COMMERCE BUSINESS DAILY ISSUE OF JUNE 13,1995 PSA#1366NASA, Johnson Space Center, BJ32, Houston, TX Y -- REPAIR ROOF - BUILDING 11 SOL 9BJ3T20518B POC CHARLES BELL,
Tel:713-483-6811 Contracting Officer:ROD ETCHBERGER, Tel:713-483-8530
This project provides for the removal of the existing aggregate,
built-up roofing material, underlying insulation board, and the entire
lightweight insulating fill deck above the existing metal deck. Upon
completion of this effort, the Contractor will install a new
lightweight insulating fill deck, a mechanically fastened base sheet,
2-ply vapor barrior, layer of rigid insulation board, 4-ply built-up
roofing, roof aggregate, and associated flashing. In addition, prior to
commencement of any roofing work, the contractor will install a
''black-iron'' support system above the existing layin ceiling in
Building 11 for the purpose of supporting the existing lighting,
mechanical, and lay-in ceiling systems. Total construction cost for
this project is estimated to between $200,000 to $500,000. The period
of performance is 95 days. Bid documents may be purchased from
Ridgeway, Inc., Attn: Bill Dement, 5711 Hillcroft, Houston, TX 77036,
713-787-1265. Bid documents may be viewed at Industry Assistance,
Building 111, NASA JSC, phone 713-483-4511 (0160) Loren Data Corp. http://www.ld.com (SYN# 0128 19950612\Y-0014.SOL)
Y - Construction of Structures and Facilities Index Page
|
|