COMMERCE BUSINESS DAILY ISSUE OF JUNE 8,1995 PSA#1363Contract Division, General Affairs Department, Kanto, Regional
Construction Bureau, Ministry of Construction, 1-3-1 Otemachi,
Chiyoda-Ku, Tokyo 100, Japan Y -- JAPAN: S16 CONSTRUCTION POC Tel 81/3/3211-6261 FAX NOT AVAILABLE.
product data a industry sector code: B detailed product description:
Construction Title: phase-32 Construction of superstructure of the
sakitama bridge; site: niikura-chisaki, wako-Shi, saitama-Ken; summary:
three-span continuous, steel floor slab girder bridge: one set, 285
meters for the ''up'' route, span length of 85.5 + 114.0 + 85.5 meters;
Construction period: approx. 20 months (610 days); main materials to be
used: steel, approx. 1,500 tons. C product specifications/technical
data: not available. D quantity: not available. E U.S. dollar value:
not available. F other information: not available. Response data a
response language: Japanese. B best way to respond: letter. C from
manufacturers only: not available. D information desired from U.S.
firm: not available. E primary buying factor: the lowest bid within the
estimated price range. F other information: pre-screening is required
to be eligible for bidding. Pre-screening deadline: 17:30 pm, June 12,
1995. Bid documents must be obtained directly from the procuring
agency, not from U.S. Embassy. Payment in yen. A issuing agency: Kanto
Regional Construction Bureau, Ministry of Construction B financing
agency: same as above. C price of bid documents: not available. D
purchase bid documents by: 16:30 pm, July 13, 1995. E Tender number
required in all communications: not available. F performance bonds
required: not required. G closed procurement procedure: no. H bidding
procedures: open competitive Tender. I bid deadline: 13:00 pm, July 24,
1995. J other information: ''kensetsu kogyo shimbun'': 6/2/95. Eligible
Tender participants must be: 1) firms that do not fall under articles
70 and 71 of the cabinet order concerning budget, auditing, and
Accounting; 2) firms pre- qualified for open competitive bidding on
steel bridge superstructure work by the Kanto Regional Construction
Bureau; 3) firms not undergoing bankruptcy procedures; 4) firms that
have -- since April 1, 1990 as the main contractor -- manufactured and
constructed a project that meets the following (a) to (e) criteria: a)
highway bridge (of at least tl-20) or railway bridge; B) steel bridge,
other than steel plate girder bridge and simple box girder bridge; C)
span length of at least 55 meters; D) project size of at least 900
tons; and e) launched Construction, or cantilever erection using a
traveling crane (the above criteria should refer to the same project).
Note: only Construction projects in which bidders have had a 20
percent or greater share are eligible for consideration; 5) firms that
can assign during the on-site Construction period a full-time chief
engineer or engineering supervisor who meets the following criteria: a)
is qualified as a certified First-class Construction supervisor or
equivalent or higher; B) has -- since April 1, 1985 as the main
contractor -- had experience with Construction of a project as
described in item (4) above; and C) in the case of engineering
supervisor, is qualified to supervise designated Construction work; 6)
firms not currently suspended from designation by the director of the
Kanto Regional Construction Bureau; and 7) firms not related by
capital or personnel to the contractors involved in this project. Post
remarks Post contact/prepared by haomori approved by gtaevs Please
send a copy of your response to: Commercial Officer (FCS TOP), American
Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to TC410. Please note:
All correspondence with the Awarding Authority and/or the Procuring
Agency MUST be in Japanese.. (0157) Loren Data Corp. http://www.ld.com (SYN# 0128 19950607\Y-0011.SOL)