COMMERCE BUSINESS DAILY ISSUE OF FEBRUARY 22,1995 PSA#1288International Boundary & Water Commission, United States Section, The
Commons, Building C, Suite 310, 4171 N. Mesa, El Paso, TX 79902-1441 R -- PARTNERING SERVICES FOR RIO GRANDE AMERICAN CANAL EXTENSION
(RGACE) - REACH B SOL RFP 95-16 due 033095. Contact Maria C. Smith,
Contract Specialist at (915) 534-6682, Delfina C. Lechuga, Contracting
Officer. The International Boundary and Water Commission, United
States and Mexico, United States Section (IBWC/US), intends to
implement the partnering concept in the construction of 2.66 miles of
the Rio Grande American Canal Extension (RGACE). Reach B, in El Paso,
El Paso County, Texas. The estimated price range for construction of
the RGACE. Reach B is between $1,000,000 and $5,000,000. This request
for proposal (RFP) is for the selection of a firm that will act as a
facilitator for partnering between the IBWC/US and the Contractor who
is awarded the RGACE. Reach B contract. The partnering requirement may
not be awarded as partnering is at the Contractor's option. The
construction of the 2.66 miles of a reinforced concrete-lined
trapezoidal canal section from design canal centerline station 499+70
to station 640+00 begins in the area of Ascarate Wasteway and ends just
upstream of the first convergence of the Playa Lateral along the United
States levee. The project includes construction of a four barrel box
sag culvert, retaining wall, concrete canal covered section, placement
of approximately 3,591 feet of PVC pipe and gated structure,
excavation and placement of compacted embankment, seeding of embankment
slope, demolition and plugging of two small turnouts, placement of
levee gravel surfacing, and appurtenant structures. The contract period
is 457 days after issuance of Notice to Proceed. The facilitator shall
serve as a neutral third party with no direct or indirect involvement
with the IBWC/US or the Contractor.The facilitator's responsibilities
shall include conducting a one daypartneringfamiliarization workshop
for approximately 20 attendees. A combination of group activities,
lectures, and experimental learning exercises shall be conducted at the
workshop setting to be held at the IBWC/US headquarters located in El
Paso, TX, and shall be attended by the IBWC/US and the Contractor's key
project personnel. The facilitator shall provide all workshop material.
At the conclusion of the workshop, the parties shall create a charter.
The facilitatorshall draft the charter, prepare the agendas for
follow-up meetings, develop partnering procedures, and submit
partnering reports. The facilitator shall arrange follow-up meetings
between key leaders to meet on a monthly basis for 1/2-day during the
contract period. These meetings shall be conducted off-site at a
neutral site pre-arranged an paid for by the facilitator. The first
follow-up meeting shall evaluate the goals and objectives established
during the initial workshop. This evaluation shall be the focus of
subsequent meetings where problems shall be addressed and the value of
partnering is encouraged and reinforced. (045) Loren Data Corp. http://www.ld.com (SYN# 0087 19950221\R-0007.SOL)
R - Professional, Administrative and Management Support Services Index Page
|
|