|
COMMERCE BUSINESS DAILY ISSUE OF JUNE 29,1995 PSA#1378Commanding Officer, Offshore Facilities Contracts Branch, Naval
Facilities Engineering Command Contracts Office, 901 M Street, SE,
Building 218, Washington, DC 20374-5063 99 -- D-9 MOORING INSTALLATION, NAVAL INACTIVE SHIP MAINTENANCE
FACILITY, MIDDLE LOCK, PEARL HARBOR, HAWAII SOL N47408-95-B-4048 DUE
081795 POC Ms. Linda Dearing, Contract Specialist, (202) 433-5311 or
FAX (202) 433-5244; Contracting Officer, Corrine A. Pearson This
project will be UNRESTRICTED. This office seeks a qualified contractor
to install a mooring in Middle Loch for the Naval Inactive Ship's
Maintenance Facility Pearl Harbor (NISMF PH), Hawaii. The contractor
shall supply all labor, construction materials and equipment as
required to accomplish the above task. Permanent materials for the
mooring shall mostly be supplied by the Government. Permanent materials
to be supplied by the Government include all required mooring chain,
shackles, chain joining links, plate anchors, concrete sinkers, wire
rope pennants, pick-up buoy pennants and buoys. Miscellaneous wire rope
and wire rope clips for the mooring will be required to be provided by
the contractor. Staging areas for Government materials are provided at
the NISMF PH site. The contractor will be required to install a mooring
system comprised of 12 driven plate anchors, complete with mooring
chain, sinkers, buoys and zinc anodes. Zinc anodes have already been
installed on the required mooring chains by the Government. The
contractor will be required to spud each anchor location to determine
the thickness of the upper soft silt layer and the depth of the
underlying stiff clay alluvium. Based on the spud results, a large
''mud'' plate anchor or a small ''clay'' anchor will be selected. If
selected, the clay anchor shall be driven to a tip depth of 30 feet
into the stiff clay alluvium. The mud anchor will be driven into the
soft upper silt layer to a tip depth of 70 feet. If the stiff clay
alluvium is reached prior to achieving a tip depth of 70 feet in mud,
then the mud anchor shall be driven a distance of 14 feet into the
alluvium. All plate anchors will be horizontally pull tested to
approximately 200,000 pounds after installation. Complete assembly and
deployment of each mooring leg is required. A mooring buoy of a
pick-up buoy shall be attached to each mooring leg as required. At the
contractor's option, the Government can provide selected steel
sections that can be used to fabricate a follower or a spud in an ''as
is'' condition. All work must be accomplished within 115 days after
award of contract. The contract will be firm-fixed priced with award
anticipated in September 1995. The estimated cost range is between
$500,000.00 and $1,000,000.00. Bids should be submitted to the Naval
Facilities Engineering Command Contracts Office, 901 M Street SE, Bldg.
218, Washington, D.C. 20374-5063. Bid opening will be on/or about 17
August 1995 at 1400 Eastern Standard Time at the Naval Facilities
Engineering Command Contracts Office (Conference Room), 901 M Street
SE, Bldg. 218 (Third Floor), Washington, D.C. Due to the critical
nature of the project, the apparent low bidder shall be requested,
within 7 calendar days of bid opening, to provide
qualification/experience information on successfully completed projects
for similar work, in addition to other information to determine the
firm's responsibility. (0178) Loren Data Corp. http://www.ld.com (SYN# 0505 19950628\99-0001.SOL)
99 - Miscellaneous Index Page
|
|