COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 1,1995 PSA#1274U. S. Postal Service, Headquarters Purchasing, 475 L'Enfant Plaza West
SW, Room 4541, Washington, DC 20260-6238 70 -- PROCESS MANAGEMENT TOOL REQUIREMENTS - REQUEST FOR INFORMATION
POC Arlene Walker-Hall, Purchasing Specialist (202) 268-4762. The U. S.
Postal Service is currently seeking companies with existing process
management tools to help standardize the overall Postal Service
software development process and to facilitate the modeling, control,
and work flow of application projects. Information Systems, at the
Postal Service is currently in the process of re-engineering its
software development processes using the Capability Maturity Model
developed by the Software Engineering Institute of Carnegie Mellon
University. This effort has produced a set of software standards and
procedures which require automated support to expedite implementation
and facilitate operation. The Postal Service is seeking information
from companies which have the current existing process management tools
which can do the following: Tool Requirements. The process management
tool should provide the following capabilities: Operational: (1)
Operate in the standard Postal Service application development
environment, including MS/Office 4.2, MS/Windows 3.1, MS/Project 4.0,
and Novell 3.1.2. (2) Support multiple users (up to 250) in LAN-based
environment and provide a standalone PC version. INTERFACE: (3) Provide
bi-directional interface with Postal Service project management tools,
MS/Project for Windows. (4) Provide interface with Postal Service form
generation software, currently F3fill and MS/Word, for completion of
official forms. (5) Be able to invoke other tools (e.g. CASE, forms
generation, data modeling, sizing/estimating) from within the process
manager environment. (6) Support interfacing with other Postal Service
publications and the electronic documentation system. FUNCTIONALITY:
(7) Provide pre-defined process templaces - i.e. adaptable Work
Breakdown Structures (WBSs) - that provide all phases, activities,
tasks and deliverables to support the software development process. (8)
Provide capability to customize pre-define process templates to Postal
Service life cyccle methodologies, including, but not limited to,
waterfall - for large, average, and small projects, client/server,
prototype and outsource. (9) Provide capability to tailor process
templates (pre-defined or customized) to individual project
requirements, creating diagram and outline views of the project WBSs.
(10) Provide capability to store and maintain sample deliverables. (11)
Provide capability to access actual project deliverables throughout
project. (12) Provide hypertext capability for all components of the
process standards and procedures (including standards text, glossary,
forms, samples, etc.). (13) Provide capability to capture, analyze,
store (for project histories and future planning and estimating) and
report measurement data. (14) Provide automated risk analysis,
performance measurement and project estimation, including use of the
function point method. (15) Provide capability to customize and
maintain the process templates, on-line help/training material, Quality
Assurance checklists, and sample deliverables. (16) Provide versioning
capability to access multiple versions of the softrware process
methodology, standards, and procedures. (17) Provide security to
control access to update by resource type (e.g. project manager).
ON-LINE ACCESS: (18) Provide on-line access to process standards and
procedurs from corresponding activities in WBSs. (19) Provide on-line
access to the format, samples, and completion template (if form) for
standard deliverables. (20) Be able to instantly display and utilize
on-line help and training materials. COMPANY REQUIREMENTS: The company
must be able to: (21) Provide on-site training and support of Postal
software process experts. (22) Provide on-site consulting fsupport for
initial set-up, customization and conversion. (23) Demonstrate
corporate viability (longevity, installed base, financial resources).
Forward your information to Arlene Walker-Hall at the above sited
address by March 1, 1995. (0030) Loren Data Corp. http://www.ld.com (SYN# 0481 19950131\70-0026.SOL)