|
COMMERCE BUSINESS DAILY ISSUE OF APRIL 18,1995 PSA#1327Department of Energy, ATTN: Document Control Specialist, P.O. Box 2500,
Washington, DC 20013 R -- PRIVATIZATION OF FACILITY DEACTIVATION POC Ms. Irie White,
Contract Specialist, (202) 634-4466, David Leotta, Contracting Officer,
(202) 634-4409 BACKGROUND The Department of Energy, Office of
Environmental Management (EM) is responsible for deactivating nuclear
facilities surplus to the Department's needs. By ''deactivation'' is
meant removing the bulk of the radioactive and hazardous materials from
a facility so aws to reduce the potential hazard and to minimize the
the surveillance and maintenance (S&M) cost. S&M activities are
required to ensure that the public and workers are protected from the
hazards of the facility and to preserve the capital investment. They
typically include operating and maintaining electrical, service water
and ventilation systems, operating and maintaining safety systems,
providing security services, taking routine readings on equipment,
correcting problems found, and replacing wornout equipment. S&M costs
for a nuclear facility are quite substantial and continue as long as a
facility exists but decreases significantly, on the order of 90-95%
upon completion of deactivation. The magnitude of the S&M cost is
largely determined by the hazard represented by the material in the
facility. For example, the presene of nuclear fuel containing highly
enriched uranium in a reactor spent fuel storage basin requires a
higher level of S&M activities, including security, than does an empty
basin. The Office of Facility Transition and Material Stabilization
(EM-60) within EM is responsible for facility deactivation.
Deactivation of existing surplus facilities could save hundreds of
millions of dollars relative to continuing to pay S&M costs, but
sufficient funding is not available to perform all the available
deativation projects without taking funds from projects which either
have higher safety priorities or are governed by legal agreements as
regards to their schedules for accomplishment. To enable the
acceleration of deactivation activities at surplus facilities, DOE is
considering the issuance of a solicitation which would enable the
placement of contracts for deactivation of DOE facilities using private
funding, with the contractor paid from the S&M savings resulting from
the reduction in cost to the Department resulting from the
deactivation. Legislation may be needed to authorize this project. The
intent is to enable early commencement of possible zero funded
deactivation projects and earlier completion of other deactivation
projects without an increase in annual funding levels. This will result
in substantial cost savings in future years after deactivation is
completed. The approach on which comments are solicited is outlined as
follows: (1) DOE would define the deactivation project scope; (2) The
contractor would obtain financing for the deactivation project from
the private sector; (3) DOE would place the contract with zero
obligated funds; (4) The contractor would perform the work to the
contract requirements. The contract would define the scope of work,
applicable requirements and the means of calculating the cost savings
from which the contractor would be paid; (5) DOE would pay the
contractor a share of the cost savings (up to 100%) resulting from
deactivation until the Department's obligations to the contractor were
met. All payments would be from cost savings. Payment would be
contingent on availability of appropriated funds. The contract would
contain ''Termination for Convenience'' and Suspension of Work''
clauses, as well as other clauses required by FAR and DEAR; (6) DOE
would retain ownership of the facility during deactivation if those
materials would remain on site pending final disposition. SPECIFIC
INFORMATION SOUGHT BY THE DEPARTMENT The Department is interested in
obtaining comments and questions from interested parties in the
following areas: (1) What specific information, term, conditions, and
other assurances would a vendor view as necessary for a fixed price,
pay from savings deactivation contract? (2) What period of time for
payment of DOE's contract obligations would be viewed as commercially
viable, e.g., payments beginning following year 1, year 3 or year 5 or
more? (3) What limit, if any, would a vendor expect on the magnitude
of private financing available for a deactivation project? (4) What
size contract should be attempted under the proposed approach, e.g.,
$1M pilot, $10M, $100M? (5) What information on regulatory standards,
permits, and regulations would be needed for a competitive fixed price
procurement? (6) Interested firms should state their willingness and
ability to borrow private funds to complete a deactivation project of
up to $100M in total cost before being paid. What assurances or
guarantees would be required from DOE to enable a vendor to obtain
private financing to cover the costs of the deactivation projeact? (7)
DOE's Management and Operating (M&O) contractors have personnel
qualified to operate the facilities being considered for deactivation
under this methodology. Not all deactivation work requires the use of
facilities being deactivated, but where operation of those facilities
is required, how would the vendor propose to either replace or to
utilize the necessary skills to accomplish the deactivation in the most
expeditious and efficient manner? (8) Part of the deactivation work
will require use of existing facilities, e.g., ventilation systems,
fluid systems, lifting and hoisting equipment, This equipment will
require preventive and corrective maintenance. During the deactivation
work how would the vendor propose to allocate responsibility between
DOE/M&O contractor and the vendor for each type of maintenance? To
discuss issues and address any comments or concerns, the Department has
scheduled a meeting for May 1, 1995. The meeting will be held at U.S.
Department of Energy, Forrestal Building Auditorium, 1000 Independence
Avenue, SW, Washington, DC 20585. The time of the meeting shall be
from 9:00 am until 1:00 pm. All interested parties are invited to
attend. (0104) Loren Data Corp. http://www.ld.com (SYN# 0057 19950417\R-0010.SOL)
R - Professional, Administrative and Management Support Services Index Page
|
|