COMMERCE BUSINESS DAILY ISSUE OF MAY 18,1995 PSA#1349Officer in Charge of NAVFAC Contracts; P. O. Box 54306; NAS Memphis;
Millington, TN 38054-0306 Z -- INDEFINITE QUANTITY CONSTRUCTION, INTERIOR AND EXTERIOR PAINTING
OF VARIOUS BUILDINGS AT NAS MEMPHIS MILLINGTON, TN Sol.
N62467-95-B-5274. Due 070595. Contact, Dolores Quinton, 901/873-5061;
Contracting Officer, Gary Busby, 901/873-5061. Furnish all labor,
tools, equiment, transportation and supervision necessary to provide
the preparation of surfaces for, and the interior and exterior painting
of portions of various buildings, all as designated by Delivery Orders
that will be issued to the Contractor. In addition to the normal
surface preparation requird for painting, preparation of surfaces shall
also include: the replacement of rotted or otherwise deteriorated or
missing wood such as faxcia boards, corner boards, window and door
trim, etc., where these items are to be painted; replacing broken,
missing, or damaged exterior siding where items are to be painted; and
patching surfaces to be painted such as concrete, concrete block,
plaster, and wallboard. The Contractor will be required to remove and
replace all building screens, window guards, storm windows, removable
signs and building numbers, unless directed otherwise, (when these
items occur over surfaces to be painted). All building signs and
numbers that are painted on structures are to remain intact and no
repainting of these signs and numbers is required. This work will also
include the surface preparation and painting of nonfriable cement
asbestos shingle siding. This contract also includes the requirement to
provide new cement asbestos siding shingles to replace missing cement
asbestos siding shingles. However, removal of damaged/deteriorated
cement asbestos siding shingles is not a part of this contract. The
removal of damaged/deteriorated cement asbestos siding shingles will be
accomplished by others. The voids where siding shingles have been
removed will be considered ``missing siding shingles'' and providing
new cement asbestos siding shingles for these areas is a part of this
contract. Time for completion is 12 months. This project is a firm
fixed price construction project. Cost estimate is between $100,000.00
and $250,000.00. Solicitation will issue on or about June 1, 1995.
(135) Loren Data Corp. http://www.ld.com (SYN# 0150 19950517\Z-0010.SOL)