying in navigable channels; (2) disciplines which
may be subcontracted: photogrammetric mapping and other related
services; (b) specialized experience and technical competence in:
(weighted equally) (1) minimum of 3 years experience in the use of
AutoCAD and Softdesk softwares, (2) minimum 2 years of experience in
global positioning system (GPS) and qualified to conduct precise
surveys, (c) capacity to maintain schedules and accomplish required
work on three simultaneous delivery orders; (d) past performance on DOD
and other contracts with respect to cost control, quality of work, and
compliance with schedules; (e) location of the firm in general
geographical area of the projects and knowledge of locality:
availability of AE staff to meet frequently with Corps personnel in the
Alaska District Corps of Engineers' office in Anchorage and ability to
mobilize staff to Alaskan project sites on relatively short notice;
(f) volume of DOD contract awards in the last 12 months as described in
Note 24; and (g) extent of participation of SB, SDB, historically black
colleges and universities, and minority institutions in the proposed
contract team, measured as a percentage of the estimated effort. The
contractor shall employ, for the purpose of performing that portion of
the contract work in the State of Alaska, individuals who are
residents of the State, and who, in the case of any craft or trade,
possess or would be able to acquire promptly the necessary skills to
perform the contract. 4. SUBMISSION REQUIREMENTS: Firms submitting SF
255s (1 copy only) should include: (1) organization of proposed project
team, (2) responsibilities and authority of key project personnel, (3)
relationship of project team to overall organizat on of the firm, (4)
a quality control plan, (5) in block 8c of the SF 255 include a POC
and phone number, and (6) willingness of all employees (including
supervisor) involved in field activities to be certified in hazardous
waste operations and emergency response 8 AAC 10.0101 & 29 CFR1910.120
prior to contract award. Submittals must be received at the address
indicated above not later than COB (4:00 pm Alaska time) on the 30th
day from the date of this announcement. If the 30th day is a Saturday,
Sunday, or Federal holiday, the deadline is the close of business of
the next business day. No additional information shall be provided, and
no faxed submittals shall be accepted. This is not a request for
proposal. (0024) Loren Data Corp. http://www.ld.com (SYN# 0028 19950125\C-0012.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|