Construction Title: phase-one Construction of the takanomine tunnel on
the hokuriku expressway; site: from oaza-taya to oaza-nakahama,
itoigawa-Shi, Niigata-ken; summary: this Project involves civil
engineering work of 1,657 meters in length, including tunneling from
the West side (one site, 1,578 meters) for the 3,129 meter-long
takanomine tunnel (soil excavation volume, approx. 93,000 cubic
meters), superstructure work for a bridge (one site, 16 meters), and
culvert box (one site); length, 1,657 meters; width: earth work
portion, 11.00 meters X 1; bridge portion, 9.75 meters X 1; tunnel
portion, 8.50 meters X 1; earth work volume, 93,000 cubic meters;
tunnel: one site, 1,578 meters; bridges, etc.: Superstructure work
only, one site, 16 meters; cross structure: culvert box, one site; main
Materials to be used: concrete, 15,700 cubic meters; reinforcing steel,
80 tons; rock bolts, 26,200 pieces; steel arch support, 1,500 sets;
Construction period: 870 days (winter recess for earth work: jan. 5 to
mar. 5). C product specifications/technical data: N/a (not available).
D quantity: N/A. e U.S. dollar value: N/A. F other information: N/A.
response data a response language: Japanese. B best Way to respond:
letter. C from manufacturers only: N/A. D information desired from U.S.
firm: N/A. e primary buying factor: the lowest bid within the estimated
price range. F other information: pre-screening is required to be
eligible for bidding. Pre-screening deadline: 16:00 pm, aug. 18, 1995.
Bid documents must be obtained directly from the procuring agency, not
from U.S. Embassy. Payment in yen. A issuing agency: Niigata
Construction Bureau (Japan Highway Public Corporation) B financing
agency: same as above. C price of bid documents: N/A. D purchase bid
documents by: 16:00 pm, aug. 18, 1995. E tender number required in all
Communications: N/A. F performance bonds required: not required. G
closed Procurement procedure: no. H bidding procedures: open
competitive tender. I bid deadline: 13:30 pm, sep. 29, 1995. J other
information: '' kensetsu kogyo shimbun'': 7/11/95. Eligible tender
participants: firms qualified to participate in bidding for this
Project must meet all of the following criteria and have their
qualification for this Project screened and confirmed by the Director
of the Niigata Construction Bureau: 1) firms that Do not fall under
article 4 of the Contract regulations of the Japan Highway Public
Corporation; 2) consortia comprised of two pre-qualified firms having
a score of at least 1,500 points in civil engineering work; 3) firms
that have -- since 1985 (in the past 10 years), as the main contractor
-- actually constructed a tunnel of at least 1.0 kilometer in length
and 50 square meters in inner Section area, using the natm method.
Note: only Construction projects in which bidders have had a 20 percent
or greater share of involvement are eligible for consideration; 4)
firms that can assign, to the Construction site, a field representative
or a full-time chief engineer or engineering supervisor who has
constructed a tunnel, using the natm method, since 1985 (in the past 10
years), as field representative or full-time chief engineer or
engineering supervisor; 5) firms not suspended from designation in no.
3 zone by the Japan Highway Public Corporation; 6) firms that can
present an adequate plan for tunneling work; 7) every consortium member
firm must meet the following criteria: a) has been in operation for at
least five years in qualified business under the Construction business
law; B) can assign -- to the Construction site, on a full-time basis --
an engineering supervisor qualified for this Project under the
Construction business law or a nationally-licensed chief engineer; and
C) has an at least 30 percent share of involvement, and the
representative firm must have the greatest share. Firms pre-screened by
the Construction minister regarding items (a) and (B) in evaluation of
their management operations are exempted from these criteria; and 8)
firms not related by capital or personnel to the contractors involved
in this Project. Post remarks Post contact/prepared by haomori approved
by cdukelow Please send a copy of your response to: Commercial Officer
(FCS TOP), American Embassy, Tokyo, Unit 45004, APO Ap 96337, Refer to
TC460. Please note: All correspondence with the Awarding Authority
and/or the Procuring Agency MUST be in Japanese.. (0195) Loren Data Corp. http://www.ld.com (SYN# 0143 19950717\Y-0005.SOL)
Y - Construction of Structures and Facilities Index Page
|
|