COMMERCE BUSINESS DAILY ISSUE OF MAY 5,1995 PSA#1340U. S. Army Corps of Engineers, Omaha District, 215 North 17th Street,
Omaha, NE 68102-4978 Y -- REHAB PIPING SHALE DRAINAGE GALLERY, OAHE DAM-LAKE OAHE, SOUTH
DAKOTA SOL DACW45-95-B-0073 DUE 062095 POC Contact Contracting Division
at: (402)221-4266. The work will include the following: (Approx.
quantities) Cleaning (Red-lead paint removal and disposal) and painting
of 630 LF of 20 inch diameter header pipe and 250 LF of 6 inch pipe
located adjacent to the Oahe Power Plant. The estimated construction
cost of this project is between $100,000 and $250,000. Contractor's
Quality Control will be a requirement in this contract. The Contractor
will be required to commence work within 10 days after notice to
proceed and complete the work 120 calendar days after receipt of Notice
to Proceed. Provisions will be included for liquidated damages in case
of failure to complete the work in the time allowed. Performance and
payment bonds will be required. Bid sets will be available on/a May 16,
1995. Half-size plans and specifications will be furnished upon
request. All requests for solicitation packages should be made in
writing no later than 14 days prior to bid opening. After such time,
packages will be furnished if supply is available. It has been
determined that the number of sets be limited to 2 (two) per firm
(additional copies will be the responsibility of the requestor). Please
list street address (for parcel del service) and mailing address.
SPECIAL NOTES: All responders are advised that this requirement may be
cancelled or revised at any time during the solicitation, selection,
selection evaluation, negotiation and/or final award structure and
disposition of US Armed Forces. Small & Disadvantaged Businesses are
encouraged to participate & will be used to maximum extent practicable
as both prime & subcontractor. (0123) Loren Data Corp. http://www.ld.com (SYN# 0193 19950504\Y-0009.SOL)
Y - Construction of Structures and Facilities Index Page
|
|