COMMERCE BUSINESS DAILY ISSUE OF APRIL 24,1995 PSA#1331U.S. ARMY CORPS OF ENGINEERS, PORTLAND DISTRICT, P.O. BOX 2946,
PORTLAND OREGON 97208-2946 Y -- BONNEVILLE FISH HATCHERY WELLS, FOLLOW-ON SOL DACW57-95-B-0045
DUE 061395 POC CONTRACT SPECIALIST, LESLIE CONKLIN, (503) 326-6418
Provide water level indication and modify existing pressure control
valves to flow control for seven hatchery wells. Provide flow meter
station on hatchery main feeder pipe, South shore. Contractor required
to commence work under this contract within 10 calendar days after the
Contractor receives Notice to Proceed, to prosecute the work diligently
and to complete the entire work not later than 60 calendar days after
receipt of Notice to Proceed. The time stated for completion includes
final cleanup of the premises. All work requiring shut down of hatchery
well(s) or pipeline shall be completed prior to hatchery well start-up
on August 23, 1995. Estimated amount between $25,000 and $100,000. IFB
available on or about May 12, 1995 at the cost of $25.00 a set. This
procurement is open to both large and small business concerns. The size
standard for which is a concern, including all affiliates, with average
annual sales or receipts for the preceeding three years not in excess
of $13.5 million. All responsible sourcese may submit a bid which will
be considered by the agency. Please indicate business size when
requesting bid documents. SIC 1629(0110) Loren Data Corp. http://www.ld.com (SYN# 0151 19950421\Y-0012.SOL)
Y - Construction of Structures and Facilities Index Page
|
|