COMMERCE BUSINESS DAILY ISSUE OF APRIL 24,1995 PSA#1331Contract Division, Hakodate Development and Construction Department,
Hokkaido Development Bureau, 1-27 Okawa-Cho, Hakodate-Shi 040, Japan 99 -- JAPAN: POC Tel 81/0138/42-7111 X312 FAX N/A S16 Construction
product data a industry sector code: s16 B detailed product
description: Construction Title: Construction of superstructure for the
osatsube large bridge at minami-kayabe-Cho on National highway Route
278; site: minami-kayabe-Cho, kayabe-gun, Hokkaido; summary: four-span
continuous, prestressed-concrete, rigid-frame box-girder bridge;
bridge length (span length): 190.0 meters (40.3, 54.0, 54.0, 40.3
meters); width: 12.5 meters (0.6, 1.0, 6.5, 1.0, 3.0, 0.4 meters);
method of Construction: by the cantilever-erection method using a
mobile cantilever cart; work on pillar heads at three sites (P-1, P-2,
P-3) (total three sites); cantilever work at three sites (P-1, P-2,
P-3) (total three sites); work on span sides at two sites (a-1, a-2)
(total two sites); work on central closure at two sites (total two
sites); closed-type rubber slab bearings at four sites (total four
sites); steel expansion joints 8.465 tons (total weight 8.465 tons);
steel drain gutter 241.6 meters (total length 241.6 meters); guardrail
85 meters (total length 217.2 meters); handrail/guardrail N/a (total
length 210.1 meters); asphalt pavement N/a (total area 2,114 square
meters); Construction period: approx. 21.7 months (650 days) (total
period fy 95/96); main materials to be used: concrete 1,728 cubic
meters (total volume 1,728 cubic meters); reinforcing steel 224 tons
(total weight 224 tons); prestressing steel bars 106 tons (total weight
106 tons); closed-type rubber slab bearings four sets (total four
sets); steel expansion joints 8.465 tons (total weight 8.465 tons);
steel drain gutter 241.6 meters (total length 241.6 meters); guardrail
85.0 meters (total length 217.2 meters); handrail/guardrail N/a (total
length 210.1 meters); asphalt pavement N/a (total area 2,114 square
meters). C product specifications/technical data: N/a D quantity: N/a
e U.S. dollar value: N/a F other information: N/a response data a
response language: Japanese. B best way to respond: letter. C from
manufacturers only: N/a D information desired from U.S. firm: N/a e
primary buying factor: the lowest bid within the estimated price range.
F other information: pre-screening required to be eligible for bidding.
Pre-screening deadline: 17:00 pm, apr. 28, 1995. Bid documents must be
obtained directly from the submitting Agency, not from U.S. Embassy.
Payment in yen. A issuing Agency: Hakodate Development and Construction
Department, Hokkaido Development Bureau B financing Agency: same as
above. C price of bid documents: N/a D purchase bid documents by: June
1, 1995. E tender number required in all communications: N/a F
performance bonds required: not required. G closed Procurement
procedure: N/a H bidding procedures: open competitive tender. I bid
deadline: 10:00 am, June 13, 1995. J other information: '' kensetsu
kogyo shimbun'': 4/18/95. Eligible tender participants: 1) firms that
do not fall under articles 70 and 71 of the cabinet order concerning
budget, auditing, and Accounting; 2) firms pre-qualified for open
competitive bidding on prestressing concrete work by the Hokkaido
Development Bureau; 3) firms that have since 1990 actually carried out
on-site Construction of a multi- span continuous,
prestressed-concrete, rigid-frame box girder of at least 50 meters
maximum span length by the cantilever erection method, using a mobile
cart. Note: only Construction projects in which bidder has had a 30
percent or greater share are eligible for review; 4) firms that can
assign to the Construction site a full-time Chief Engineer or
engineering supervisor who meets the following criteria: a) is
qualified as a certified first-class Construction supervisor; B) has
since 1990 had experience with a project as described in item (3)
above; and C) in the case of engineering supervisor, is qualified to
supervise designated Construction works; 5) firms not currently
suspended from designation by the Director of the Hokkaido Development
Bureau; 6) firms not related by capital or personnel to the
contractors involved in this project; and 7) this project is open only
to pre-qualified single entities. Post remarks Post Contact/prepared
by haomori approved by vtran Please send a copy of your response to:
Commercial Officer (FCS TOP), American Embassy, Tokyo, Unit 45004, APO
Ap 96337, Refer to TC356.. (0110) Loren Data Corp. http://www.ld.com (SYN# 0480 19950421\99-0001.SOL)
99 - Miscellaneous Index Page
|
|