COMMERCE BUSINESS DAILY ISSUE OF MARCH 15,1995 PSA#1303ESC/PKOC, 104 Barksdale St, Hanscom AFB, MA 01731-1806 Z -- ENERGY EFFICIENCY IMPROVEMENTS, BUILDING 1201, HANSCOM AFB, MA
SOL F19650-95-B0003 DUE 050395 POC SrA Sean Burney, Contract
Specialist, 617-377-2572, or MSgt Gary Pritchett, Contracting Officer,
617-377-2831. The intent of this project is to remove and replace the
existing 1000 ton, R-11, ODC, chillers and associated equipment to
improve the energy efficiency of the chilled water central plant at
Hanscom AFB, MA. Principal items of work include but are not limited
to: Replace existing chillers and associated piping, replace the
existing plate and frame heat exchanger and related mechanical piping,
demolition, installation of new air separator and expansion tank,
replace the existing condensing water controls, replace existing
chilled water control system, rigging heavy equipment, critical
phasing, coordination of the work with existing contractor, and all
associated electrical work. The basic bid will consist of the
replacement of one 1000 ton chiller with associated piping, chiller
controls, central plant control system, condenser water reset,
refrigerant monitoring system, mechanical room ventilation, electrical
work, and training. There will be optional bid items on the following:
(1) Replacement of a second 1000 ton chiller with associated piping
controls, connection to central chiller plant control, electrical work,
and training. (2) Replacement of the plate and frame heat exchanger
with associated piping, installation of existing condensor water
control valve, electrical work, and training. (3) Demolition and
removal of existing steam absorption chiller and associated piping, and
electrial connections, and removal of R-114 container. (4) Install air
separator and expansion tank with associated piping. The Contractor
will be allowed 9 months to complete the basic bid only. The Contractor
will be allowed 18 months to complete the entire project including all
options awarded with the basic bid. For options awarded after intitial
award period, the performance will be specified in the bid documents.
These periods include an exclusion for physical work during the peak
cooling season, 15 June until 30 September. The magnitude for this
project is between $1 million and $5 million. If you wish to receive a
copy of the solicitation package, please send a non-refundable
cashier's check or money order payable to ''THE UNITED STATES
TREASURY'' for $30.00 (for each requested copy, up to three copies) and
a written request to: ESC/PKOC, ATTN: SrA Sean Burney, 104 Barksdale
St., Hanscom AFB, MA 01731-1806 (Phone No. 617-377-2572, Fax
617-377-1156). If you wish to receive the solicitation documents on a
computer disk and a hard copy of the drawings, please send a
non-refundable cashier's check or money order payable to ''THE UNITED
STATES TREASURY'' for $25.00 and one blank 3.5 or 5.25 size computer
disk to the same address. WARNING - PLEASE NOTE: If you fax a request
to the above address, we will not send you a solicitation package until
a non-refundable cashier's check or money order payable to ''THE UNITED
STATES TREASURY'' is received by the above address. All firms
responding will indicate whether they are or are not a small, small
disadvantaged, or small woman-owned business concern. (0072) Loren Data Corp. http://www.ld.com (SYN# 0097 19950314\Z-0001.SOL)
Z - Maintenance, Repair or Alteration of Real Property Index Page
|
|