COMMERCE BUSINESS DAILY ISSUE OF JUNE 14,1995 PSA#1367International Boundary & Water Commission, United States Section, The
Commons, Building C, Suite 310, 4171 N. Mesa, El Paso, TX 79902-1441 Y -- RIO GRANDE AMERICAN CANAL EXTENSION (RGACE) - REACH C AND REACH
E SOL IFB 95-07. DUE 073195. Contact Delfina C. Lechuga, Contracting
Officer, or Maria C. Smith, Contract Specialist at (915) 534-6682. The
International Boundary and Water Commission, United States Section,
requires the furnishing of labor, materials, and equipment for the
construction of Reach C and E of the Rio Grande American Canal
Extension (RGACE) project located in El Paso, El Paso county, TX. Reach
C consists of approximately 5 miles of new canal extension. Reach E
consists of approximately 1.5 miles of canal reconstruction. The RGACE
will be located adjacent to the Rio Grande on U.S. Government property
on the landside of the U.S. levee. The RGACE is part of an overall
project which involves the construction of approximately 12 miles of a
concrete-lined extension and approximately 3 miles of Franklin Canal
reconstruction. Contracts have previously been awarded for 7 of the 12
miles of canal extension. The purpose of the facility will be to
ultimately provide a more equitable distribution of waters between the
United States and Mexico and reduce water losses. Reach C begins in
the area adjacent to the Yarbrough Drive overpass and ends at the
Riverside Canal, a length of approximately 5 miles. This portion of the
project includes the construction of a reinforced concrete-lined
trapezoidal canal section, concrete check structures, turnouts, a
wasteway, an outlet structure, relocation of the Playa Lateral and the
Playa Interceptor Drain and structures, box culvert installation,
canal transitions, demolition of small canal structures, placement of
riprap, placement of levee gravel surfacing and seeding of canal slopes
and other disturbed areas. The Rio Grande may be used as the borrow
source for the embankment fill material for Reach C. Reach E begins in
the area of the Leon Street Wasteway and ends at the 2nd Street
culvert and is approximately 1.5 miles long. This portion of the canal
extension includes demolition of existing concrete trapezoidal canal
section and reconstruction of a new reinforced concrete trapezoidal
canal extenson, canal transitions, a turnout, chain link fence salvage
and demolition, small metering bridge, placement of levee gravel
surfacing and seeding of canal slopes and other disturbed areas.
Tentative dates for issuing and closing IFB 95-07 are July 31, 1995 and
August 30, 1995, respectively. The work under this contract is to be
completed within 630 calendar days. The estimated price range for
construction of the RGACE - Reach C and E is over $10,000,000.00. Plans
and specifications will be available for inspection, without charge, at
the International Boundary and Water Commission, U.S. Section, The
Commons, Building C, Suite 224, 4171 North Mesa Street, El Paso, Texas
79902-1441. Requests for IFB 95-07 should be submitted in writing by
July 7, 1995 to the International Boundary and Water Commission, U.S.
Section, Attn: Maria C. Smith, at the preceding address. An amount of
$60.00, nonrefundable, will be charged for each set of solicitation
documents. Recipients of the IFB that do not submit a bid should advise
the issuing office as to their desire to remain on the mailing list for
receipt of future solicitation notices. (158) Loren Data Corp. http://www.ld.com (SYN# 0139 19950613\Y-0002.SOL)
Y - Construction of Structures and Facilities Index Page
|
|