COMMERCE BUSINESS DAILY ISSUE OF MAY 1,1995 PSA#1336Department of the Army, Baltimore District, Corps of Engineers, P.O.
Box 1715, Baltimore, MD 21203-1715 Z -- REMEDIATION OF EAST RETAINING WALL, SPILLWAY APPROACH CHANNEL,
WHITNEY POINT DAM, NEW YORK SOL DACW31-95-B-0077 DUE 061595 POC Carol
Williams or Marie Johnson (410) 962-3464 or 962-5638 Remediation of
East Retaining Wall, Spillway Approach Channel, WHitney Point Dam, New
York. Est cost is between $100,000 and $250,000. Completion no later
than 181 calendar days. Construction consists of wall stabilization
using anchors, steel bearing plates, grout pads, rock bolts and
concrete work. Specs only $10.44. Make company check or money order
payable to FAO, USAED, Baltimore. Non-Refundable. (No cash accepted).
Contractors are encouraged to provide their Federal Express or UPS
account number at the time of request or have them pick up. Issuance
o/a 15 May 1995. Note: This procurement is unrestricted. (0117) Loren Data Corp. http://www.ld.com (SYN# 0154 19950428\Z-0029.SOL)