COMMERCE BUSINESS DAILY ISSUE OF MAY 22,1995 PSA#1351Commanding Officer, Southwest Division, Naval Facilities Engineering
Command, Code 0211, 1220 Pacific Highway, Room 145, San Diego, CA
92132-5187 C -- A-E SERVICES FOR FY 1996 DFSC PROJECTS NOR 96-1, 96-2, 96-3,
96-4, 96-5, 96-6 AND 96-7, EVALUATE/REPAIR DIKE PIPING FOR SEVEN TANK
LOCATIONS AT DEFENSE FUEL SUPPLY POINT, NORWALK, CALIFORNIA SOL
N68711-95-C-7671 DUE 062795 POC Anne Garrett/Contract Specialist, (619)
532-3708, Nancy J. Trent/Contracting Officer, (619) 532-2853.
Architect-Engineer services are required for the design and preparation
of plans and specifications for the purpose of bidding and construction
for evaluation and repair of the dike piping at seven tank locations at
the Defense Fuel Supply Point, Norwalk, California. The projects are to
repair the tank suction and fill lines to relieve stresses induced by
solar heating and hydraulic action during product transfers. Dike
manifold piping shall be repaired to relieve stresses induced by
out-of-alignment piping. All contract documents will be required to be
in metric measurement. The estimated start date is July 1995. The
estimated completion date is April 1997. The contract will be
negotiated and awarded for design services with an option for
Post-Construction Award Services (PCAS). Authority to award design is
available at this time. The estimated construction cost is between
$500,000 and $1,000,000. A-E Selection criteria will include (in order
of importance): (1) Recent specialized experience of the firm
(including consultants) in the design of aviation fuel distribution
systems including relief of stresses induced by solar heating and
hydraulic action during product transfers. Do not list more than a
total of 10 projects in block 8. Include point of contact name and
telephone number in block 8c for each project listed. Indicate which
consultants from the proposed team, if any, participated in the design
of each project. (2) Professional qualifications of the staff to be
assigned to this project in the design of aviation fuel distribution
systems including relief of stresses induced by solar heating and
hydraulic action during product transfers. List only the team members
who actually will perform major tasks under this project,
qualifications should reflect the individual's potential contributions
to this project. (3) Past performance on contracts with government
agencies and private industry in terms of cost control, quality of work
and compliance with performance schedules. Indicate by briefly
describing internal quality assurance and cost control procedures and
indicate team members who are responsible for monitoring these
processes. List recent awards, commendations and other performance
evaluations (do not submit copies). (4) Location in the general
geographic area of the project and knowledge of the locality of the
project, provided that the application of this criterion leaves an
appropriate number of firms given the nature and size of this project.
(5) Capacity to accomplish the work in the required time. Indicate the
firms present workload and the availability of the project team
(including consultants) for the specified contract performance period
and indicate specialized equipment available and prior security
clearances. (6) List the small or disadvantaged or woman- owned
business firms used as primary consultants or as subconsultants. If a
large business concern is selected for this contract, they will be
required to submit a subcontracting plan that should reflect a minimum
5% Small Disadvantaged Business of the amount to be subcontracted out.
Those firms which meet the requirements described in this announcement
and wish to be considered, must submit one copy each of a SF 254 and
a SF 255 for the firm and a SF 254 for each consultant listed in block
6 of the firms SF 255. One copy of the submittal package is to be
received in this office no later than 3:00 P.M. Pacific Time on the due
date indicated above. Should the due date fall on a weekend or holiday,
the submittal package will be due the first workday there after.
Submittals received after this date and time will not be considered.
Additional information requested of applying firms: indicate
solicitation number in block 2b, CEC (Contractor Establishment Code)
and/or Duns number (for the address listed in block 3) and TIN number
in block 3, telefax number (if any) in block 3a and discuss why the
firm is especially qualified based on the selection criteria in block
10 of the SF 255. For firms applying with multiple offices, indicate
the office which completed each of the projects listed in block 8 and
list which office is under contract for any contracts listed in block
9. Use block 10 of the SF 255 to provide any additional information
desired. Personal interviews may not be scheduled prior to selection of
the most highly qualified firm. SF 255's shall not exceed 30 printed
pages (double sided is two pages/organizational charts and photographs
excluded, exception: photographs with text will be considered as a
page). All information must be included on the SF 255 (cover letter,
other attachments and pages in excess of the 30 page limit will not be
included in the evaluation process). Firms not providing the requested
information in the format (i.e. listing more than a total of 10
projects in block 8, not providing a brief description of the quality
control plan, not listing which office of multiple office firms
completed projects listed in block 8, etc.) directed by this synopsis
may be negatively evaluated under selection criteria (3). Firms, their
subsidiaries or affiliates, which design or prepare specifications for
a construction contract or procurement of supplies cannot provide the
construction or supplies. This limitation also applies to subsidiaries
and affiliates of the firm. This is not a request for proposal.
Telegraphic and facsimile SF 255's will not be accepted. Site visits
will not be arranged during the submittal period. See Numbered Note(s):
24. (0138) Loren Data Corp. http://www.ld.com (SYN# 0022 19950519\C-0006.SOL)
C - Architect and Engineering Services - Construction Index Page
|
|