Loren Data Corp.

'

 
 

COMMERCE BUSINESS DAILY ISSUE OF JULY 21,1995 PSA#1393

Arnold Engineering Development Center, ATTN: AEDC PKP, 100 Kindel Drive, Suite A332, Arnold AFB, TN 37389-1332

59 -- REPLACE MAIN SUBSTATION CIRCUIT BREAKERS SOL F40650-95-B-0076 DUE 090695 POC Emily H. Walker, Contract Specialist, (615)454-5174, W. Richard Stewart, Contracting Officer. The purpose of this procurement is to purchase and install three new 161-kv sulphur hexafluoride (SF6) circuit breakers to replace existing oil circuit breakers 904,914, and 944 at the Main Substation. Delivery to Arnold AS TN shall be 280 days after contract award. Any responsible source may submit a bid that will be considered. Firms responding to this synopsis should do so in writing within 15 days after this publication. Please indicate if you are a small or small disavantaged business concern. (0200)

Loren Data Corp. http://www.ld.com (SYN# 0403 19950720\59-0014.SOL)


59 - Electrical and Electronic Equipment Components Index Page